NL-25-0478, GEN-ISI-ALT-2026-01 - Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection
| ML26037A274 | |
| Person / Time | |
|---|---|
| Site: | Farley, Vogtle |
| Issue date: | 02/06/2026 |
| From: | Coleman J Southern Nuclear Operating Co |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| NL-25-0478 | |
| Download: ML26037A274 (0) | |
Text
3535 Colonnade Parkway Birmingham, AL 35243 205.992.5000 Regulatory Affairs February 6, 2026 Docket Nos.: 50-348 50-424 NL-25-0478 50-364 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Southern Nuclear Operating Company Joseph M. Farley Nuclear Plant, Units 1 and 2 Vogtle Electric Generating Plant, Units 1 and 2 GEN-ISI-ALT-2025 Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection Ladies and Gentlemen:
In accordance with 10 CFR 50.55a, "Codes and standards," paragraph (g)(4)(iv), and the guidance provided in Nuclear Regulatory Commission (NRC) Regulatory Issue Summary (RIS) 2004-12, "Clarification on Use of Later Editions and Addenda to the ASME OM Code and Section XI," Southern Nuclear Operating Company (SNC) hereby requests NRC approval to use the provisions of a later edition of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code,Section XI, incorporated by reference in 10 CFR 50.55a(a)(1)(ii), for Joseph M. Farley Nuclear Plant, Units 1 and 2, and Vogtle Electric Generating Plant, Units 1 and 2.
Specifically, SNC requests approval to use the 2019 Edition of the ASME B&PV Code,Section XI, in its entirety for inservice inspection (ISI).
The enclosure to this letter provides details of the request.
SNC respectfully requests approval by July 1, 2026.
This letter contains no new regulatory commitments. If you have any questions, please contact Mr. Ryan Joyce at 205.992.6468.
Respectfully submitted, Jamie M. Coleman Director, Regulatory Affairs Southern Nuclear Operating Company JMC/btr/cbg Digitally signed by JAMIEMCO Date: 2026.02.06 11:46:26 -06'00'
U.S. Nuclear Regulatory Commission NL-25-0478 Page 2 of 2
Enclosure:
GEN-ISI-ALT-2025 Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection cc:
Regional Administrator, Region II NRR Project Manager - Farley, Vogtle 1&2 Senior Resident Inspector - Farley, Vogtle 1&2 Director, Alabama Office of Radiation Control Director, Environmental Protection Division - State of Georgia RType: CFA04.054, CVC7000
Southern Nuclear Operating Company Joseph M. Farley Nuclear Plant - Units 1 and 2 Vogtle Electric Generating Plant - Units 1 and 2 Enclosure to NL-25-0478 GEN-ISI-ALT-2025 Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection
Enclosure to NL-25-0478 E-1 GEN-ISI-ALT-2025 Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection In accordance with 10 CFR 50.55a, "Codes and standards," paragraph (g)(4)(iv), and the guidance in Reference 1, Southern Nuclear Operating Company (SNC) requests Nuclear Regulatory Commission (NRC) approval to use a later edition of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code,Section XI, for Joseph M. Farley Nuclear Plant, Units 1 and 2 (FNP), and Vogtle Electric Generating Plant, Units 1 and 2 (VEGP 1&2). Specifically, SNC requests approval to use the 2019 Edition of the ASME B&PV Code,Section XI, in its entirety for inservice inspection (ISI) requirements.
- 1. Components Affected Class 1, 2, and 3 components included in the ASME Section XI ISI Programs at FNP and VEGP 1&2.
- 2. Requested Date for Approval Approval is requested by July 1, 2026.
3. Applicable Code Edition and Addenda
The current applicable ASME Section XI Code of Record for each plant's ISI interval is shown in Table 1.
Table 1 - Current ASME Section XI ISI Interval Code of Record Plant ISI Interval Current Edition Interval Start Interval Scheduled End Farley Nuclear Plant, Units 1 and 2 Fifth 2007 Edition with 2008 Addenda 12/01/2017 11/30/2027 Vogtle Electric Generating Plant, Units 1 and 2 Fourth 2007 Edition with 2008 Addenda 05/31/2017 05/30/2027
- 4. Proposed Subsequent Code Edition and Addenda (or Portion)
The current ISI Program Code of Record at FNP and VEGP 1&2 is the 2007 Edition with 2008 Addenda of ASME Section XI.
SNC requests NRC approval to use the 2019 Edition of the ASME B&PV Code,Section XI, in its entirety for ISI requirements. This request is made in accordance with 10 CFR 50.55a paragraph (g)(4)(iv), which permits the use of subsequent editions and addenda that are incorporated by reference in 10 CFR 50.55a, subject to NRC approval. The 2019 Edition is incorporated by reference in 10 CFR 50.55a (Reference 2).
Enclosure to NL-25-0478 E-2
- 5. Related Requirements 10 CFR 50.55a(g)(4)(iv) states, in part:
Inservice examination of components and system pressure tests may meet the requirements set forth in subsequent editions and addenda that are incorporated by reference in paragraph (a) of this section, subject to the conditions listed in paragraph (b) of this section, and subject to Commission approval. Portions of editions or addenda may be used, provided that all related requirements of the respective editions or addenda are met.
SNC is requesting to use the 2019 Edition of the ASME Section XI Code in its entirety for ISI.
6. Duration of Proposed Alternative
Use of the 2019 Edition of the ASME Code,Section XI, in its entirety for ISI would remain in effect for the remainder of the current ISI Intervals at FNP and VEGP 1&2, as identified in Section 3 of this enclosure.
- 7. References
- 1. NRC Regulatory Issue Summary 2004-12, "Clarification on Use of Later Editions and Addenda to the ASME OM Code and Section XI, dated July 28, 2004.
- 2. Federal Register, 87 FR 65128, dated October 27, 2022.
- 8. Precedent Vogtle Electric Generating Plant, Units 3 and 4, "VEGP3&4-ISI-ALT-2025-01, Request for Use of a Later Edition of the ASME Section XI Boiler and Pressure Vessel Code for Inservice Inspection," May 20, 2025 (ADAMS Accession No. ML25140A970). The request was authorized on July 24, 2025 (ADAMS Accession No. ML25196A297).