David P. Rhoades Senior Vice President Chief Nuclear Officer Constellation Energy Generation, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000237/2025501 AND 05000249/2025501
Dear David Rhoades:
On April 23, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3 and discussed the results of this inspection with C. Webb and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25
Enclosure:
As stated cc w/ encl: Distribution via LISTSERV May 8, 2025 Signed by Ziolkowski, Michael on 05/08/25
ML25126A205 Entire Report:
SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RIII/DRSS RIII/DRSS NAME JKutlesa:dc MZiolkowski DATE 05/07/2025 05/08/2025
Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Numbers:
05000237 and 05000249 License Numbers:
DPR-19 and DPR-25 Report Numbers:
05000237/2025501 and 05000249/2025501 Enterprise Identifier:
I-2025-501-0003 Licensee:
Constellation Energy Generation, LLC Facility:
Dresden Nuclear Power Station, Units 2 and 3 Location:
Morris, IL Inspection Dates:
April 7, 2025 to April 23, 2025 Inspectors:
D. Chyu, Project Engineer B. Jebbia, Operations Engineer T. McGowan, Emergency Preparedness Inspector M. Jones, Sr. Emergency Response Coordinator J. Kutlesa, Sr. Emergency Preparedness Inspector Approved By:
Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations No findings or violations of more than minor significance were identified.
Additional Tracking Items None.
3 INSPECTION SCOPES Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY 71114.07 - Exercise Evaluation - Hostile Action (HA) Event Inspection Review (IP Section 02.01 - 02.11) (1 Sample)
(1)
The inspectors observed the biennial hostile action event exercise and evaluated emergency plan performance on April 8, 2025. The exercise scenario simulated an event at the Dresden Nuclear Power Station that initiated with the declaration and notification of an Alert in response to a simulated land-based threat on site. The scenario conditions simulated the escalation of the significance of the event, requiring the declaration of a Site Area Emergency, and then a General Emergency, as well as the development of Protective Action Recommendations that were communicated to the required state and local government agencies.
71114.08 - Exercise Evaluation - Scenario Review Inspection Review (IP Section 02.01 - 02.04) (1 Sample)
(1)
The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on March 6, 2025.
4 OTHER ACTIVITIES - BASELINE 71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)
(1)
January 1, 2023, through March 31, 2025 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13)
(1 Sample)
(1)
January 1, 2023, through March 31, 2025 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14)
(1 Sample)
(1)
January 1, 2025, through February 28, 2025 INSPECTION RESULTS No findings were identified.
EXIT MEETINGS AND DEBRIEFS The inspectors verified that no proprietary information was retained or documented in this report.
On April 23, 2025, the inspectors presented the emergency preparedness biennial exercise inspection results to C. Webb and other members of the licensee staff.
5 DOCUMENTS REVIEWED Inspection Procedure Type Designation Description or Title Revision or Date Corrective Action Documents Resulting from Inspection AR 04856905 NRC ID Questions Following HAB Exercise 04/14/2025 71114.07 Procedures EP-AA-1000 Exelon Nuclear Standardized Radiological Emergency Plan 33 71114.08 Miscellaneous E250206t154858_RS-25-018 2025 Dresden Hostile Action Based NRC Graded Exercise Scenario 02/26/2025 LS-AA-2110 Monthly Data Elements for NRC ROP Indicator -
Emergency Response Organization (ERO) Drill Participation 01/01/2023 -
03/31/2025 LS-AA-2120 Monthly Data Elements for NRC ROP Indicator - Drill Exercise Performance 01/01/2023 -
03/31/2025 LS-AA-2130 Monthly Data Elements for NRC ROP Indicator - Alert and Notification System (ANS) Reliability 01/01/2023 -
03/31/2025 71151 Miscellaneous LS-AA-2135 Monthly Data Elements for NRC ROP Indicator -
Emergency Response Facility and Equipment Readiness (ERFER) 01/01/2025 -
02/28/2025