June 11, 2025 MEMORANDUM TO: Michelle W. Hayes, Chief Licensing and Regulatory Infrastructure Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation FROM:
Victoria V. Huckabay, Senior Project Manager
/RA/
Licensing and Regulatory Infrastructure Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF THE MAY 8, 2025, PUBLIC MEETING WITH SMR, LLC (A HOLTEC INTERNATIONAL COMPANY) TO DISCUSS THE PLANNED FIRE PROBABILISTIC SAFETY ASSESSMENT FOR THE SMR-300 CONSTRUCTION PERMIT APPLICATION Meeting Information:
Vendor: SMR, LLC (SMR), A Holtec International Company (Holtec)
Docket No.: 99902049 Meeting
Title:
SMR-300 Fire Analyses Plan Meeting Date: May 8, 2025 Meeting Type: Partially Closed Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)
Accession No.: ML25125A035 Meeting Attendees: See Enclosure 1 for list of meeting attendees CONTACT: Victoria V. Huckabay, NRR/DNRL/NLIB (301) 415-5183
M. Hayes 2
Meeting Summary:
The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271). SMR (Holtec) provided an overview of its planned methodology for the fire probabilistic safety assessment (PSA) for the future SMR-300 application.
During the open portion of the meeting, SMR (Holtec) explained that it plans to provide a high-level overview of the planned fire PSA for the upcoming SMR-300 construction permit application submittal (ML25115A262). SMR (Holtec) discussed the planned asymmetrical dual-unit site layout at the existing Palisades site, which provides unique considerations for the fire PSA.
At the end of the open portion of the meeting, members of the public were invited to provide comments or ask the NRC staff questions pertaining to the scope of the meeting. Two members of the public provided comments that were outside the scope of this meeting. The only comment within the scope of the meeting was the one in which a member of the public expressed a concern that the majority of the information in this pre-application engagement was not publicly available.
Enclosures:
- 1. List of Attendees
- 2. Meeting Minutes - Closed Portion (non-public)
Package: ML25160A226 Letter: ML25160A228 : ML25160A228 via email NRC-001 OFFICE NRR/DNRL/NLIB:PM NRR/DNRL/NLIB:LA NRR/DNRL/NLIB BC NRR/DNRL/NLIB:PM NAME VHuckabay SGreen MHayes VHuckabay DATE 06/04/2025 06/09/2025 06/09/2025 06/11/2025
Enclosure 1 May 8, 2025, Public Meeting with SMR (Holtec) to Discuss the Planned Fire Probabilistic Safety Assessment for the SMR-300 Construction Permit Application Meeting Attendees Name Organization Victoria Huckabay U.S. Nuclear Regulatory Commission (NRC)
Reinaldo Rodriguez NRC Jennifer Beaton NRC Thinh Dinh NRC Charles Moulton NRC Steven Alferink NRC Mihaela Biro NRC Jay Robinson NRC Clark Shurtleff SMR (Holtec)
Hovhannes Hovhannisyan SMR (Holtec)
Jeff Miller SMR (Holtec)
Kevin Elliott SMR (Holtec)
Sarah Horacek SMR (Holtec)
Sean McCloskey SMR (Holtec)
Joseph Nithsdale U.K. Office for Nuclear Regulation Deric Tilson The Breakthrough Institute Donna Christiansen Institute for Nuclear Power Operations Michael Keegan Alfred Meyer Kathy Barnes