ADVISORY COMMITTEE ON REACTOR SAFEGUARDS NUCLEAR REGULATORY COMMISSION Lee V. Gossick Executive Director for Operations WASHINGTON, D. C. 20555 March 12, 1976
Subject:
ACRS REVIEW OF SWESSAR-Pl/CESSAR-80 At its 191st meeting on March 4-6, 1976, the ACRS concluded that it would not be necessary for the Committee to make a specific review of the combined SWESSAR-Pl/CESSAR-80 option since it has previously re-viewed and reported on the SWESSAR-Pl and CESSAR-80 standard safety analysis reports and consideration was given to the interface between these facilities during this review.
(See ACRS Reports of February 11, 1976 and September 17, 1975).
The Committee plans to make a detailed review of the first application for a specific construction permit that utilizes the SWESSAR-Pl/CESSAR-80 combination.
3568 Sincerely, Dade W. Moeller Chairman