www.holtec.com www.smrllc.com SMR-300 LWA Planning Updates August 27, 2025 Presented by: Phil Lashley & Clark Shurtleff SMR, LLC, A Holtec International Company Krishna P. Singh Technology Campus One Holtec Boulevard Camden, NJ 08104, USA

[Not Export Controlled]

holtec.com l smrllc.com l Page 2 Meeting Agenda

Introductions

Purpose Regulatory Basis Planned LWA Activities

holtec.com l smrllc.com l Page 3 Purpose Communicate SMRs plans for the Palisades SMR LWA Part 50 licensing pathway Construction Permit Application (CPA)

Operating License Application (OLA)

Limited Work Authorization (LWA) as part one of a two-part CPA Comprehensive Environmental Report submitted with LWA Reminder - Palisades SMR Existing Palisades SMR-300s Property Line

holtec.com l smrllc.com l Page 4 Application Timeline Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 CPA Part I CPA Part II OLA 2025 2026 2027 2028 2029 2030 Submittal NRC Review Submittal NRC Review Approval Approval Submittal NRC Review Approval Preapplication

~14-month LWA construction window

holtec.com l smrllc.com l Page 5 holtec.com l smrllc.com l Page 5 Mar 1972: 50.10(c) defines commencement of construction Feb 1974: proposed rule creates 50.10(e), LWA concept Apr 1974: NRC responds to public comments on proposed rule Apr 1974: NRC issues final rule Oct 2007: 50.10 revised to current text, established current LWA process

37 FR 5745

39 FR 4582

SECY-R-74-167

39 FR 14506

72 FR 57416 Regulatory History/Basis

holtec.com l smrllc.com l Page 6 SECY-R-74-167 discusses the basis for the LWA rule Encl 2, Page 8: There is a strong incentive to ensure that the rule establishing LWAs incorporates sufficient critical path work to effectively utilize the time saving that an LWA offers.

Encl 2, Page 12: Thus, provision has been made to ensure maximum effective use of the potential time saving offered by the LWA concept.

Encl 2, Page 15: The optimum course of action is one that results in the issuance of LWAs that include a well-defined scope of work large enough to take advantage of the potential time saving

holtec.com l smrllc.com l Page 7 1974 Regulations Allowable LWA activities:

LWA 50.10(e)(1):

Site preparation Construction support facilities SSCs not subject to 10 CFR 50 Appendix B (i.e., non-safety-related SSCs)

LWA 50.10(e)(3):

(for safety-related SSCs)

Subsurface preparation Installation of foundations

  • (SSCs: structures, systems, and components)

holtec.com l smrllc.com l Page 8 Current Regulations (2007 Rule)

Allowable LWA activities under current 50.10(d)(1):

Driving of piles Subsurface preparation Placement of backfill, concrete, or permanent retaining walls within an excavation Installation of foundations

holtec.com l smrllc.com l Page 9 holtec.com l smrllc.com l Page 9 Development of 10 CFR 50.10 Regulation Onsite Activities Allowed Without NRC Approval Onsite Activities Allowed With an LWA 1972 rule Site exploration N/A - LWA did not exist Exemptions could be considered 1974 rule Same as 1972 All non-safety-related work*

(LWA-1 activities)

Installation of safety-related foundations (LWA-2 activities) 2007 rule All non-construction activities defined in 50.10(a)(2)

Installation of safety-related foundations

  • 50.10(e)(1)(v) allowed the construction of structures, systems, and components which are not subject to the provisions of Appendix B.