ADAMS Accession # ML25114A165 1
PAPERWORK REDUCTION ACT STATEMENT This letter contains mandatory information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB) approved these information collections (approval number 3150-0011). Send comments regarding this information collection to the Information Services Branch, Office of the Chief Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011)
Office of Management and Budget, Washington, DC 20503.
Public Protection Notification The NRC may not conduct nor sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number.
2 Document Request for Inspection 2025402-Grand Gulf Nuclear Station 71130.05, Protective Strategy and 71130.14, Target Set, June 9-13, 2025 Please provide the attached information to the inspection team for in-office inspection and review to arrive at our regional office no later than May 30, 2025.
Items may be provided on CERTREC/IMS, in hard copy, or a combination of both (CERTREC is preferred method). NOTE: DO NOT forward any information on flash drives as current NRC procedures prohibit using this type of media unless issued by the NRC. Please properly package and mark any SGI materials. If you have NON-SGI procedures or material that you can send via email, feel free to do so after you password protect them, raymond.lanfear@nrc.gov, Michael.hein@nrc.gov, and michael.stafford@nrc.gov. Thank you in advance for your assistance.
Send to: Attention, Ray Lanfear / Mike Hein / Michael Stafford U.S. Nuclear Regulatory Commission 1600 E. Lamar Blvd.
Arlington TX 76011-4511 In an effort to keep the requested information organized please submit the information to us using the same lettering system below. For example, all contacts and phone numbers for each the first inspection procedure should be in a file/folder titled 1-A, Applicable organization charts in file/folder 1-B, etc.
General: All Security Event Log entries since April 1, 2025. Security Program Procedure indices for all procedures, instructions, desk-top guides, standing orders, etc. The site Corrective Action Program procedure. The Safety Security Interface procedure. Please state what revision of your physical security plan you are currently using.
Document Request List
- 1. Licensee Protective Strategy and Performance Evaluation Program (71130.05), Issue Dated 01/01/2024 A.
Condition Reports written since September 12, 2022, that relate in any way to your Protective Strategy and/or Performance Evaluation Program, as related to the effectiveness of the onsite physical protection program and protective strategy, including drills and exercises. Please provide any additional Protective Strategy and Performance Evaluation Program CRs that may be written after this request while we are on site.
3 B.
Any Protective Strategy related procedure or lower tier document. Also, any procedure that covers contingency equipment available to the security force.
C.
Security Program Reviews, audits, or self-assessments which in any way address the Protective Strategy and Performance Evaluation Program since September 12, 2022.
D.
Provide documents/procedures that describe how the licensee will demonstrate and assess the effectiveness of the onsite physical protection program and protective strategy, to include: any implementing procedure or lower tier tool related to your PEP, any procedures or lower tier tool related to design and implementation of tactical drills and FOF exercise program.
E.
Provide any procedure or lower tier document that governs your training and use of exercise controllers and the mock adversary force.
Please be prepared to provide the following items upon our arrival onsite.
F.
Quarterly drill records w/participants, to include scenarios and critiques, since October 1, 2023. Also include tabletop drill records.
G.
Annual exercise records, to include scenarios and critiques, since January 1, 2023.
H.
A complete list of personnel that will be used as controllers during the exercise that you will be conducting during the week of the inspection.
I.
Exercise controller and mock adversary force training and records.
J.
Any exercise scenarios that will or may be used during the exercise that you will be conducting during the week of the inspection.
K.
MILES weapons issue procedures and MILES no play areas.
L.
Engineering standoff calculations related to DBT requirements related to human fragility for AR/ASOs.
M.
Manufacturer or vendor manuals or data sheets supporting various barriers, BREs, etc.
N.
Basis document for security force and adversary timelines, and a list of all timelines.
O.
Current Target Set list.
4 P.
Unattended Openings map and analysis.
Q.
Documented copy of liaison established with LLEA R.
Protective Strategy Brief, to include maps/overview of site footprint, with structures and OCA/PA boundaries and delays, and interior delays.
S.
All current compensatory measures.
LAST ITEM FOR 71130.05
- 2. Review of Power Reactor Target Sets (71130.14), Issue Dated 03/09/2023 A.
All non-SGI procedures that relate to the Target Set identification, maintenance, and development.
B.
List of the Target Set Expert Panel members (names, qualifications, and positions).
C.
Response to security event operations procedure.
D.
Any procedure listed as a credited operator action (OMA) in the target sets.
E.
Results of the last two target set expert panel reviews (meeting minutes).
F.
Corrective action program (CAP) procedures and CRs associated with Target Sets and the program since the last triennial target set inspection (last 3 years).
G.
A list of any issue/condition reports since the last target set inspection (3 years) directly related to target sets and/or Safety/Security interface.
H.
Any design change packages or modification packages that affected target sets.
I.
A summary or list of any changes that have occurred to the target sets since the last inspection.
J.
A copy of the sites Safety / Security Interface procedure.
Items needed On-Site during the Inspection Week:
K.
Access to all NON-SGI and SGI procedures related to Target Sets.
5 L.
Site Target Sets, Protective Strategy, Contingency Plan.
M.
A POC knowledgeable in Target Sets and the protective strategy.
LAST ITEM FOR 71130.14