Text
Constellation~
November 13, 2025 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop Pl-37 One White Flint North 11555 Rockville Pike Rockville MD 20852-2738 Calvert Cliffs Nuclear Power Plant, Unit No. 2 Renewed Facility Operating License No. DPR-69 NRC Docket No. 50-318 Christopher J. Smith Plant Manager Calvert Cl1tts Nuclear Power Plant 1650 Calvert Clitts Parkway Lusby. MD 20657 410-495-5205 Ottice 815-931*5902 Mobile wwwconstellation com christopher sm1th,aconstellat1on com TS 5.6.5
Subject:
Core Operating Limits Report for Unit 2, Cycle 26, Revision 1 Pursuant to Calvert Cliffs Nuclear Power Plant Technical Specification 5.6.5, the attached Core Operating Limits Report for Unit 2, Cycle 26, Revision 1 (Attachment 1), is provided for your records.
Please replace the Unit 2 Core Operating Limits Report in its entirety, with the attached Revision
- 1.
There are no regulatory commitments contained in this correspondence.
Should you have questions regarding this matter, please contact Mr. Larry D. Smith at (667) 313-6503.
Respectfully, Christopher J. Smith Plant Manager CJS/LDS/jj
Attachment:
(1)
Core Operating Limits Report for Unit 2, Cycle 26, Revision 1 cc:
(With Attachment)
NRC Project Manager, Calvert Cliffs NRC Regional Administrator, Region Sr. Resident Inspector, NRC Z. Barthel, MD-DNR