ML25364A303
| ML25364A303 | |
| Person / Time | |
|---|---|
| Site: | 99902137 |
| Issue date: | 12/30/2025 |
| From: | Prosanta Chowdhury Office of Nuclear Reactor Regulation |
| To: | Blue Energy, Blue Energy Global |
| References | |
| Download: ML25364A303 (0) | |
Text
From:
regulatoryaffairs@blueenergy.co Cc:
ext_CJ_Fong; ext_Antonios_Zoulis; Mahmoud -MJ-Jardaneh; Riley Maynard; Alina Schiller
Subject:
ACTION: Final Safety Evaluation for Blue Energy Topical Report BE-BOPTR-02, Resequencing Balance-of-Plant and Nuclear Island Construction for Blue Energy Deployments, Revision 1 (Non-Proprietary)
Date:
Tuesday, December 30, 2025 2:00:00 PM Attachments:
Safety Evaluation for Blue Energy Topical Report BE-BOPTR-02, Rev. 1.pdf By letter dated September 11, 2025, Blue Energy Global, Inc. (Blue Energy) submitted Revision 1 of Topical Report (TR) BE-BOPTR-02, Resequencing Balance-of-Plant and Nuclear Island Construction for Blue Energy Deployments, (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML25254A215), to the U.S. Nuclear Regulatory Commission (NRC). The NRC staff has prepared a final safety evaluation for BE-BOPTR-02, Revision 1. The non-proprietary final safety evaluation is attached (ML25260A494). The NRC staff has found BE-BOPTR-02, Revision 1, to be acceptable for referencing in future licensing applications to the extent specified and under the limitations and conditions delineated in the attached final safety evaluation.
The NRC staff requests that Blue Energy publish the accepted version of this TR within three months of receipt of this electronic mail. The accepted version shall incorporate this electronic mail and the enclosed final safety evaluation after the title page. It must be well indexed such that information is readily located.Also, it must contain historical review information, including NRC requests for additional information and accepted responses. The accepted version of the TR shall include a -A (designated accepted) following the report identification number.
If the NRCs criteria or regulations change such that the NRC staffs conclusion in this electronic mail (that the TR is acceptable) is invalidated, Blue Energy and/or the applicant referencing the TR will be expected to either revise and resubmit its respective documentation or to submit justification for continued applicability of the TR without revision of the respective documentation.
If you have any questions or comments concerning this matter, I can be reached at (301) 415-1647 or via e-mail at Prosanta.Chowdhury@nrc.gov.
Sincerely,
Project No. 99902137
Prosanta Chowdhury Senior Project Manager US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of New and Renewed Licenses New Reactor Licensing Branch Ph. 301-415-1647 Email: Prosanta.Chowdhury@nrc.gov