MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) 2024-04-26
[Table view] Category:License-Application for Combined License (COL) (Amend/Renewal) DKT 52
MONTHYEARNL-24-0217, License Amendment Request: Source Range Neutron Flux Doubling Function Applicability2024-11-0101 November 2024 License Amendment Request: Source Range Neutron Flux Doubling Function Applicability NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements NL-24-0128, License Amendment Request: Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) Testing Frequency2024-04-0404 April 2024 License Amendment Request: Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) Testing Frequency NL-23-0742, To Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fo Surveillance Technical Specifications2023-09-20020 September 2023 To Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fo Surveillance Technical Specifications NL-23-0346, License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007)2023-05-25025 May 2023 License Amendment Request for Exception to Regulatory Guide 1.163 (LAR 23-007) NL-23-0385, License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1)2023-05-17017 May 2023 License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 (LAR-23-006R1) ML23088A1382023-05-0404 May 2023 Enclosure 9 - Attachment to License Amendment No. 189 for COL No. NPF-91 ML23088A1372023-05-0404 May 2023 Enclosure 8 - Attachment to License Amendment No. 124 for COL No. NPF-92 ML23088A1362023-05-0404 May 2023 Enclosure 7 - Attachment to License Amendment No. 181 for COL No. NPF-92 ML23088A1352023-05-0404 May 2023 Enclosure 6 - Attachment to License Amendment No. 166 for COL No. NPF-92 ML23088A1342023-05-0404 May 2023 Enclosure 5 - Attachment to License Amendment No. 188 for COL No. NPF-91 ML23045A1802023-05-0404 May 2023 Enclosure 4 - Attachment to License Amendment No. 147 for COL No. NPF-92 ML23045A1792023-05-0404 May 2023 Enclosure 3 - Attachment to License Amendment No. 148 for COL No. NPF-91 ML23045A1782023-05-0404 May 2023 Enclosure 2 - Attachment to License Amendment No. 117 for COL No. NPF-92 ML23045A1772023-05-0404 May 2023 Enclosure 1 - Attachment to License Amendment No. 118 for COL No. NPF-91 NL-23-0135, License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005)2023-04-17017 April 2023 License Amendment Request: Timing of Technical Specifications Effectiveness Prior to Initial Criticality (LAR-23-005) NL-23-0132, License Amendment Request: Remove Combined License Appendix C (LAR 23-001)2023-04-0404 April 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-001) NL-23-0193, Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003)2023-03-24024 March 2023 Request for License Amendment: Relocation of TS 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) ML23039A1672023-02-0808 February 2023 Draft LAR to Remove Tier 1 and Tier 2 Star Requirements NL-23-0076, Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004)2023-01-31031 January 2023 Exigent License Amendment Request: Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality (LAR-23-004) NL-23-0020, Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality2023-01-12012 January 2023 Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality ND-22-0881, License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002)2023-01-0303 January 2023 License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002) ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ML22284A1312022-11-22022 November 2022 LAR-22-003 U4 Electrical ITAAC Consolidation Amendment No. 187 ML22307A0072022-11-0202 November 2022 Draft LAR for TS 3.8.3 Inverters Operating Completion Time Extension ND-22-0709, Request for License Amendment and Exemption Electrical Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Optimization (LAR-22-003)2022-09-0202 September 2022 Request for License Amendment and Exemption Electrical Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Optimization (LAR-22-003) ML22087A0682022-03-31031 March 2022 Draft LAR 22-001, Unit 4 Security ITAAC for 3-31-22 Public Meeting with SNC ND-21-0772, Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001)2021-08-24024 August 2021 Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001) ML21230A0162021-08-19019 August 2021 Invessel As-built ITAAC Draft LAR 21-001 for 210819 Psm ML20196L6762020-08-11011 August 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 3 for LAR 20-002 ML20132A0522020-08-0303 August 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ND-20-0725, Plants Units 3 and 4, Revision to License Amendment Request: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation2020-06-22022 June 2020 Plants Units 3 and 4, Revision to License Amendment Request: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation