ML25323A067

From kanterella
Jump to navigation Jump to search
Form 2.1-1 Examination Preparation Checklist (LAS 2025)
ML25323A067
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 11/14/2025
From:
NRC/RGN-III
To:
Constellation Energy Generation, Exelon Generation Co
Troy Henning
Shared Package
ML23202A180 List:
References
Download: ML25323A067 (1)


Text

Form 2.1-1 Examination Preparation Checklist Facility: LaSalle Date of Examination: September 22, 2025 Developed by: Written:

Facility NRC

//

Operating:

Facility NRC Days from Exam Target Date*

Task Description CEs Initials

-240 01/25/25

1. Examination administration date confirmed (A.1-5). For NRC-prepared examinations, arrangements are made for the facility licensee to submit reference materials (B.4, C.4.g and F).

TJH

-210 02/24/25

2. NRC examiners and facility licensee contact assigned (B.1 and C.1-3).

TJH

-210 02/24/25

3. Facility licensee contact briefed on examination security and other requirements (D.4).

As applicable, the facility licensee contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facility licensees prescreening process (ES-4.1 A.1.and ES-4.1 B.2).

TJH

-210 02/24/25

4. Reference material due for NRC-prepared examinations (F).

N/A

-210 02/24/25

5. Examination kick-off call held (C.4). The NRC sends the corporate notification letter (A.5).

TJH

-195 03/11/25

6. Written examination outline developed by the NRC and sent to the facility licensee contact (must be on the examination security agreement) (B.2, ES-4.1 A.1.b and ES-4.1 A.2.a).

TJH

-150 04/25/25

7. Operating test outlines and checklists due: Forms 1.3-1, 2.3-1, 3.2-1, 3.2-2, 3.3-1, and 3.4-1, as applicable (B.6). Facility licensee provides a draft operating test administration schedule to the NRC (B.18).

TJH

-136 05/09/25

8. Operating test outlines reviewed by the NRC and feedback provided to the facility licensee (ES-2.3).

TJH

-100 06/14/25

9. NRC-prepared examinations approved by the NRC supervisor and forwarded for facility licensee review (ES-2.3).

N/A

-75 07/09/25

10. Proposed examinations (written, JPMs, and scenarios, as applicable) and outline forms; quality checklists and supporting documentation (including Forms 2.3-2 and 2.3-4 and any Form 2.3-1, 1.3-1, and 3.4-1 updates); and reference materials due.

TJH

-60 07/24/25

11. Preliminary waiver/excusal requests due (ES-2.2 E.1).

TJH

-50 08/03/25

12. Written examination and operating test reviews completed (ES-2.3). The NRC supervisors authorization to proceed with the facility review granted (ES-2.3 D).

TJH

-50 08/03/25

13. Examination review results discussed between the NRC and the facility licensee (B.14).

TJH

-35 08/18/25

14. Examination preparatory week conducted by the NRC and the facility licensee (I).

TJH

-30 08/23/25

15. Preliminary license applications, including any waiver/excusal requests, due (ES-2-2 C.1).

TJH

-14 09/08/25

16. Final license applications, including any waiver/excusal requests, due and Form 2.2-1 prepared (ES-2.2 C and E).

TJH

-7 09/15/25

17. Written examinations and operating tests approved by the NRC supervisor (C.9)

TJH

-7 09/15/25

18. Facility licensee management feedback on the examination requested by the NRC supervisor (C.10).

TJH

-7 09/15/25

19. Final applications reviewed; 10% of applications audited to confirm qualifications/eligibility (ES-2.2 G); and examination approval letter (Letter 2.3-1) and waiver/excusal letters sent.

TJH

-7 09/15/25

20. Written examination administration guidelines reviewed with the facility licensee (D.14).

TJH

-7 09/15/25

21. Approved scenarios and job performance measures distributed to NRC examiners (D.12).

TJH

  • Target dates are based on facility licensee-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted in coordination with the facility licensee.