Independent Spent Fuel Storage Installation, Final Safety Analysis Report Update
ML24200A174
Person / Time
Site: 07200011
Issue date: 06/27/2024
From: Ed Miller
Sacramento Municipal Utility District (SMUD)
To:
Division of Fuel Management, Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
DPG 24-276
Download: ML24200A174 (1)


Text

Powering forward. Together.

June 27, 2024

  • DPG 24-276 ATTN: Document Control Desk Director, Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Rancho Seco Independent Spent Fuel Storage Installation Renewed Materials License No. SNM-2510 Docket 72-11 RANCHO SECO ISFSI FINAL SAFETY ANALYSIS REPORT UPDATE Attention: Shana Helton This letter serves as the 24-month update of the Final Safety Analysis Report (FSAR) for the Rancho Seco Independent Spent Fuel Storage Installation (ISFSI) as required by 10 CFR 72.70(c)(6).

On June 26, 2024, Revision 11 to the Rancho Seco ISFSI FSAR was submitted. Since the date of the last FSAR update on June 26, 2024, no changes were made to the Rancho Sec_o Quality Manual. A biennial evaluation was conducted in accordance with 10 CFR 72.48 to make FSAR revisions to allow a delegated representative of Manger, Rancho Seco Assets to be the Radiation Health Protection Manager. This update was submitted as Revision 11 to the ISFSI FSAR on June 26, 2024, under DPG 24-275, "Rancho Seco ISFSI Final Safety Analysis Report, Revision 11 ".

No other safety evaluations performed in accordance with 10 CFR 72.48 required an update to the ISFSI FSAR.

No other analyses performed by the Commission have identified the need to update the ISFSI FSAR.

No change to the facility has occurred that requires the ISFSI FSAR to be updated.

,}Aj S 5 2 !)

µ0~52~

Rancho Seco Nuclear Generating Station I 14440 Twin Cities Road I Herald, CA 95638-9799 I 916.452.3211 I smud.org

By signature below, the Sacramento Municipal Utility District certifies that the above is true and correct. If you, or members of your staff, have questions requiring additional information or clarification you may contact me at (916) 732-6239.

Sincerely,

~~

Ernest Miller Manager, Rancho Seco Assets cc: