Westinghouse Columbia Fuel Fabrication Facility - Inspection Schedule for Calendar Year 2026
ML25176A208
Person / Time
Site: Westinghouse
Issue date: 06/26/2025
From: Michel C
NRC/RGN-II/DFRSS/FOB2
To: Stutts R
Westinghouse
References
Download: ML25176A208 (1)


Text

Roy Stutts Site Director, Columbia Fuel Fabrication Facility Westinghouse Electric Company 5801 Bluff Road Hopkins, SC 29061

SUBJECT:

WESTINGHOUSE COLUMBIA FUEL FABRICATION FACILITY - INSPECTION SCHEDULE FOR CALENDAR YEAR 2026

Dear Roy Stutts:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Columbia Fuel Fabrication Facility (CFFF) in calendar year 2026. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative or reactive inspections are not included in the schedule. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Thomas Vukovinsky at (404) 997-4622 with any questions or concerns you may have regarding this letter or the inspection schedule.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Eric C. Michel, Chief Fuels Oversight Branch 2 Division of Fuels, Radiological Safety, and Security Docket No. 07001151 License No. SNM-1107

Enclosure:

As stated cc w/ encl: Distribution via LISTSERV June 26, 2025 Signed by Michel, Eric on 06/26/25

ML25176A208 X

SUNSI Review X

Non-Sensitive

Sensitive X

Publicly Available

Non-Publicly Available OFFICE RII/DFRSS RII/DFRSS NAME T. Vukovinsky E. Michel DATE 6/26/2025 6/26/2025

Enclosure 2026 U.S. NUCLEAR REGULATORY COMMISSION INSPECTION/ACTIVITY PLAN FOR COLUMBIA FUEL FABRICATION FACILITY Dates Number of Inspectors Description/Inspection Procedures (IPs)

February 2 - 6 3

Nuclear Criticality Safety 1 (IP 88015)

Radiation Protection (IP 88030)

April 6 - 10 2

Operational Safety 1 (IP 88020)

June - to be determined 3

Evaluation of Exercises and Drills (IP 88051)

September 28 -

October 2 2

Nuclear Criticality Safety 2 (IP 88015)

Plant Modifications - Annual (IP 88070)

October 5 - 9 2

Physical Security (various IPs)

November 16 - 20 2

Operational Safety 2 (IP 88020)