ML25343A199

From kanterella
Jump to navigation Jump to search
Submittal of Supplemental Information to Support the Kemmerer Unit 1 Construction Permit Application Review
ML25343A199
Person / Time
Site: Kemmerer File:TerraPower icon.png
Issue date: 12/09/2025
From: George Wilson
TerraPower
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
TP-LIC-LET-0472
Download: ML25343A199 (0)


Text

15800 Northup Way, Bellevue, WA 98008 www.TerraPower.com P. +1 (425) 324-2888 F. +1 (425) 324-2889 December 9, 2025 TP-LIC-LET-0472 Docket Number 50-613 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Document Control Desk

Subject:

Submittal of Supplemental Information to Support the Kemmerer Unit 1 Construction Permit Application Review

References:

1. TerraPower, LLC, Submittal of the Construction Permit Application for the Natrium Reactor Plant, Kemmerer Power Station Unit 1, March 28, 2024 (ML24088A059).

This letter transmits information to supplement the construction permit application for Kemmerer Unit 1, provided via Reference 1. Specifically, the earliest projected construction completion date is August 30, 2030, with a six-month contingency resulting in the latest projected construction completion date of February 28, 2031.

This letter makes no new or revised regulatory commitments.

If you have any questions regarding this submittal, please contact Ian Gifford at igifford@terrapower.com.

Sincerely, George Wilson Senior Vice President, Regulatory Affairs TerraPower, LLC

Date: December 9, 2025 Page 2 of 2 15800 Northup Way, Bellevue, WA 98008 www.TerraPower.com P. +1 (425) 324-2888 F. +1 (425) 324-2889 cc:

Mallecia Sutton, NRC Josh Borromeo, NRC Nathan Howard, DOE