CCN: 25-09 10 CFR 50.59 10 CFR 72.48 February 7, 2025 U.S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station (PBAPS), Units 1, 2, and 3 and PBAPS Independent Spent Fuel Storage Installation (ISFSI)
Facility Operating License No. DPR-12 Subsequent Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-171, 50-277, 50-278, and 72-29 (ISFSI)
Subject:
Biennial 10 CFR 50.59 and 10 CFR 72.48 Reports for the Period 1/1/2023 through 12/31/2024 For the reporting period of 1/1/2023 through 12/31/2024, there were no plant changes implemented for Peach Bottom Units 1, 2, 3, or ISFSI using a 10 CFR 50.59 Evaluation or 10 CFR 72.48 Evaluation. Therefore, no reports are required pursuant to 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2).
There are no new regulatory commitments contained in this transmittal.
If you have any questions or require additional information, please contact Amy Huber at (267) 533-7247.
Sincerely, Martin A. Bonifanti Site Vice President Peach Bottom Atomic Power Station cc:
USNRC Region I, Regional Administrator USNRC Project Manager, PBAPS USNRC Senior Resident Inspector, PBAPS Director, Pennsylvania Department of Environmental Protection, Bureau of Radiation Protection Bonifanti, Martin A.
Digitally signed by Bonifanti, Martin A.
Date: 2025.02.03 11:36:09