ML25030A236
Jump to navigation
Jump to search
| ML25030A236 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 01/30/2025 |
| From: | NRC/RGN-II |
| To: | |
| References | |
| Download: ML25030A236 (1) | |
Text
Form 2.1-1 Examination Preparation Checklist Facility: ____Vogtle 1&2___________________________
Date of Examination: December 2, 2024 Developed by: Written:
Facility NRC
//
Operating:
Facility NRC Target Date*
Task Description Chief Examiners Initials
-240
- 1. Examination administration date confirmed (A.1-5). For NRC-prepared examinations, arrangements are made for the facility licensee to submit reference materials (B.4, C.4.g and F).
KK
-210
- 2. NRC examiners and facility licensee contact assigned (B.1 and C.1-3).
KK
-210
- 3. Facility licensee contact briefed on examination security and other requirements (D.4). As applicable, the facility licensee contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facility licensees prescreening process (ES-4.1 A.1.a and ES-4.1 B.2).
KK
-210
- 4. Reference material due for NRC-prepared examinations (F).
N/A
-210
- 5. Examination kick-off call held (C.4). The NRC sends the corporate notification letter (A.5).
KK
-195
- 6. Written examination outline developed by the NRC and sent to the facility licensee contact (must be on the examination security agreement) (B.2, ES-4.1 A.1.b and ES-4.1 A.2.a).
N/A
-150
- 7. Operating test outlines and checklists due: Forms 1.3-1, 2.3-1, 3.2-1, 3.2-2, 3.3-1, and 3.4-1, as applicable (B.6). Facility licensee provides a draft operating test administration schedule to the NRC (B.18).
KK
-136
- 8. Operating test outlines reviewed by the NRC and feedback provided to the facility licensee (ES-2.3).
KK
-100
- 9. NRC-prepared examinations approved by the NRC supervisor and forwarded for facility licensee review (ES-2.3).
N/A
-75
- 10. Proposed examinations (written, JPMs, and scenarios, as applicable) and outline forms; quality checklists and supporting documentation (including Forms 2.3-2 and 2.3-4 and any Form 2.3-1, 1.3-1, and 3.4-1 updates); and reference materials due.
KK
-60
- 11. Preliminary waiver/excusal requests due (ES-2.2 E.1).
KK
-50
- 12. Written examination and operating test reviews completed (ES-2.3). The NRC supervisors authorization to proceed with the facility review granted (ES-2.3 D).
KK
-50
- 13. Examination review results discussed between the NRC and the facility licensee (B.14).
KK
-35
- 14. Examination preparatory week conducted by the NRC and the facility licensee (I).
KK
-30
- 15. Preliminary license applications, including any waiver/excusal requests, due (ES-2-2 C.1).
KK
-14
- 16. Final license applications, including any waiver/excusal requests, due and Form 2.2-1 prepared (ES-2.2 C and E).
KK
-7
- 17. Written examinations and operating tests approved by the NRC supervisor (C.9)
KK
-7
- 18. Facility licensee management feedback on the examination requested by the NRC supervisor (C.10).
KK
-7
- 19. Final applications reviewed; 10% of applications audited to confirm qualifications/eligibility (ES-2.2 G); and examination approval letter (Letter 2.3-1) and waiver/excusal letters sent.
KK
-7
- 20. Written examination administration guidelines reviewed with the facility licensee (D.14).
KK
-7
- 21. Approved scenarios and job performance measures distributed to NRC examiners (D.12).
KK
- Target dates are based on facility licensee-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted in coordination with the facility licensee.
Form 5.1-1 Postexamination Check Sheet Postexamination Check Sheet Facility: Vogtle 1&2 Dates of Examination: Dec 2 - 6, 2024 Dec 11, 2024 Activity Description Date Complete
- 1. *Received postexamination package from facility licensee and verified complete. (ES-4.4) 12/16/24
- 2. *Reviewed and incorporated any necessary facility and applicant written examination comments. NRC grading of written examination completed. (ES-4.4) 12/20/24
- 3. *Reviewed and incorporated any necessary facility and applicant operating test comments. NRC grading of operating test completed.
(ES-3.6) 12/20/24
- 4. *Completed NRC chief examiner review of operating test and written examination grading. (ES-3.6 and ES-4.4) 12/26/24
- 5. Completed licensing official review.
1/15/25
- 6. Mailed licenses, preliminary results, and pass letters.
1/15/25
- 7. Notified facility licensee of results.
1/15/25
- 8. Issued the examination report (refer to Operator Licensing Manual Chapter (OLMC) 510, Operator Licensing Examination Reports).
1/24/25
- 9. Returned reference material after final resolution of any informal NRC staff reviews, hearing demands, or both.
N/A
- 10. Performed examination recordkeeping activities (refer to OLMC 520, Operator Licensing Examination Records and Documentation, and Management Directive 3.53, NRC Records and Document Management Program).
1/27/25
- Activity may not be applicable for a retake examination. If this activity does not apply, place an N/A in the Date Complete column.