UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 MEMORANDUM TO: Michelle R. Rome, Chief Environmental Technical Review Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards FROM:
Jennifer A. Davis, Senior Project Manager Environmental Technical Review Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards
SUBJECT:
SUMMARY
OF MAY 15, 2025, MEETING BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION STAFF, PACIFIC GAS AND ELECTRIC COMPANY, AND THE yak tityu tityu yak tiłhini NORTHERN CHUMASH TRIBE On May 15, 2025, the U.S. Nuclear Regulatory Commission (NRC) staff held a virtual meeting with representatives from Pacific Gas and Electric Company (PG&E) and the yak tityu tityu yak tiłhini Northern Chumash Tribe (ytt) related to the proposed license renewal for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon). A list of NRC, PG&E, and ytt attendees is provided at the end of this summary.
The meeting began with a brief introduction by NRC staff, who noted that ongoing conversations conducted as part of its National Historic Preservation Act Section 106 consultations resulted in a mutual interest in providing the ytt access to culturally important areas of the Diablo Canyon site. The purpose of the meeting was to bring PG&E and ytt together to discuss a path forward for establishing a formal site access agreement and protocol. During the meeting, PG&E representatives outlined the framework for a pilot program to allow site access and answered questions from the ytt related to logistical considerations.
CONTACT:
Jennifer A. Davis, NMSS/REFS 301-415-3835 June 2, 2025 Signed by Davis, Jennifer on 06/02/25
M. Rome 2
LIST OF ATTENDEES:
yak tityu tityu yak tiłhini Northern Chumash Tribe Mona Olivas Tucker, Chairwoman Wendy Lucas, Vice President, ytt Non-profit Scott Lathrop, Chief Executive Officer, ytt Non-profit Becca Lucas Thomas, Executive Director, ytt Non-profit Pacific Gas and Electric Company Staff Tom Jones, Senior Director, Strategic Initiatives Trevor Rebel, Environmental Protection Manager Michael Taggart, Senior Consulting Cultural Resources Specialist Michael Wagoner, Environmental Permitting Supervisor U.S. Nuclear Regulatory Commission Staff Jennifer Davis, Senior Environmental Project Manager Kim Conway, Senior Environmental Project Manager
ML25150A040 (Memo)
OFFICE PM ETRB1 PM EPMB1 LA:REFS ETRB1 BC PM ETRB1 NAME JDavis KConway AWalker-Smith MRome JDavis DATE 05/30/2025 05/30/2025 05/30/2025 05/30/2025 06/2/2025