Project Long Mott Docs - Re Re Fws Mitigation Measures Letter
ML26005A235
Person / Time
Site: 05000614
Issue date: 01/05/2026
From:
NRC
To:
NRC/NMSS/DREFS
References
Download: ML26005A235 (0)


Text

From:

Joe OHara Sent:

Monday, January 5, 2026 3:43 PM To:

Milton Gorden; ext_Mark_Feltner; ProjectLongMott-EnvPUBLICem Resource Cc:

Robert Hoffman; Shannon Healy; Daniel Barnhurst

Subject:

RE: RE: FWS Mitigation Measures Letter Hi Milton, We are evaluating a tentative initiation date of Monday February 9th for a 60-day window which would terminate on Friday April 10th.

R/

Joe OHara Environmental Project Manager U.S. Nuclear Regulatory Commission Environmental Review Project Management Branch From: Milton Gorden <mgorden@x-energy.com>

Sent: Monday, January 5, 2026 3:30 PM To: Joe OHara <Joe.OHara@nrc.gov>; ext_Mark_Feltner <mfeltner@dow.com>; ProjectLongMott-EnvPUBLICem Resource <ProjectLongMott-EnvPUBLICem.Resource@nrc.gov>

Cc: Robert Hoffman <Robert.Hoffman@nrc.gov>; Shannon Healy <Shannon.Healy@nrc.gov>; Daniel Barnhurst <Daniel.Barnhurst@nrc.gov>

Subject:

[External_Sender] RE: FWS Mitigation Measures Letter Yes, we plan on getting out the USFWS measures letter by Jan. 16.

Just so we know, when does the USFWS consultation window begin in your schedule?

Milton Gorden Manager, Licensing Direct: 240.802.8580 Mobile: 240-405-5482 mgorden@x-energy.com This message (including any attachments) is intended only for the use of the individual or entity to which it is addressed and may contain information that is non-public, proprietary, privileged, confidential, and exempt from disclosure under applicable law or may constitute attorney work product. If you are not the intended recipient, you are hereby notified that any use, dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, notify us immediately and delete this message immediately. Thank you. X Energy, LLC From: Joe OHara <Joe.OHara@nrc.gov>

Sent: Monday, January 5, 2026 3:23 PM To: Milton Gorden <mgorden@x-energy.com>; ext_Mark_Feltner <mfeltner@dow.com>; ProjectLongMott-EnvPUBLICem Resource <ProjectLongMott-EnvPUBLICem.Resource@nrc.gov>

Cc: Robert Hoffman <Robert.Hoffman@nrc.gov>; Shannon Healy <Shannon.Healy@nrc.gov>; Daniel Barnhurst <Daniel.Barnhurst@nrc.gov>

Subject:

FWS Mitigation Measures Letter Hi folks, I just wanted to confirm that the letter we discussed this afternoon at out 1 pm meeting, which is making its way through the X-energy management concurrence, will include a discussion on the FWS mitigation measures. Those mitigation measures were discussed at a meeting on Monday December 15th.

My understanding is that the letter should be issued sometime before Friday January 16th.

Notice: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

We are looking at the FWS Consultation timeline, and we want to ensure our timing is correct to initiate the 60 day window with FWS and meet any schedule obligations.

Thank you, Joe Joe OHara Environmental Project Manager U.S. Nuclear Regulatory Commission Environmental Review Project Management Branch

Hearing Identifier:

XeDOW_ProjectLongMott_EnvPublic Email Number:

34 Mail Envelope Properties (BLAPR09MB6484717D2BC8BB1C2734A945EE86A)

Subject:

RE RE FWS Mitigation Measures Letter Sent Date:

1/5/2026 3:42:38 PM Received Date:

1/5/2026 3:42:46 PM From:

Joe OHara Created By:

Joe.OHara@nrc.gov Recipients:

"Robert Hoffman" <Robert.Hoffman@nrc.gov>

Tracking Status: None "Shannon Healy" <Shannon.Healy@nrc.gov>

Tracking Status: None "Daniel Barnhurst" <Daniel.Barnhurst@nrc.gov>

Tracking Status: None "Milton Gorden" <mgorden@x-energy.com>

Tracking Status: None "ext_Mark_Feltner" <>

Tracking Status: None "ProjectLongMott-EnvPUBLICem Resource" <ProjectLongMott-EnvPUBLICem.Resource@nrc.gov>

Tracking Status: None Post Office:

BLAPR09MB6484.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3350 1/5/2026 3:42:46 PM Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date: