Response to Korea Hydro & Nuclear Power Company, Ltd Letter Regarding Revising the Duration of Design Certifications
ML24232A191
Person / Time
Site: 99901453
Issue date: 08/21/2024
From: Glisan J, Beverly Smith
NRC/NRR/DNRL/NLIB
To: Suh J
Korea Hydro Nuclear Power Co, Ltd
References
Download: ML24232A191 (1)


Text

Mr. Jeong-Kwan Suh, Project Manager Korea Hydro & Nuclear Power Company, Ltd.

70-1312-gil, Yuseong-daero, Yuseong-gu Daejeon, 34101, South Korea

SUBJECT:

RESPONSE TO KOREA HYDRO & NUCLEAR POWER COMPANY, LTD LETTER REGARDING REVISING THE DURATION OF DESIGN CERTIFICATIONS

Dear Mr. Suh:

I am responding to your letter dated July 22, 2024, expressing Korea Hydro & Nuclear Power Co., Ltd.s support for a proposal that is before the U.S. Nuclear Regulatory Commission (NRC) to extend the duration of NRC design certifications from 15 to 40 years in general and for all active design certifications at the time of the rulemaking (Agencywide Documents Access and Management System Accession No. ML24206A254). You also expressed you would like for the NRC to consider a similar change for standard design approvals. Once the Commission issues direction on the proposal, the NRC staff will act accordingly.

If you have any questions or need additional information, please contact Jordan Glisan via email at Jordan.Glisan@nrc.gov.

Sincerely, Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No. 99901453 August 21, 2024 Lee, Samuel signing on behalf of Smith, Brian on 08/21/24

ML24232A191

  • via e-concurrence NRR-106 OFFICE NRR/DNRL/NLIB: PM NRR/DNRL/NLIB: LA NAME JGlisan SGreen DATE 08/19/2024 08/20/2024 OFFICE NRR/DNRL/NLIB: BC NRR/DNRL: D NAME MHayes BSmith: SLee for DATE 08/21/2024