From:
ext_Jessica_Maddocks Sent:
Friday, May 31, 2024 3:14 PM To:
Ondra Dukes
Subject:
[External_Sender] RE: RE: RE: X-energy Graphite Topical Report Readiness Assessment
- Ondra, I just tried calling and once again it did not ring. Im not sure what is going on. I have a rough graphite agenda for you, so give me a call when you have a moment. Thanks!
Jessica Maddocks Licensing Project Manager jmaddocks@x-energy.com This message (including any attachments) is intended only for the use of the individual or entity to which it is addressed and may contain information that is non-public, proprietary, privileged, confidential, and exempt from disclosure under applicable law or may constitute attorney work product. If you are not the intended recipient, you are hereby notified that any use, dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, notify us immediately and delete this message immediately. Thank you. X Energy, LLC From: Ondra Dukes Sent: Friday, May 31, 2024 8:41 AM To: Jessica Maddocks Cc: Adrian Muniz
Subject:
RE: RE: RE: X-energy Graphite Topical Report Readiness Assessment Thank you Jessica-Ondra Dukes Project Manager NRR/DANU/UAL2 301-415-0537 ondra.dukes@nrc.gov From: Jessica Maddocks <jmaddocks@x-energy.com>
Sent: Friday, May 31, 2024 8:30 AM To: Ondra Dukes <Ondra.Dukes@nrc.gov>
Cc: Adrian Muniz <Adrian.Muniz@nrc.gov>
Subject:
[External_Sender] RE: RE: X-energy Graphite Topical Report Readiness Assessment
- Ondra, The graphite team has a meeting this afternoon to work on a graphite outline/agenda. I will give you a call later this afternoon. It will be after 3pm.
Notice: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Jessica Maddocks Licensing Project Manager jmaddocks@x-energy.com This message (including any attachments) is intended only for the use of the individual or entity to which it is addressed and may contain information that is non-public, proprietary, privileged, confidential, and exempt from disclosure under applicable law or may constitute attorney work product. If you are not the intended recipient, you are hereby notified that any use, dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, notify us immediately and delete this message immediately. Thank you. X Energy, LLC From: Ondra Dukes <Ondra.Dukes@nrc.gov>
Sent: Wednesday, May 29, 2024 12:00 PM To: Jessica Maddocks <jmaddocks@x-energy.com>
Cc: Adrian Muniz <Adrian.Muniz@nrc.gov>
Subject:
RE: RE: X-energy Graphite Topical Report Readiness Assessment Good Morning Jessica, I have blocked off July 25th from 8AM-12PM for the Graphite TR Readiness Assessment entrance meeting.
As discussed, I will reach out Friday morning for an update on the outline/agenda if I do not hear from you prior to then.
Thank you, Ondra Dukes Project Manager NRR/DANU/UAL2 301-415-0537 ondra.dukes@nrc.gov From: Jessica Maddocks <jmaddocks@x-energy.com>
Sent: Wednesday, May 29, 2024 9:51 AM To: Ondra Dukes <Ondra.Dukes@nrc.gov>
Subject:
[External_Sender] RE: X-energy Graphite Topical Report Readiness Assessment Ondra, July 25th works for X-energy. Ive tried calling a few times but cant seem to get you. Im free until our 11am, and assuming our call does not take an hour, I am free right after.
Jessica Maddocks Licensing Project Manager jmaddocks@x-energy.com This message (including any attachments) is intended only for the use of the individual or entity to which it is addressed and may contain information that is non-public, proprietary, privileged, confidential, and exempt from disclosure under applicable law or may constitute attorney work product. If you are not the intended recipient, you are hereby notified that any use, dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, notify us immediately and delete this message immediately. Thank you. X Energy, LLC Notice: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
From: Ondra Dukes <Ondra.Dukes@nrc.gov>
Sent: Thursday, May 23, 2024 4:47 PM To: Jessica Maddocks <jmaddocks@x-energy.com>
Cc: Adrian Muniz <Adrian.Muniz@nrc.gov>
Subject:
RE: X-energy Graphite Topical Report Readiness Assessment Good Afternoon Jessica, I have coordinated with NRC staff and there are a few schedule conflicts the week of July 15th. We are available to support a readiness assessment of the graphite topical report the week of July 22nd. Would X-energy be available any of the following dates?
July 22nd (afternoon)
July 23rd (afternoon)
July 24th (afternoon)
July 25th (morning)
I would also like to gather some more information on the entrance meeting duration and agenda, please give me a call to discuss.
Thank you, Ondra Dukes Project Manager NRR/DANU/UAL2 301-415-0537 ondra.dukes@nrc.gov From: Jessica Maddocks <jmaddocks@x-energy.com>
Sent: Wednesday, May 15, 2024 9:13 AM To: Adrian Muniz <Adrian.Muniz@nrc.gov>
Cc: Ondra Dukes <Ondra.Dukes@nrc.gov>
Subject:
[External_Sender] X-energy Graphite Topical Report Readiness Assessment
- Adrian, X-energy would like to do a readiness assessment for our graphite topical report starting the week of July 15. For the entrance meeting X-energy would like a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> block. We are available anytime July 15 - 17 for the meeting. Please let me know what other information you need from X-energy to support.
Jessica Maddocks Licensing Project Manager jmaddocks@x-energy.com This message (including any attachments) is intended only for the use of the individual or entity to which it is addressed and may contain information that is non-public, proprietary, privileged, confidential, and exempt from disclosure under applicable law or may constitute attorney work product. If you are not the intended recipient, you are hereby notified that any use, dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, notify us immediately and delete this message immediately. Thank you. X Energy, LLC Notice: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Hearing Identifier:
XeDOW_ProjectLongMott_SafPublic Email Number:
33 Mail Envelope Properties (PH3P110MB224774FA6B7EBD429222F39090FCA)
Subject:
[External_Sender] RE RE RE X-energy Graphite Topical Report Readiness Assessment Sent Date:
5/31/2024 3:14:00 PM Received Date:
5/31/2024 3:14:16 PM From:
ext_Jessica_Maddocks Created By:
/O=EXCHANGELABS/OU=EXCHANGE ADMINISTRATIVE GROUP (FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=BB0743AD17B046F39958AF4A985C5297-8AC523D3-F8 Recipients:
"Ondra Dukes" <Ondra.Dukes@nrc.gov>
Tracking Status: None Post Office:
PH3P110MB2247.NAMP110.PROD.OUTLOOK.COM Files Size Date & Time MESSAGE 7243 5/31/2024 3:14:16 PM image001.png 3997 Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date: