WAmeren MISSOURI December 16, 2024 ULNRC-06889 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
10 CFR 50.55a DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.
Callaway Plant RENEWED FACILITY OPERATING LICENSE NPF-30 CALLAWAY INSERVICE TESTING PROGRAM AND SNUBBER PROGRAM PLANS FOR THE FIFTH INSERVICE TESTING (IST) INTERVAL Pursuant to 10 CFR 50.55a(t)(5)(i), and in accordance with 10 CFR 50.55a(t)(7), Union Electric Company (Ameren Missouri) is submitting the "Inservice Testing Program" and the "Snubber Examination, Testing, and Service Life Monitoring Program Plan" for Callaway's fifth inservice testing (1ST) interval for which the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code), 2020 Edition, is applicable.
Callaway's fifth 1ST interval begins December 20, 2024. Ameren Missouri is providing these 1ST program plans for information only, in accordance with the above-noted requirements.
The "Inservice Testing Program" is provided in Enclosure 1 which includes NRC-approved 1ST relief requests associated with the fifth testing interval (ADAMS Accession No. ML24144A04). The "Snubber Examination, Testing, and Service Life Monitoring Program Plan" is provided in.
This letter does not contain new commitments. If there are any questions, please contact Thomas Elwood at 314-225-1905.
Sincerely, ft~
Jacob Kuhlenberg Director, Nuclear Plant Engineering 8315 County Road 459 Steedman, MO 65077 AmerenMissouri.com
ULNRC-06889 December 16, 2024 Page 2 of 4 ESS
- Inservice Testing Program : Snubber Examination, Testing, and Service Life Monitoring Program Plan
ULNRC-06889 December 16, 2024 Page 3 of 4 cc:
Mr. John Monninger Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. M. Chawla Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O8B1A Washington, DC 20555-0001
ULNRC-06889 December 16, 2024 Page 4 of 4 Index and send hardcopy to QA File A160.0761 Hardcopy:
Certrec Corporation 6500 West Freeway, Suite 400 Fort Worth, TX 76116 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)
Electronic distribution for the following can be made via Other Situations ULNRC Distribution:
F. M. Diya K. C. Scott T. M. Hart J. G. Beck T. A. Witt T. B. Elwood NSRB Secretary STARS Regulatory Affairs Mr. Jay Silberg (Pillsbury Winthrop Shaw Pittman LLP)
Ms. Kathleen McNelis (Public Service Commission)
Ms. Claire Eubanks (Public Service Commission)