ND-18-1100, Vogtie, Units 3 and 4, Resubmittal Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.01.11a.i (Index Number 114)

From kanterella
(Redirected from ND-18-1100)
Jump to navigation Jump to search
Vogtie, Units 3 and 4, Resubmittal Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.01.11a.i (Index Number 114)
ML18235A302
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/20/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-18-1100
Download: ML18235A302 (8)


Text

Michael J. Yox 7825 River Road Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtie 3 & 4 706-848-6459 tel 410-474-8587 ceil myox@southernco.com AUG 2 0 2018 Docket Nos.: 52-025 52-026 ND-18-1100 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Resubmittal Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.01.11a.i [Index Number 1141 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of August 14, 2018, Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.01.Ila.i [Index Number 114] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

Southern Nuclear Operating Company (SNC) previously submitted Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load for Item 2.2.01.11 a.i [Index Number 114] ND-18-0816

[ML18171A053] dated June 18, 2018. This resubmittal supersedes ND-18-0816 in its entirety.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs DirectorA/ogtle 3 &4

Enclosure:

Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.01.11 a.i [Index Number 114]

MJY/SBB/amw

U.S. Nuclear Regulatory Commission ND-18-1100 Page 2 of 3 To:

Southern Nuclear Operating Companv/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones (w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Vox Mr. A. 8. Parton Ms. A. L. Pugh Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. C. T. Defnall Document Services RTYPE; VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W. Jones (w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Ms. A. E. Rivera-Varona Mr. M. E. Ernstes Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Oolethorpe Power Corporation Mr. R. B. Brinkman Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-18-1100 Page 3 of 3 Westlnqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch BIngham

U.S. Nuclear Regulatory Commission ND-18-1100 Enclosure Page 1 of 5 Southern Nuclear Operating Company ND-18-1100 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.01.11a.l [Index Number 114]

U.S. Nuclear Regulatory Commission ND-18-1100 Enclosure Page 2 of 5 ITAAC Statement Design Commitment 11 .a) The motor-operated and check valves identified in Table 2.2.1-1 perform an active safety-related function to change position as indicated in the table.

Insoections. Tests. Analvses i) Tests or type tests of motor-operated valves will be performed to demonstrate the capability of each valve to operate under design conditions.

ii) Inspection will be performed for the existence of a report verifying that the as-built motor-operated valves are bounded by the tests or type tests.

Acceotance Criteria i) Atest report exists and concludes that each motor-operated valve changes position as indicated in Table 2.2.1-1 under design conditions.

ii) Areport exists and concludes that the as-built motor-operated valves are bounded bythe tests or type tests.

ITAAC ComDietion Description Multiple Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) are performed to demonstrate that the Containment System (CMS) motor-operated valves identified in the Combined License (COL) Appendix C, Table 2.2.1-1 perform an active safety-related function to change position as indicated in the table.

\) A test reoort exists and concludes that each motor-operated valve changes position as indicated in Table 2.2.1-1 under design conditions.

This portion of the subject ITAAC requires tests or typetests of motor-operated valves to be performed to demonstrate the capability of the valve to operate under itsdesign conditions.

The motor-operated valves identified in COL Appendix C, Table 2.2.1-1 are qualified in accordance with the provisions of American Society of Mechanical Engineers (ASME)

QME-1-2007, "Qualification of Active Mechanical Equipment Used in Nuclear Power Plants" (Reference 1).

Functional qualification is performed under the design conditions identified in the design specification for the valves (Reference 2) to demonstrate that each motor-operated valve is qualified to perform its designatedfunction when used in its intended service. In accordance with ASME QME-1-2007, qualification is substantiated by demonstrating the relationship between the sen/ice requirements and the type testing and analysis that was conducted as part of this qualification program.

Type testing is performed, including natural frequency determination, side load static deflection testing, final static seat and stem leakage testing, steam testing, and water testing, for the

U.S. Nuclear Regulatory Commission ND-18-1100 Enclosure Page 3 of 5 ranges of the pressure, temperature and flow for each valve and the maximum seat-sealing differential pressure. In accordance with ASME QME-1-2007, the functional qualification process for these motor-operated valve assemblies also included valve and actuator internal inspections and measurement, orientation requirements, seat and stem leakage limitations, diagnostic data collection and analysis methods, static and dynamic flow diagnostic testing, and pressure locking and thermal binding evaluations. The qualification also followed the provisions of ASME QME-1-2007 for the extrapolation of functional qualification to another valve assembly, and demonstration of functional capability of production valve assemblies.

The results of the qualification are documented in the Equipment Qualification (EQ) Reports (Reference 3) which are identified in Attachment Afor each applicable valve. These reports summarize the test methodology and ASME QME-1-2007 functional qualification that demonstrate that each motor-operated valve changes position as indicated in VEGP Unit 3 and Unit 4 CQL Appendix C Table 2.2.1-1 under design conditions.

ii) A report exists and concludes that the as-built motor-operated valves are bounded bv the tests or tvoe tests.

