| To: | Burgum D, Colosimo R, Driscoll D, Hassett K, Lutnick H, Scarlett K, Vought R US Dept of Commerce, Office of the Secretary, US Dept of Interior, Office of the Secretary, US Dept of the Army, Office of the Assistant Secretary, Civil Works, US Dept of the Army, Office of the Secretary, US Executive Office of the President, Council on Environmental Quality (CEQ), US Executive Office of the President, Office of Mgmt & Budget (OMB) |
| References | |
| SRM-OGC250127-1-NMSS, CORR-25-0045 | |
| Download: ML25122A009 (1) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 4, 2025 The Honorable Doug Burgum Secretary of the Interior U.S. Department of the Interior 1849 C Street, NW Washington, DC 20240
Dear Secretary Burgum:
On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am providing the agency's status report as required by Section 5(c) of the January 20, 2025, Executive Order (EO) 14156, entitled "Declaring a National Energy Emergency." On March 13, 2025, in accordance with Section 5(a) of the EO, the NRC submitted our initial summary report listing planned or potential actions to facilitate the Nation's energy supply that may be subject to the Endangered Species Act (ESA) regulation on consultations during emergencies. Section 5(c) further directs the heads of all agencies to then submit a status report at least every 30 days for the duration of the national emergency following the submission of the initial summary report.
The NRC's status report is enclosed, reflecting the following changes since the April summary report:
The Section 7 ESA consultation for the subsequent license for the project, "Diablo Canyon Power Plant, Units 1 & 2 (Pacific Gas & Electric Co.) License Renewal Application," was completed on April 21, 2025, and has been removed from this list.
Tennessee Valley Authority submitted a Construction Permit Application for the Clinch River Nuclear Site in Oak Ridge, Tennessee on May 20, 2025, and this application has been moved from "Planned or Potential License Application Reviews," to "Current Licensing Reviews."
Per the direction in Section 5(c) of EO 14156, the NRC will continue to provide these status reports every 30 days for the duration of the declared national energy emergency. Please feel free to contact me or have your staff contact Mirela Gavrilas, Executive Director for Operations, via e-mail at Mirela.Gavrilas@nrc.gov or via telephone at 301-415-1700, if you have any questions or need additional information.
Sincerely, David A. Wright
Enclosure:
As stated
Identical letter sent to:
The Honorable Doug Burgum Secretary of the Interior U.S. Department of the Interior 1849 C Street, NW Washington, DC 20240 The Honorable Howard Lutnick Secretary of Commerce 1401 Constitution Ave, NW Washington, DC 20230 The Honorable Russell Vought Director, Office of Management and Budget New Executive Office Building 725 17th Street, NW Washington, DC 20503 The Honorable Kevin Hassett Director, National Economic Council Eisenhower Executive Office Building 1650 Pennsylvania Avenue, NW Washington, DC 20501 The Honorable Katherine Scarlett Chief of Staff, Council on Environmental Quality 730 Jackson Place, NW Washington, DC 20503 The Honorable Daniel Driscoll Secretary of the Army 101 Army Pentagon Washington, DC 20310-0101 The Honorable Robyn S. Colosimo Assistant Secretary of the Army for Civil Works, Acting 108 Army Pentagon Washington, DC 20310-0108