NRC Review of Kemmerer Unit 1 Construction Permit Application ACRS Subcommittee Meeting October 8-9, 2025
NRC Opening Remarks Joshua Borromeo, Branch Chief, NRR/DANU/UAL1 2
Kemmerer Unit 1 Construction Permit Application
- Part 50 application was submitted under 10 CFR Part 50, which governs the domestic licensing of production and utilization facilities
- Follows Licensing Modernization Project (LMP) methodology, as described in NEI 18-04.
- This methodology, endorsed by the NRC in Regulatory Guide 1.233, provides a framework for identifying licensing basis events, classifying safety-related SSCs, and evaluating defense-in-depth adequacy for non-light-water reactors.
- CP application generally aligns with the advanced reactor content of application (ARCAP) and technology inclusive content of application (TICAP) guidance 3
Agenda for October 8 & 9, 2025 October 8, 2025
- Design Overview
- LMP Overview
- LBE Identification and Scope
- Implementation of LMP Safety Classification Process October 9, 2025
- Safety Analysis Methods & Results
- DID & Integrated Risk Evaluation
- LBE Identification and Scope 4
Review Chronology
- March 28, 2024 Application Tendered
- April 10, 2024 Acceptance Review-Start
- May 21, 2024 Application Docketed
- May 22, 2024 - Present General Audit
- February 26, 2025 SE with Open Items
- August 29, 2025 Advanced SE
- October 3, 2025 PSAR Revision 1 5
Kemmerer Unit 1 Review Team - Core Team Joshua Borromeo NRR/DANU/UAL1 Licensing Branch Chief Candace de Messieres NRR/DANU/UTB1 Technical Branch Chief Mallecia Sutton NRR/DANU/UAL1 Natrium Lead Project Manager Stephanie Devlin-Gill NRR/DANU/UAL1 Sr. Project Manager Deion Atkinson NRR/DANU/UAL1 Project Manager Reed Anzalone NRR/DANU/UTB2 Natrium Lead Technical Reviewer Zachary Gran NRR/DANU/UTB2 Technical Reviewer Hanh Phan NRR/DANU/UTB2 Technical Reviewer Michelle Hart NRR/DANU/UTB2 Technical Reviewer Hakan Ozaltun NRR/DANU/UTB2 Technical Reviewer Alec Neller NRR/DANU/UTB2 Technical Reviewer Bruce Lin NRR/DANU/UTB2 Technical Reviewer Matt Hiser NRR/DANU/UAL1 Technical Reviewer Tracy Radel NRR/DANU/UTB2 Technical Reviewer Steve Jones NRR/DANU/UTB3 Technical Reviewer 6
CORE TEAM
Alex Siwy NRR/DANU/UTB2 Nuclear Engineer Amitava Ghosh NRR/DEX/ESEB Geotech. & Hazards Analysis Ken Mott NSIR/DPR/RLB Em. Preparedness Specialist Eddie Robinson NSIR/DPR/RLB Sr. Em. Preparedness Specialist Liliana Ramadan NRR/DEX/EEEB Electrical Engineer Nadim Khan NRR/DEX/EEEB Electrical Engineer Phil OBryan NRR/DANU/UARP Sr. Reactor Operations Engineer Hosung Ahn NRR/DEX/EXHB Hydrologist Jenise Thompson NRR/DEX/EXHB Geologist Kevin Quinlan NRR/DEX/EXHB Sr. Meteorologist Sarah Tabatabai NRR/DEX/EXHB Seismologist Brian Zaleski NSIR/DPCP/AAFPB Fitness-For-Duty Jay Robinson NRR/DRA/APLB Sr. Fire Protection Engineer Charles Moulton NRR/DRA/APLB Fire Protection Engineer Liz McAndrew-Benavides NSIR/DPCP/CSB Sr. Security Specialist (Cyber)
Travis Leach NSIR/DPCP/RPPB Security Specialist Yamir Diaz-Castillo NRR/DRO/IQVB Quality Assurance Dinesh Taneja NRR/DEX/EICB Sr. Electrical Engineer Lauren Nist NRR/DRO/IOLB Reactor Engineer Calvin Cheung NRR/DEX/EICB Electronics Engineer Lauren Nist NRR/DRO/IOLB Reactor Engineer Calvin Cheung NRR/DEX/EICB Electronics Engineer Shawn Harwell NMSS/REFS/FAB Financial Analyst Kosmas Lois NMSS/REFS/FAB Financial Analyst Nick Melly RES/DRA/FXHAB Sr. Fire Protection Engineer Matt McConnell NRR/DEX/ELTB Sr. Electrical Engineer Tom Scarbrough NRR/DEX/EMIB Sr. Mechanical Engineer Yuken Wong NRR/DEX/EIMB Sr. Mechanical Engineer Garry Armstrong NRR/DRO/IOLB Reactor Engineer Ryann Bass NRR/DANU/UTB2 Reactor Systems Engineer Shelia Ray NRR/DEX/EEEB Sr. Electrical Engineer Ting-Leung Sham NRR/DEX Sr. Advisor Brian Bettes NRR/DANU/UAL1 Project Manager Katie Wagner NRR/DANU/UAL1 Project Manager Contractor Argonne National Laboratory (ANL)
Contractor CNWRA/SWRI Structural Engineering 7
Kemmerer Unit 1 Review Team - Safety SMEs SAFETY SMEs
Acronyms ACRS - Advisory Committee on Reactor Safeguards ANL - Argonne National Lab ARCAP - advanced reactor content of application DID - Defense In Depth LBE - Licensing Basis Event LMP - Licensing Modernization Project NMSS - Office of Nuclear Material Safety and Safeguards NRC - Nuclear Regulatory Commission NRR - Office of Nuclear Reactor Regulation NSIR - Office of Nuclear Security and Incident Response PRA - Probabilistic Risk Assessment PSAR - Preliminary Safety Analysis Report TICAP - technology inclusive content of application RES - Office of Nuclear Regulatory Research SE - Safety Evaluation 8