NRC Email to Osage Nation, August 21, 2025
ML25234A162
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/21/2025
From: Goldstein B
NRC/NMSS/DREFS/ETRB1
To: Beaudoin A
Osage Nation
References
Download: ML25234A162 (1)


Text

From:

Beau Goldstein To:

andrew.beaudoin@osagenation-nsn.gov Cc:

Ashley Waldron; Colleen A. Bell; Desiree Davis

Subject:

Clinton Power Station Unit 1 License Renewal Date:

Thursday, August 21, 2025 12:32:31 PM Attachments:

Conclusion of Section 106 Consultation and Notice of Availability of the Final Supplemental Environmental Impact Statement for the Clinton Power Station Unit 1 License Renewal.msg image001.png Good day,

Thank you for your written correspondence dated August 8, 2025 regarding the Clinton Power Station (CPS) license renewal. During the proposed license renewal period, the applicant, Constellation Energy Generation (CEG), would continue operations at CPS; CEG proposes no new ground disturbing activities during the license renewal period. The notice of availability of the final supplemental environmental impact statement (FSEIS) was mailed to the Osage Nations Principal Chief on August 7, 2025 (letter dated August 5, 2025) and the letter was also sent by email to the Osage Nations Tribal Historic Preservation Officer on August 7, 2025 (see attached). The FSEIS is available at ML25212A224. Section 3.9 of the FSEIS includes a description of the Area of Potential Effects (APE), identification efforts conducted since the 1970s, and previously identified cultural resources. Additional project-related information can be found on the NRCs webpage:

https://www.nrc.gov/reactors/operating/licensing/renewal/applications/clinton.html

Although the sacred mound referenced in your correspondence dated August 8, 2025, is located outside the APE for the license renewal undertaking, CEG has several administrative controls and environmental procedures that aim to identify, protect, and minimize potential impacts to historic properties within the CPS site. Procedure SA-AA-117, Excavation, Trenching, and Shoring," outlines work practices for excavation, trenching, and shoring. The procedure defines Cultural, Historical, and Paleontological resources and aims to protect against impacts to sites and unanticipated discoveries of historic and cultural resources. The procedure is used in conjunction with CEGs Excavation Permit. Procedure EN-AA-103-F-02, Environmental Screening Checklist, oversees the environmental checklist process. The Land section of the procedure addresses potential impacts as a result of ground-disturbing activities. Procedure EN-AA-103, Environmental Review, oversees the aforementioned environmental checklist process. The document provides a process for screening proposed activities to determine if an activity requires further evaluation for environmental impacts and risk.

Last, EN-AA-103-0001, Environmental Evaluations, provides environmental personnel with direction on performing environmental evaluations to identify the environmental and regulatory impacts, if any, of proposed activities. Upon discovery of human remains,

CEG would engage their site security team, who would then engage the local law enforcement. If remains are over 100 years old, the Illinois SHPO would take over jurisdiction. If the remains are considered less than 100 years old, the coroner would maintain jurisdiction. In Illinois, human remains and associated burial artifacts are protected by the States Human Skeletal Remains Protection Act.

Should CEG propose previously unanalyzed ground disturbing activities at the CPS facility that require NRC authorization as part of a license amendment request or a subsequent license renewal application, consistent with its licensing process, the NRC staff will review the proposed activity at that time, including determining whether it is an undertaking per 36 CFR 800.3. If it is an undertaking, then the NRC would follow the National Historic Preservation Act (NHPA) Section 106 process, including initiating any necessary consultations.

Regards,

Beau J. Goldstein, RPA Environmental Project Manager U.S. Nuclear Regulatory Commission Office of Nuclear Materials Safety and Safeguards