February 3, 2026 Christopher H. Mudrick Senior Vice President and Chief Nuclear Officer Constellation Energy Generation, LLC President Constellation Nuclear 200 Energy Way, KSA-3N Kennett Square, PA 19348
SUBJECT:
RESTART INSPECTION ACTIVITY PLAN FOR CHRISTOPHER M. CRANE CLEAN ENERGY CENTER
Dear Christopher Mudrick:
On September 26, 2019, the Christopher M. Crane Clean Energy Center (CCEC), formerly Three Mile Island Nuclear Station, Unit 1, permanently ceased power operations and removed all fuel from the reactor, as certified in a letter to the U. S. Nuclear Regulatory Commission (NRC) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19269E480). On November 19, 2024, Constellation Energy Generation, LLC (Constellation) submitted a letter to the NRC requesting exemptions from certain portions of the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(2) to pursue the potential reauthorization of power operations at CCEC (ML24324A048). The NRCs initial acceptance to review CCECs request for exemptions was documented in a letter on December 20, 2024 (ML24355A057). This letter informs you of the NRCs plans for future inspections at your facility.
The general inspection program discussed in Inspection Manual Chapter 2562, Light-Water Reactor Inspection Program for Restart of Reactor Facilities Following Permanent Cessation of Power Operations, dated April 24, 2025, states, in part, that the NRC will ensure that operational readiness has been reasonably verified across the Reactor Oversight Process (ROP) cornerstones of safety. The Crane Restart Panel has approved an inspection program plan (ML25114A121). If restart is authorized, the NRC will determine the appropriate point to transition NRC oversight to the ROP.
The enclosed site inspection activity plan lists the inspections scheduled through June 1, 2027.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. Inspection dates may move, depending on the restoration status of equipment and programs, to ensure the NRC can adequately assess CCECs readiness to enter the Reactor Oversight Process. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
C. Mudrick 2
This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 610-337-5120 with any questions you have regarding this letter.
Sincerely, Erin E. Carfang, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000289 License No. DPR-50
Enclosure:
Crane Site Inspection Activity Plan cc w/encl: Distribution via GovDelivery ERIN CARFANG Digitally signed by ERIN CARFANG Date: 2026.02.03 08:09:21 -05'00'
ML26034A001 SUNSI Review
- Non-Sensitive Sensitive
- Publicly Available Non-Publicly Available OFFICE RI/DORS RI/DORS NAME NFloyd ECarfang DATE 1/29/2026 1/30/2026
Site Inspection Activity Plan 05000289 - Crane Clean Energy Center 01/01/2026 - 06/01/2027 Unit Start End Activity CAC Title Staff Count 2026 Q1 and Q2 IMC 2562 Inspections 1
1 2/2/2026 2/3/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
SEC - Access Authorization, SGI, FFD - Crane 3
1 2/9/2026 2/13/2026 IP 81000.01 001940 Access Authorization 1
2/9/2026 2/13/2026 IP 81000.06 001943 Protection of Safeguards Information 1
2/9/2026 2/13/2026 IP 81000.08 001941 Fitness-for-Duty Program MRP-227 Reactor Vessel Internal Inspection - Crane 2
1 6/1/2026 6/5/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR) 2026 Crane Initial Operator Licensing Exam 8
1 5/18/2026 5/22/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV) 1 8/3/2026 8/14/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Cyber Security - Crane 2
1 8/24/2026 8/28/2026 IP 81000.12 001950 Cybersecurity Restart Inspection--Pre-Fuel Load Fire Protection - Crane 3
1 11/30/2026 12/4/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI) 1 12/14/2026 12/18/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
License Renewal Phase 4 - Crane 4
1 1/11/2027 1/15/2027 IP 71003 000687 Post-Approval Site Inspection for License Renewal 1
1/25/2027 1/29/2027 IP 71003 000687 Post-Approval Site Inspection for License Renewal Environmental Qualification Inspection - Crane 1
1 1/11/2027 1/15/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)
SEC - Access Control, Training - Crane 2
1 1/18/2027 1/22/2027 IP 81000.02 001937 Access Control 1
1/18/2027 1/22/2027 IP 81000.07 001939 Security Training EP Exercise Inspection - Crane Clean Energy Center 5
1 2/8/2027 2/12/2027 IP 71114.01 000716 Exercise Evaluation SEC - Equip Perf, Testing and Maintenance, Org and Program Reviews, TSR - Crane 4
1 2/8/2027 2/12/2027 IP 81000.04 001938 Equipment Performance, Testing, and Maintenance 1
2/8/2027 2/12/2027 IP 81000.10 001947 Security Organization, Management Effectiveness, Program Reviews and Audits 1
2/8/2027 2/12/2027 IP 81000.14 001944 Review of New Power Reactor Target Sets Flexible Coping Strategy Verification - Crane 2
1 2/22/2027 2/26/2027 IP 71152 000748 Problem Identification and Resolution (PI&R)
Prepared on 1/27/2026 12:34:43 PM 1 of 2
Site Inspection Activity Plan Problem Identification and Resolution Team Inspection - Crane 3
1 2/22/2027 2/26/2027 IP 71152B 000747 Problem Identification and Resolution 1
3/8/2027 3/12/2027 IP 71152B 000747 Problem Identification and Resolution SEC - TSR - Crane 1
1 3/1/2027 3/5/2027 IP 81000.14 001944 Review of New Power Reactor Target Sets TI-194 Open Phase Inspection - Crane 1
1 3/8/2027 3/12/2027 TI 2515/194 000989 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012 01)
SEC - Performance Eval Program, Protective Strategy - Crane 4
1 3/15/2027 3/19/2027 IP 81000.03 001946 Performance Evaluation Program 1
3/15/2027 3/19/2027 IP 81000.05 001945 Protective Strategy Evaluation 2027 Crane Initial Operator Licensing Exam 8
1 3/1/2027 3/5/2027 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV) 1 4/5/2027 4/16/2027 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Cyber Security - Crane 2
1 5/3/2027 5/7/2027 IP 81000.13 Cybersecurity Restart Inspection--Post-Fuel Load 1
5/17/2027 5/21/2027 IP 81000.13 Cybersecurity Restart Inspection--Post-Fuel Load Prepared on 1/27/2026 12:34:43 PM 2 of 2