Response to Order EA-NRR-2025-0013 Rensselaer Polytechnic Institute Reactor Critical Facility, Docket 50-225, Renewed Facility Operating License No. CX-22
ML25058A089
Person / Time
Site: Rensselaer Polytechnic Institute
Issue date: 02/26/2025
From: Ji W
Rensselaer Polytechnic Institute
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
EA-NRR-2025-0013
Download: ML25058A089 (1)


Text

SCHOOL OF ENGINEERING Rensselaer Polytechnic Institute School of Engineering JEC 3004, 110 8th Street l Troy, NY 12180-3590 www.eng.rpi.edu/

February 26, 2025 10 CFR 2.202 Attn: Director, Office of Nuclear Reactor Regulation Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Response to Order EA-NRR-2025-0013 Rensselaer Polytechnic Institute Reactor Critical Facility, Docket 50-225, Renewed Facility Operating License No. CX-22

Reference:

EA-NRR-2025-0013, Order Modifying Licenses and Establishing Initial Final Safety Analysis Report Update Due Dates Consistent with the Non-Power Production or Utilization Facility License Renewal Rule On February 6, 2025, the Nuclear Regulatory Commission issued the referenced order, EA-NR-2025-0013. This order modified certain Non-Power Utilization Facilities (NPUFs) licenses and established initial final safety analysis report update dues dates for certain NPUFs consistent with the NPUF Facility License Renewal Rule dated December 30, 2024. This response is to indicate that the Rensselaer Polytechnic Institute Reactor Critical Facility consents to the order and does not request a hearing.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on __02/26/2025__

Sincerely, Dr. Wei Ji, Facility Director Professor of Mechanical, Aerospace, and Nuclear Engineering School of Engineering Rensselaer Polytechnic Institute, Troy, NY 12180 cc: Ms. Jessica Lovett, U.S. Nuclear Regulatory Commission Reactor Advisory Committee