ND-18-0804, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03a.i (Index Number 343)

From kanterella
(Redirected from ND-18-0804)
Jump to navigation Jump to search
ITAAC Closure Notification on Completion of ITAAC 2.3.05.03a.i (Index Number 343)
ML18211A623
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 07/27/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-18-0804
Download: ML18211A623 (6)


Text

Michael J. Yox 7825 River Road

^ Southern Nuclear Regulatory Affairs Director Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel 410-474-8587 cell JUL 2 7 2018 myox @southernco.com Docket No.: 52-025 ND-18-0804 10CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03a.i llndex Number 3431 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.3.05.03a.i [Index Number 343] for verifying the Material Handling System Polar Crane is single failure proof. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs irector Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.3.05.03a.i [Index Number 343]

MJY/KJD/amw

U.S. Nuclear Regulatory Commission ND-18-0804 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones (w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Yox Mr. A. 8. Parton Ms. A. L. Pugh Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Ms. K. M. Stacy Ms. A. C. Chamberlain Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Ms. A. E. Rivera-Varona Mr. M. E. Ernstes Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Oaiethoroe Power Corporation Mr. R. B. Brinkman Municioai Eiectric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Daiton Utiiltles Mr. T. Bundros

U.S. Nuclear Regulatory Commission ND-18-0804 Page 3 of 3 Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. 8. Roetger, Georgia Pubiic Service Commission Ms. 8. W. Kernizan, Georgia Pubiic Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0804 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0804 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.3.05.03a.i [Index Number 343]

U.S. Nuclear Regulatory Commission ND-18-0804 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment S.a) The polar crane is single failure proof.

Inspections.Tests. Analysis i) Validation of double design factors is provided for hooks where used as load bearing components. Validation of redundant factors is provided for load bearing components such as:

  • Hoisting ropes
  • Sheaves
  • Equalizer assembly
  • Holding brakes Acceptance Criteria i) A report exists and concludes that the polar crane is single failure proof. A certificate of conformance from the vendor exists and concludes that the polar crane is single failure proof.

ITAAC Determination Basis Multiple ITAAC are performed to demonstrate that the polar crane is single failure proof. The subject ITAAC requires that validation of double design factors is provided for hooks where used as load bearing components, and that validation of redundant factors is provided for load bearing components such as hoisting ropes, sheaves, equalizer assembly and holding brakes.

The polar crane is a single failure proof design which conforms to the guidelines of NUREG-0554 "Single-Failure-Proof Cranes for Nuclear Power Plants" (Reference 1), supplemented by American Society of Mechanical Engineers (ASME) NOG-1-1998, "Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder)" (Reference 2). Single failure proof design is described in NUREG-0554 as "a single failure will not result in the loss of the capability of the system to safely retain the load." The requirements to follow NUREG-0554, supplemented by ASME NOG-1-1998, for the design of the polar crane were imposed in the API 000 polar crane design specification (Reference 3).

The polar crane single failure proof report (Reference 4) exists and concluded that the polar crane is single failure proof. Additionally, a Certificate of Conformance (Reference 5) from the polar crane vendor (manufacturer) exists and concluded that the polar crane is single failure proof.

U.S. Nuclear Regulatory Commission ND-18-0804 Enclosure Page 3 of 3 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertainingto the subject ITAAC and associated corrective actions. This review found that there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.3.05.03a.i (Reference 6) and is available for NRC review.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.3.05.03a.i was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition inaccordance with approved plant programsand procedures.

References (available for NRC inspection)

1. NUREG-0554, "Single-Failure-Proof Cranes for Nuclear Power Plants", May 1979
2. ASME NOG-1 -1998, "Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder)"
3. APP-MH01 -ZO-101, Rev 5, "Design Specification for API000 Polar Crane for System MRS"
4. WEC_SV0_000005, "Vogtle Unit 3 MH01 Polar Crane Supporting References to Topical Report EDR-1", July 13, 2018
5. SV3-MH01-VQQ-009, Rev. 0, "Quality Release and Certificate of Conformance for SV3 API 000 Polar Crane Shipment"
6. 2.3.05.03a.i-U3-CP-Rev 0, ITAAC Completion Package