TRISO-X Oak Ridge - Inspection Schedule for TX-1 Phase 2A
ML26012A293
Person / Time
Site: Triso-X
Issue date: 01/13/2026
From: Eric Michel
NRC/RGN-II/DFRSS/FOB2
To: Wheeler J
Triso-X
References
Download: ML26012A293 (0)


Text

Jennifer Wheeler Vice President, Regulatory Affairs TRISO-X, LLC 151 Lafayette Drive, Suite 300 Oak Ridge, TN 37830

SUBJECT:

TRISO-X - OAK RIDGE - INSPECTION SCHEDULE FOR TX-1 PHASE 2A

Dear Jennifer Wheeler:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the TRISO-X facility for the proposed TX-1 building Phase 2a, only. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative, reactive inspections, or additional inspections needed to support changes in construction schedule, licensing actions, new processes or technologies are not included in the schedule and will be added as detailed schedule information becomes available. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Cynthia Taylor (404) 997-4480 with any questions or concerns you may have regarding this letter or the inspection schedule.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Eric C. Michel, Chief Fuels Oversight Branch 2 Division of Fuels, Radiological Safety, and Security Docket No. 07007027

Enclosure:

As stated cc w/ encl: Distribution via LISTSERV January 12, 2026 Signed by Michel, Eric on 01/12/26

J. Wheeler 2

SUBJECT:

TRISO-X - OAK RIDGE - INSPECTION SCHEDULE FOR TX-1 PHASE 2A DATED JANUARY 12, 2026 DISTRIBUTION:

L. Suggs, RII C. Taylor, RII C. Oelstrom, RII B. Bout, RII T. Govan, NMSS M. Bartlett, NMSS L. McKown, RII A. Ponko, RII ADAMS ACCESSION NUMBER: ML26012A293 X

SUNSI Review X

Non-Sensitive

Sensitive X

Publicly Available

Non-Publicly Available OFFICE RII/DRS RII/DRS RII/DRS NAME C. Oelstrom C. Taylor E. Michel DATE 01/12/2026 01/12/2026 01/12/2026 OFFICIAL RECORD

Enclosure Proposed Inspections per IMC 2694-Fuel Cycle Facility Construction and Pre-Operational Readiness Review Inspection Program for Building TX Phase 2A Building Construction Inspection*

Activity Hours Inspection Procedure Inspectors Est. Branch Resources Management Measures 30 88201 1

Foundations - Rigid Inclusion 15 88200 A 0.5 1

Structural Concrete

- Mat 45 88200 B 1.5 FOB2/ EB3 2**

Structural Steel -

Columns, Connections, Braced Frames, Decking 30 88200 C & K 1

EB3 3**

Structural Steel -

Braced Frames, Connections, Joists, Roof, Siding 30 88200 C & K 1

EB3 Total Hours 150

  • Inspections may be shifted and/or adjusted due to construction schedule and availability.
    • Inspections 2 and 3 can be combined into one inspection with 2 inspectors if warranted by construction schedule.