This portion of the subject ITAAC requires that an inspection is performed for the existence of a report verifying that the as-built motor-operated valves are bounded by tests or type tests.

The motor-operated valves in VEGP Unit 3 and Unit 4 COL Appendix 0 Table 2.2.1-1 are verified by tests in accordance with section i) above, to demonstrate the capability of the valves to operate under their design conditions. The EQ Reports in Attachment A identify the equipment mounting employedfor the testing and the specific conditions tested.

In accordance with the EQ Walkdown ITAAC Guideline (Reference 4), an inspection is conducted of the CMS to confirm the satisfactory installation of the motor-operated valves. The inspection includes verification of equipment make/model/serial number, verification of equipment mounting and location, and verification that the mechanical and electrical connections are bounded by the tested conditions.

The documentation of installed configuration of the motor-operated valves includes photographs and/or sketches of equipment mounting and connections. The verification of installed component configuration is documented in the As-Built EQ Reconciliation Report(s) (EQRR)

(Reference 5).

Attachment A identifies the EQRR which verify that the installed configuration of the motor-operated valves identified in VEGP Unit 3 and Unit 4 COL Appendix C Table 2.2.1-1 are bounded by the tests or type tests.

Together, these EQ Reports and EQRR (References 3 and 5), provide evidence that the ITAAC Acceptance Criteria requirements are met:

  • A test report exists and concludes that each motor-operated valve changes position as indicated in Table 2.2.1-1 under design conditions; and
  • A report exists and concludes that the as-built motor-operated valves are bounded by the tests or type tests.

U.S. Nuclear Regulatory Commission ND-18-1100 Enclosure Page 4 of 5 References 3 and 5 are available for NRG Inspection as part of the Unit 3 and Unit 4ITAAC 2.2.01.11a.l Completion Packages (References 6 and 7, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This finding review, which Includes now-consolidated ITAAC Index 115, found the following relevant ITAAC finding associated with this ITAAC:

References favaiiable for NRG inspection)

1. American Society of Mechanical Engineers (ASME) QME-1 -2007, "Qualification of Active Mechanical Equipment Used In Nuclear Power Plants"
2. APP-PV11 -ZO-001 Revision X, "Design Specification for Butterfly Valves, ASME Boiler and Pressure Vessel Code Section III, Class 2 and 3"
3. Equipment Qualification (EQ) Reports as Identified In Attachment A
4. ND-XX-XX-001, EQ Walkdown ITAAC Guideline
5. As-Bullt EquipmentQualification Reconciliation Reports (EQRR) as Identified In Attachment A for Units 3 and 4
6. 2.2.01.11a.l-U3-CP- RevO, ITAAC Completion Package
7. 2.2.01.11 a.l-U4-CP- RevO, ITAAC Completion Package
8. NEI 08-01, "IndustryGuideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-18-1100 Enclosure Page 5 of 5 Attachment A System: Containment System (CNS)

Active EQ Reports As-Bullt EQRR Equipment Name

  • Tag No. + Function * (Reference 3) (Reference 5)*

Component Cooling Water System (CCS) Containment Isolation Motor-operated CCS-PL- Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-Valve (MOV) - Inlet Line V200 Closed APP-PV11-VBR-006 EORR-PCDXXX Outside Reactor Containment (ORC)

CCS Containment Isolation CCS-PL- Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-MOV - Outlet Line IRC V207 Closed APP-PV11-VBR-006 EORR-PCDXXX CCS Containment Isolation CCS-PL- Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-MOV - Outlet Line ORC V208 Closed APP-PV11-VBR-006 EORR-PCDXXX SFS Discharge Line Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-Containment Isolation MOV SFS-PL-V038 Closed APP-PV11-VBR-006 EORR-PCDXXX

-ORC SFS Suction Line Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-Containment Isolation MOV SFS-PL-V034 Closed APP-PV11-VBR-006 EORR-PCDXXX

-IRC SFS Suction Line Transfer APP-PV11-VBR-005/ 2.2.01.11a.i-U3-Containment Isolation MOV SFS-PL-V035 Closed APP-PV11-VBR-006 EORR-PCDXXX

-ORC Transfer Vacuum Relief Containment VFS-PL- Closed / APP-PV11-VBR-005/ 2.2.01.11 a.i-U3-Isolation A MOV - ORC V800A Transfer APP-PV11-VBR-006 EORR-PCDXXX Open Transfer Vacuum Relief Containment VFS-PL- Closed / APP-PV11-VBR-005/ 2.2.01.11a.i-U3-Isolation 8 MOV - ORC V800B Transfer APP-PV11-VBR-006 EORR-PCDXXX Open Notes:

Excerpt from COL Appendix C Table 2.2.1-1

  • The Unit 4 As-Built EQRR are numbered "2.2.01.11a.i-U4-EQRR-PCDXXX"