August 20, 2025 MEMORANDUM TO FILE
SUBJECT:
DIABLO CANYON REVISION TO TECHNICAL SPECIFICATION 3.8.1 REQUIRED ACTION B.2 COMPLETION TIME USING RISK-INFORMED PROCESS FOR EVALUATIONS (EPID: L-2025-LLA-0124)
By \
letter dated July 31, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25212A192), Pacific Gas and Electric Company (the licensee) submitted the subject risk-informed process for evaluations (RIPE) license amendment request (LAR) for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon). The NRC staff held a LAR clarification call with the licensee on August 20, 2025, to discuss (1) severe weather procedures and (2) proposed technical specification insert language.
NRC
Participants:
Khadijah West, NRR/DSS/STSB Khoi Nguyen, NRR/DEX/EEEB Samson Lee, NRR/DORL/LPL4 Diablo Canyon
Participants:
James Morris Kenneth Schrader Matthew Shepard Nathan Barber Christopher Mehigan Docket Nos. 50-275 and 50-323