ML26049A076
| ML26049A076 | |
| Person / Time | |
|---|---|
| Site: | 99902159 |
| Issue date: | 03/13/2026 |
| From: | Carolyn Lauron NRC/NRR/DNRL/NLIB |
| To: | Hazelhoff A EnergySolutions |
| References | |
| EPID L-2026-TOP-0005 | |
| Download: ML26049A076 (0) | |
Text
From:
India Banks To:
"achazelhoff@energysolutions.com" Cc:
"jrlynch@energysolutions.com"; "james.moorman.iii@gmail.com"; Michelle Hayes; Carolyn Lauron; Douglas Bollock
Subject:
Completeness Determination for EnergySolutions, "Topical Report Quality Assurance Program Description for the EnergySolutions Kewaunee New Nuclear Initiative" - Report Number ES-QA-PG-003, Revision 0 Date:
Friday, March 13, 2026 4:18:00 PM Attachments:
NRC 898 - Technical Staff Completeness Determination - EnergySolutions QAPD(signed).pdf Amy C. Hazelhoff Senior Vice President Regulatory Affairs
Dear Ms. Hazelhoff,
Attached please find NRC Form 898, Topical Report Completeness Determination, that the NRC staff has prepared for report number ES-QA-PG-003, Revision 0, Topical Report Quality Assurance Program Description for the EnergySolutions Kewaunee New Nuclear Initiative. The estimated due dates for several milestones, including the issuance of a Request for Additional Information (RAI), and completion of the Draft Safety Evaluation (SE) and Final SE are shown on the form. The review schedule assumes a timely response to audit issues and a 30-day response to RAIs (if applicable).
The dates and resource estimates are subject to change as they may be affected by the timeline of resolution of technical issues or other factors. If there are emergent complexities or challenges in the NRC staff review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
If you have any questions, please feel free to contact me via email at India.Banks@nrc.gov.
Docket No.: 99902159 EPID: L-2026-TOP-0005
Thank you,
INDIA BANKS PROJECT MANAGER U.S. NUCLEAR REGULATORY COMMISSION NRR/DNRL/NLIB