Request for Additional Information Decommissioning Funding Status Report
ML25224A228
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/12/2025
From: Tanya Hood
Reactor Decommissioning Branch
To: James Holloway
Dominion Energy Nuclear Connecticut
References
EPID L-2025-DFA-0013
Download: ML25224A228 (1)


Text

From:

Tanya Hood To:

james.holloway@dominionenergy.com Cc:

julie.h.hough@dominionenergy.com

Subject:

Millstone Unit 1 - Annual Decommissioning Funding Report Requested Additional Information Date:

Tuesday, August 12, 2025 12:28:00 PM Attachments:

RAI - Millstone Unit 1 - Annual Decommissioning Funding Report Review for CY 2024.pdf

SUBJECT:

MILLSTONE POWER STATION UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RE: DECOMMISSIONING FUNDING STATUS REPORT (EPID L-2025-DFA-0013)

Dear James E. Holloway

By letter dated March 26,2025 (Agencywide Documents Access and Management System Accession No. ML25093A222), Dominion Energy Nuclear Connecticut, Inc. (licensee),

submitted its annual report on the status of decommissioning funding for Millstone Power Station Unit 1 (Millstone Unit 1). The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information submitted and determined that additional information is required to complete its review. The requested additional information (RAI) is attached.

The draft questions were sent to Julie Hough of your staff to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. A response is expected within 30 days from the date of this email, September 12, 2025.

Tanya E. Hood Project Manager Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, Maryland 20852-2738 301-415-1387 Tanya.Hood@nrc.gov