ND-20-0668, Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005)2020-06-19019 June 2020 Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005) ND-20-0464, Request for License Amendment: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation2020-05-0707 May 2020 Request for License Amendment: Technical Specification 3.3.13 for Main Control Room Emergency Habitability System (Ves) Instrumentation Applicability Change and Include Undervoltage Actuation ND-20-0504, Transmittal of Section 404 Permit Modification Request2020-05-0404 May 2020 Transmittal of Section 404 Permit Modification Request ND-20-0507, Request for License Amendment: Core Makeup Tank Boron Concentration Requirements (LAR-20-004)2020-04-30030 April 2020 Request for License Amendment: Core Makeup Tank Boron Concentration Requirements (LAR-20-004) ND-20-0289, Transmittal of NPDES Permit Renewal Application2020-03-31031 March 2020 Transmittal of NPDES Permit Renewal Application ND-20-0266, Revised Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019R1)2020-03-20020 March 2020 Revised Request for License Amendment: Reconciliation of Environmental Conditions Inputs to Civil Structural Design Licensing Basis (LAR-19-019R1) ND-20-0122, Request for License Amendment: Main Control Room Emergency Habitability System (Ves) Pressure Regulating Valve and Source Range Neutron Flux Doubling Surveillance Changes, and Other Miscellaneous.2020-02-28028 February 2020 Request for License Amendment: Main Control Room Emergency Habitability System (Ves) Pressure Regulating Valve and Source Range Neutron Flux Doubling Surveillance Changes, and Other Miscellaneous. ND-20-0075, Request for License Amendment and Exemption: Unit 3 Auxiliary Building Wall 11 Seismic Gap Requirements (LAR-20-001)2020-02-0707 February 2020 Request for License Amendment and Exemption: Unit 3 Auxiliary Building Wall 11 Seismic Gap Requirements (LAR-20-001) ND-20-0092, Revision to Request for License Amendment: Removal of the Preoperational Passive Residual Heat Removal Heat Exchanger Natural Circulation Test (LAR-19-017R1)2020-01-31031 January 2020 Revision to Request for License Amendment: Removal of the Preoperational Passive Residual Heat Removal Heat Exchanger Natural Circulation Test (LAR-19-017R1) ND-19-1388, Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014)2019-11-13013 November 2019 Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014) ND-19-1292, Proposed Changes to the Licensing Basis Documents (LAR-19-018)2019-10-31031 October 2019 Proposed Changes to the Licensing Basis Documents (LAR-19-018) ND-19-1314, Second Preliminary Amendment Request (Par): Reinforcement Changes for Wall L (PAR-19-016-2)2019-10-25025 October 2019 Second Preliminary Amendment Request (Par): Reinforcement Changes for Wall L (PAR-19-016-2) ND-19-1313, Revision to Request for License Amendment: Reinforcement Changes for Wall L and Wall 7.3 (LAR-19-016R1)2019-10-25025 October 2019 Revision to Request for License Amendment: Reinforcement Changes for Wall L and Wall 7.3 (LAR-19-016R1) ML19262F8552019-10-22022 October 2019 Attachment - Vogtle Electric Generating Plant, Unit 3 Amendment 165 (LAR-19-006) ML19262F8562019-10-22022 October 2019 License Amendment - Vogtle Electric Generating Plant, Unit 4 (LAR 19-006) ML19262F8572019-10-22022 October 2019 Attachment - Vogtle Electric Generating Plant, Unit 4 Amendment 163 (LAR-19-006) ND-19-1142, Request for License Amendment and Exemption: Automatic Depressurization System (ADS) and Core Makeup Tank (Cmt) Design Parameters (LAR-19-009)2019-09-30030 September 2019 Request for License Amendment and Exemption: Automatic Depressurization System (ADS) and Core Makeup Tank (Cmt) Design Parameters (LAR-19-009) 2024-07-25
[Table view] |
Text
B. H. Whitley Southern Nuclear Director Operating Company, Inc.
Regulatory Affairs 3535 Colonnade Parkway Birmingham, AL 35243 Tel 205.992.7079 November 29, 2018 Docket Nos.: 52-025 52-026 ND-18-1476 10 CFR 50.90 10 CFR 52.98 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Preliminary Amendment Request (PAR):
Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling (PAR-18-028)
Ladies and Gentlemen:
The U.S. Nuclear Regulatory Commission (NRC) issued the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 combined licenses (COL) (License Nos. NPF-91 and NPF-92) to Southern Nuclear Operating Company (SNC) on February 10, 2012.
By SNC letter ND-18-1408, dated November 16, 2018, SNC submitted License Amendment Request (LAR), LAR-18-028 (ADAMS Accession Number ML18320A225), to revise information in the VEGP Units 3 and 4 licensing basis documents. The LAR proposes to change the routing of Class 1E divisional cables supporting passive containment cooling.
