Crane Clean Energy Center - Presentation for July 31, 2025, Public Outreach Meeting
ML25210A355
Person / Time
Issue date: 07/29/2025
From: Ballard B
NRC/NRR/DORL/LPL3
To:
References
Download: ML25210A355 (14)


Text

NRC Public Meeting Crane Clean Energy Center Potential Restart July 31, 2025

Agenda 2

Welcome, Ground Rules, Opening Remarks 6:00 - 6:10 pm NRC Presentation on Licensing and Inspection Activities 6:10 - 6:30 pm Statements from Elected Officials 6:30 - 6:45 pm Public Questions and Comments 6:45 - 8:00 pm Meeting Adjourned 8:00 pm

Meeting Opening

  • Welcome & Ground Rules
  • Opening Remarks
  • Introductions 3

NRC Presenters & Facilitators

  • Jamie Pelton, Acting Director, Division of Operating Reactor Licensing (DORL)
  • Ray McKinley, Deputy Director, Division of Operating Reactor Safety (DORS), Region I
  • Erin Carfang, Branch Chief, Engineering Branch 1, DORS, Region I

NRC Presentation Topics:

  • Crane Restart Panel
  • Licensing Activities
  • Noticing Process
  • Environmental Review
  • Inspection Activities
  • Decommissioning Activities 5

Crane Restart Panel

  • Oversees regulatory activities
  • Provides management for licensing and inspection activities
  • Proactively identifies and promptly resolves any challenges regarding restart
  • Focus on communications 6

Licensing Activities

  • Existing licensing processes are being used to review and evaluate potential restart
  • Safety reviews of restart-related licensing actions are ongoing
  • NRC enables the safe and secure use of nuclear technology through efficient and reliable licensing 7

Noticing Process

  • License amendment requests are noticed for comment and opportunity to request a hearing
  • 1 Notice - License amendments:

30-day comment / 60-day hearing request window 8

Environmental Review

  • The NRC and other federal agencies are required by the National Environmental Policy Act (NEPA) to assess the environmental effects of proposed actions before making decisions 9
  • Conclusions of the NRCs review of the environmental and related social and economic effects will be made publicly available

Inspection Activities

  • IMC-2562 provides a roadmap for potentially transitioning a decommissioning reactor to an operating plant
  • This guidance includes details on:

10 The Restart Panel Identifying and developing pathway for transition from decommissioning to potential operations Conducting inspections and reviews Outlining NRCs final assessment of plants readiness to restart operation

Inspection Activities

  • NRC Region I developed an inspection plan to assess the plants readiness to resume operations
  • Inspections will be risk-informed to focus on changes made to the plant, restoration to an operating state, and other items of interest
  • Existing NRC procedures will be used to perform the inspection activities
  • These inputs are critical for the NRCs final evaluation of the plants readiness to restart 11

TMI-2 Decommissioning

  • TMI-2 is in active decommissioning and can proceed in accordance with NRC regulations

- NRC inspects TMI-2 in accordance with Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program

  • Impacts from TMI-2 decommissioning on CCEC needs to be evaluated and mitigated
  • Inspections to assure continued safety of CCEC continue 12

Contact Information 13 Crane Public Webpage https://www.nrc.gov/info-finder/reactors/ccec.html Crane Restart Questions CraneRestartProject@nrc.gov Reminder There will be a second meeting hosted virtually on August 6, 2025, 4 - 5:30 PM. Register via the webinar link in the meeting notice.

14 Please silence phones, smart watches, and laptops.

Please keep your questions brief and concise to allow everyone to participate.

Come to the microphone when you see your ticket number.

Public Questions and Comments