Meeting Summary - July 31 2025 Public Meeting on Apco Joshua Falls Early Site Permit Pre-Application
ML25240B537
Person / Time
Site: 99902129
Issue date: 09/11/2025
From: Prosanta Chowdhury
NRC/NRR/DNRL/NRLB
To: Jardaneh M
Office of Nuclear Reactor Regulation
References
EPID L-2024-LRM-0143
Download: ML25240B537 (5)


Text

September 11, 2025 MEMORANDUM TO:

Mahmoud Jardaneh, Chief New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation FROM:

Prosanta Chowdhury, Senior Project Manager /RA/

New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

SUBJECT:

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE JULY 31, 2025, PUBLIC MEETING ON APPALACHIAN POWER COMPANY JOSHUA FALLS EARLY SITE PERMIT PRE-APPLICATION (EPID: L-2024-LRM-0143)

The U.S. Nuclear Regulatory Commission (NRC) held an Observation public meeting on July 11, 2025, with Appalachian Power Company (APCo) - a subsidiary of American Electric Power (AEP) - on its Joshua Falls Early Site Permit (ESP) Pre-Application. APCos presentation slides are found at NRCs Agencywide Documents Access and Management System Accession No. ML25204A215 (July 23, 2025).

During the meeting, APCo provided a status of their anticipated ESP application (ESPA) development. Specifically, the APCo presentation covered the following topics:

Project background and basis, under which APCo discussed: American Electric Power (AEP)/APCo overview; Joshua Falls small modular reactor project site; Project team overview; ESPA regulatory engagement timeline; Guidance utilized for site safety analysis report, environmental report, and emergency planning; and Quality Assurance Program Description, ESPA development status, under which APCo discussed: APCo siting study and results; meteorological tower; monitoring wells; and geotechnical borings, and Stakeholder engagement, under which APCo discussed community outreach and stakeholder engagement.

CONTACT:

Prosanta Chowdhury, NRR/DNRL 301-415-1647

M. Jardaneh 2

In response to an NRC staff question, APCo stated that the onsite meteorological tower would be completed by September of 2025 when the first-year data collection will begin; and that the second-year data collection is expected to be completed in September of 2027. APCo suggested that NRC staff visit the Jashua Falls site before October of 2025 to observe the geotechnical core borings and review samples that are already available onsite. APCo and NRC staff also discussed site visits by the NRCs emergency preparedness and environmental review staff. APCo requested to have the next public meeting in March of 2026, 12 months prior to the ESPA submittal, when they would provide results of subsurface exploration and characterization, as well as seismic hazard characteristics. Additionally, APCo proposed to start the Readiness Assessment (per NRC Office Instruction LIC-116, Preapplication Readiness Assessment; ML20104B698) in the Fall of 2026, approximately 6 months prior to the ESPA submittal.

There were no public comments. No regulatory decisions were discussed or made at this meeting.

The meeting was adjourned at 2:40 p.m. U.S. Eastern Time.

The public meeting notice posted on the NRC public website can be found under ML25204A233. Enclosure to this summary provides a list of the attendees of the meeting.

Project No. 99902129

Enclosure:

List of Attendees

Pkg: ML24353A261 Memo: ML25240B537 APCo Slides: ML25204A215 Meeting Notice: ML25204A233

  • via email NRR-106 OFFICE NRR/DNRL/NRLB: PM NRR/DNRL/NLIB: LA NRR/DNRL/NRLB: PM NAME PChowdhury SGreen*

RMaynard*

DATE 08/25/2025 08/28/2025 09/10/2025 OFFICE NRR/DNRL/NRLB: BC NRR/DNRL/NRLB: PM NAME MJardaneh*

PChowdhury DATE 09/10/2025 09/11/2025

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE JULY 31, 2025, PUBLIC MEETING ON APPALACHIAN POWER COMPANY JOSHUA FALLS EARLY SITE PERMIT PRE-APPLICATION LIST OF ATTENDEES July 31, 2025 Name Organization Prosanta Chowdhury U.S. Nuclear Regulatory Commission (NRC)

Alina Schiller NRC Michele Sampson NRC Ravi Penmetsa NRC Mahmoud Jardaneh NRC Alina Schiller NRC Nebiyu Tiruneh NRC Mary Richmond NRC Kenneth Mott NRC Jenise Thompson NRC Sarah Tabatabai NRC Frankie Vega NRC Edward Robinson NRC Jared Nadel NRC Kevin Quinlan NRC Maureen Conley NRC Jamole Skeeter NRC Tim Siefer Appalachian Power Company (APCo)

Mike Gallagher APCo Kimberly Hilty APCo Kaycee Graal APCo Virginia Limmiatis APCo Munsell Randall APCo Sam Roberts APCo Stephen Siefert APCo Grant Stuller APCo Joe Yeagler APCo Derek Young APCo Addison Hall Public

2 Name Organization Peter Carusona Public Alex Chereskin Public Elliott Gayle Public Marcus Hoffman Public Joseph Stoney Public Mario Bonet Public Jeff Fleck Public Rachel Turney Public Lisa Matis Public Debbie Meyers Public Bill Elzinga Public Harley Hutchins Public Ryan Henderson Public Walter Williams Public Jenny Weil Public Jesse Flythe Public Valentina Montaldo Public Jordan Burns Public Sam Musatow Public Hunter Young Public Noelle Coates Public Rob Mann Public Scott Blake Public George Porter Public Kevin Burlingham Public Allison Rohrs Public Stephanie Kane Public Brandt Modlin Public Neil Herman Public Michael Rinebold Public PJ Seel Public Julie Rautio Public Clarence Tolliver Public Joe Mize Public