SNC is submitting this Preliminary Amendment Request (PAR), PAR-18-028, to minimize construction delays for VEGP Units 3 and 4 during the NRCs evaluation of the related LAR. The determination of whether the NRC has any objection to SNC proceeding with construction based on the proposed licensing basis changes identified in the LAR is requested on or before January 7, 2019. Delayed determination regarding this PAR could result in delay of the completion of installation of divisional cable raceway and the associated cables in rooms affected by the LAR.
A description of the proposed change and the reason for the change are contained in the Enclosure to this letter. This PAR has been developed in accordance with guidance provided in the most recent revision to the Interim Staff Guidance on Changes during Construction Under 10 CFR Part 52, COL-ISG-25 [ADAMS Accession Number ML15058A377] and corresponds accurately and technically with the above-mentioned LAR-18-028. The technical scope of this PAR is consistent with the subject LAR. Section 7 of the Enclosure further identifies and details the scope of the no objection finding sought in this PAR.
U.S. Nuclear Regulatory Commission ND-18-1476 Page 2 of 4 This letter does not contain any NRC commitments. This letter has been reviewed and confirmed to not contain security-related information.
Should you have any questions, please contact Ms. Amy Chamberlain at (205) 992-6361.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 291h of November 2018.
Respectfully submitted, Director, Regulatory Affairs Southern Nuclear Operating Company
Enclosure:
Vogtle Electric Generating Plant (VEGP) Units 3 and 4 - Preliminary Amendment Request: Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling (PAR-18-028)
U.S. Nuclear Regulatory Commission ND-18-1476 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)
Mr. D. G. Bost (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones (w/o enclosures)
Mr. J. B. Klecha Mr. G. Chick Mr. D. L. McKinney (w/o enclosures)
Mr. T. W. Yelverton (w/o enclosures)
Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. A. G. Aughtman Mr. D. L. Fulton Mr. M. J. Yox Mr. C. T. Defnall Mr. J. Tupik Mr. W. A. Sparkman Ms. A. C. Chamberlain Ms. A. L. Pugh Mr. E. Riffle Ms. K. Roberts Document Services RTYPE: VND.LI.L00 File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosures)
Ms. J. Dixon-Herrity Mr. C. Patel Ms. J. M. Heisserer Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. C. J. Even Mr. A. Lerch Mr. S. Walker State of Georgia Mr. R. Dunn
U.S. Nuclear Regulatory Commission ND-18-1476 Page 4 of 4 Oglethorpe Power Corporation Mr. M. W. Price Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosures)
Mr. C. Churchman (w/o enclosures)
Mr. M. Corletti Mr. M. L. Clyde Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light
Southern Nuclear Operating Company ND-18-1476 Enclosure Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Preliminary Amendment Request:
Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling (PAR-18-028)
(This Enclosure consists of 4 pages, including this cover page.)
ND-18-1476 Enclosure PAR-18-028: Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling Pursuant to 10 CFR 52.98(c) and in accordance with 10 CFR 50.90, Southern Nuclear Operating Company (SNC) submitted license amendment request (LAR)-18-028 to change the Vogtle Electric Generating Plant (VEGP) Units 3 and 4 licensing basis documents associated with Combined License Nos. NPF-91 and NPF-92, respectively.
Accordingly, SNC requests the determination of whether the NRC has any objection to SNC proceeding with construction of VEGP Units 3 and 4 routing of Class 1E divisional cables supporting passive containment cooling, which is subject to the changes proposed in LAR-18-028.
Delayed determination regarding this PAR will result in delay in the construction completion of VEGP Units 3 and 4, as identified in the Preliminary Amendment Request (PAR) provided below, to be provided by the date shown below.
PAR Request Number: Station Name: Unit Number(s): PAR Request Date:
SNC PAR-18-028 VEGP 3 4 November 29, 2018
- 1. NRC PAR Notification Requested Date (see Block 7 for basis): January 7, 2019
- 2. License Amendment Request References (as applicable):
LAR submittal date and SNC Correspondence Number: LAR-18-028 - November 16, 2018 / ND-18-1408 Expected LAR submittal date:
- 3. Brief Description of Proposed Change:
The proposed change would revise licensing basis information in the Updated Final Safety Analysis Report (UFSAR) Tier 2 information (plant-specific DCD), which involves a change to the COL Appendix C and corresponding plant-specific Tier 1 information in Table 3.3-3 to reflect revised routing of divisional cables supporting passive containment cooling system (PCS) functions. Additionally, related consistency revisions in the safe shutdown evaluation divisional separation information are proposed.
