Report of Changes to Big Rock Point ISFSI Security Plan, Revision 10
ML25084A049
Person / Time
Site: Big Rock Point  File:Consumers Energy icon.png
Issue date: 03/19/2025
From: Noval W
Holtec Decommissioning International
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
HDI BRP-2025-007
Download: ML25084A049 (1)


Text

SAFEGUARDS INFORMATION HOLTEC DECOMMISSIONI N G INTERNATIONA L Krishna P. Singh Technology Campus, 1 Holtec Blvd., Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 HDI BRP 2025-007 March 19, 2025 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Big Rock Point Docket No. 50-155 and 72-043 Facility Operating License No. DPR-06 10 CFR 50.54(p)(2)

Subject:

Report of Changes to Big Rock Point ISFSI Security Plan, Revision 1 O In accordance with Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Section 54, Conditions of licenses, paragraph (p)(2), (10 CFR 50.54(p)(2)), Holtec Decommissioning International, LLC (HDI), is submitting on behalf of Holtec Palisades, LLC, Revision 10 to the Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI) Security Plan. The Enclosure contains a description and the basis for each change included in Revision 10 to the ISFSI Security Plan. The BRP ISFSI security Plan, Revision 10, is provided as an Attachment to the Enclosure.

The changes made to the BRP ISFSI Security Plan were analyzed as required by 10 CFR 50.54(p )(2). The analysis concluded that the changes do not decrease the safeguards effectiveness of the BRP ISFSI Security Plan. Accordingly, this revision is submitted under the provisions of 10 CFR 50.54(p)(2).

Information contained in the Enclosure and Attachment to this document has been classified as Safeguards Information (SGI). Therefore, HDI requests that this information be withheld from public disclosure in accordance with 10 CFR 73.22, Protection of Safeguards Information:

Specific Requirements.

This letter contains no new commitments and no revised commitments.

Should you have any questions or require additional information, please contact Tom LaCroix, BRP Project Manager at (231) 237-2302.

Respectfully, William Noval William Noval Digitally signed by William Noval ON: cn=William Noval, o=HOI, ou=Regulatory Affair.s, email=w.noval@holtec.com Date: 2025 03 19 09:22:29 *04'00' Director, Regulatory Affairs Holtec Decommissioning International, LLC NOTICE. The Attachment and Enclosure to this letter contains "Safeguards Information." Upon separation of the Attachment and Enclosure from this letter this page becomes "DECONTROLLED."

SAFEGUARDS INFORMATION

HDI BRP 2025-007 Page 2 of 2 SAFEGUARDS INFORMATION

Attachment:

Big Rock Point ISFSI Security Plan Change Summary

Enclosure:

Big Rock Point ISFSI Security Plan, Revision 10 (SGI) cc:

NRC Region Ill Regional Administrator, w/o Attachment & Enclosure NRC Senior Resident Inspector-Big Rock Point, w/o Attachment & Enclosure NRC Project Manager - Big Rock Point, w/o Attachment & Enclosure NOTICE: The Attachment and Enclosure to this letter contains "Safeguards Information." Upon separation of the Attachment and Enclosure from this letter this page becomes "DECONTROLLED."

SAFEGUARDS INFORMATION

SAFEGUARDS INFORMATION Attachment to HDI BRP 2025-007 Big Rock Point ISFSI Security Plan Change Summary NOTICE: The Attachment contains "Safeguards Information." Upon separation of the Attachment from this page this page becomes "DECONTROLLED."