Application for Revision of Certificate of Compliance No. 9186 for the Model No. S-6213 Shipping Container - Acknowledgment of Receipt Letter
ML24190A076
Person / Time
Site: 07109186
Issue date: 07/11/2024
From: Melendez-Colon D
Storage and Transportation Licensing Branch
To: Kampen J
US Dept of Energy, National Nuclear Security Admin
References
EPID L-2024-LLA-0081
Download: ML24190A076 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Jedidiah H. Kampen, Naval Reactors Engineer U. S. Department of Energy National Nuclear Security Administration 1000 Independence Avenue SW Washington, DC 20585-1000

SUBJECT:

APPLICATION FOR REVISION OF CERTIFICATE OF COMPLIANCE NO. 9186 FOR THE MODEL NO. S-6213 SHIPPING CONTAINER -

ACKNOWLEDGMENT OF RECEIPT LETTER

Dear Jedidiah Kampen:

By letter dated June 11, 2024 (Agencywide Documents Access and Management System

[ADAMS] Accession No. ML24166A230), Naval Reactors submitted an application for revision to certificate of compliance (CoC) No. 9186 for the Model No. S-6213 shipping container. The application includes a request to add the S1B power unit as a new authorized contents for the Model No. S-6213 shipping container.

This letter informs you that the application appears to contain the necessary information to begin our technical review. We have established a schedule for the technical review of your amendment request. We understand Naval Reactors has a need by date of February 1, 2025.

Please note that the U.S Nuclear Regulatory Commission (NRC) staffs technical review of your submittal may identify issues that could require that you provide additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by December 2024. The schedule includes the issuance, if needed, of a request for additional information (RAI) by October 1, 2024, and, provided that we receive your responses to the RAI within 30 days after its issuance, we anticipate issuing the CoC/Safety Evaluation Report by January 2025. The NRC staff estimates that completing the review of your submittal will require approximately 1,057 staff hours. We will promptly communicate significant schedule and/or cost changes, if any.

Your application has been assigned Cost Activity Code/Enterprise Project Identification Number 001029/L-2024-LLA-0081. Please reference this number and Docket No. 71-9186 in any future correspondence associated with this request.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.July 11, 2024 If you have any questions regarding this communication, please contact me at (301) 415-7295, or via email to Daneira.Melendez-Colon@nrc.gov.

Sincerely, Daneira Meléndez Colón, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-9186 EPID No. L-2024-LLA-0081 Signed by Melendez-Colon, Daneira on 07/11/24