These changes impact COL Appendix C (and corresponding plant-specific Tier 1) Table 3.3-3, and UFSAR Table 3.7.3-1, Subsection 9.5.1, and Appendix 9A (various subsections),
including Table 9A-2, Table 9A-3 and Table 9A-4.
- 4. Reason for License Amendment Request:
When the shield building changed from reinforced concrete to modular construction in the enhanced shield building design, the modular design and the associated revised structural elements created an interference with the embedded raceway. As a result, a design change is necessary to reroute the electrical raceways which are intended to support the Class 1E dc and Uninterruptible Power Supply (UPS) System (IDS) Class 1E cabling for the loads located in the PCS valve room, which consists of Division A, Division B, and Division C, as well as non-safety raceways.
To determine the licensing basis impact of this change activity, an extensive review was performed of the routing of the affected Class 1E dc cables supporting PCS components.
This review also identified additional impacts to the licensing basis fire protection analysis as described in UFSAR Appendix 9A. The fire areas in this appendix identify the room(s)
Page 2 of 4
ND-18-1476 Enclosure PAR-18-028: Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling that comprise the fire area and are assessed, in part, to confirm the capability to safely shut down the plant following a fire. Details pertaining to the safe shutdown components for these fire areas are tabulated in UFSAR Table 9A-2 and include IDS Class 1E cables/trays, as applicable.
The proposed change requires a change to Tier 2 information in UFSAR and involves a change to Tier 1 information. Therefore, the proposed change requires NRC approval in accordance with 10 CFR 52.98(c).
Additional details are provided in the referenced LAR-18-028.
- 5. Is Exemption Request Required? Yes No If Yes, Briefly Describe the Reason for the Exemption.
No exemption required for the PAR. An exemption is required for the LAR since a change is needed to the Tier 1 information incorporated by reference into 10 CFR Part 52, Appendix D.
- 6. Identify Applicable Precedents:
No precedent identified.
- 7. Impact of Change on Installation and Testing Schedules:
A delayed determination regarding this PAR will result in delay of the installation of divisional cable raceway (e.g., tray and conduit) and associated cable for the Vogtle Units 3 and 4, as described below.
As such, this PAR requests a no objection finding related to the changes described in LAR-18-028 by the date identified in Block 1 above (or sooner if reasonably achievable) to allow for appropriate notifications and release of further activities dependent on construction of the Vogtle Units 3 and 4 divisional cable raceway and associated cable, as noted below.
Specifically, SNC is requesting a no objection finding to allow:
Installation of Division D cable raceway and associated cable in Fire Area 1201 AF 02 Room Nos. 12104, 12204, 12207, 12304, and 12344 Installation of Division B cable raceway and associated cable in Fire Area 1201 AF 03 Room Nos. 12105, 12205, 12305, and 12345 Installation of Division B, C and D cable raceway and associated cable in Fire Area 1204 AF 01 Room No. 12163 Installation of Division A and C cable raceway and associated cable in Fire Area 1200 AF 03 Room Nos. 12311 and 12411 Installation of Division C cable raceway and associated cable in Fire Area 1242 AF 02 Room No. 12412 Construction holds have been issued for these activities.
A no objection finding for the above activities would allow for VEGP Units 3 and 4 construction activities to proceed.
Page 3 of 4
ND-18-1476 Enclosure PAR-18-028: Routing of Class 1E Divisional Cables Supporting Passive Containment Cooling
- 8. Impact of Change on ITAAC:
ITAAC 337 (2.3.04.10), ITAAC 795 (3.3.00.07c.i.a), ITAAC 796 (3.3.00.07c.i.b), ITAAC 797 (3.3.00.07c.ii.a), and ITAAC 798 (3.3.00.07c.ii.b), are affected by this changes identified in the LAR.
The testing of the as-built individual fire detectors will be performed in the fire areas identified in Table 3.3-3. This PAR does not impact this testing as it is not scheduled until well after the requested approval date for the LAR.
The separation maintained between Class 1E divisions in the fire areas identified in Table 3.3-3 is impacted as the specific divisions in each room are revised. The revised routing will continue to meet the separation standards identified in the UFSAR.
Final approval of the License Amendment Request will be necessary for closure of the related ITAAC, but a no objection finding is requested for this PAR in order to proceed with construction pursuant to the process outlined in COL Condition 2.D(1), Changes during Construction. This PAR should be considered for any inspections related to ITAAC 3.3.00.07c (item Nos. 795, 796, 797 and 798) of the VEGP Units 3 and 4 COL Appendix C Table 3.3-3.
- 9. Additional Information:
None Page 4 of 4