MONTHYEARInspection Manual Change Notice 24-034, Table of Contents for Inspection Manual Change Notice 24-0342024-10-31031 October 2024 Table of Contents for Inspection Manual Change Notice 24-034 Inspection Manual Change Notice 24-033, Table of Contents for Inspection Manual Change Notice 24-0332024-10-29029 October 2024 Table of Contents for Inspection Manual Change Notice 24-033 Inspection Manual Change Notice 24-031, Table of Contents for Inspection Manual Change Notice 24-0312024-10-25025 October 2024 Table of Contents for Inspection Manual Change Notice 24-031 Inspection Manual Change Notice 24-032, Table of Contents for Inspection Manual Change Notice 24-0322024-10-25025 October 2024 Table of Contents for Inspection Manual Change Notice 24-032 Inspection Manual Change Notice 24-030, Table of Contents for Inspection Manual Change Notice 24-0302024-10-23023 October 2024 Table of Contents for Inspection Manual Change Notice 24-030 ML24150A2392024-07-29029 July 2024 IMC 2562 Light-Water Reactor Inspection Program for Restart of Reactor Facilities Following Permanent Cessation of Power Operations Inspection Manual Change Notice 24-023, Table of Contents for Inspection Manual Change Notice 24-0232024-07-29029 July 2024 Table of Contents for Inspection Manual Change Notice 24-023 Inspection Manual Change Notice 24-022, Table of Contents for Inspection Manual Change Notice 24-0222024-07-26026 July 2024 Table of Contents for Inspection Manual Change Notice 24-022 Inspection Manual Change Notice 24-021, Table of Contents for Inspection Manual Change Notice 24-0212024-07-24024 July 2024 Table of Contents for Inspection Manual Change Notice 24-021 Inspection Manual Change Notice 24-018, Table of Contents for Inspection Manual Change Notice 24-0182024-07-0101 July 2024 Table of Contents for Inspection Manual Change Notice 24-018 Inspection Manual Change Notice 24-016, Table of Contents for Inspection Manual Change Notice 24-0162024-05-30030 May 2024 Table of Contents for Inspection Manual Change Notice 24-016 Inspection Manual Change Notice 24-015, Table of Contents for Inspection Manual Change Notice 24-0152024-05-16016 May 2024 Table of Contents for Inspection Manual Change Notice 24-015 ML24044A2152024-05-10010 May 2024 IMC 0306 Planning, Scheduling, Tracking, and Reporting of the Reactor Oversight Process (ROP) Inspection Manual Change Notice 24-014, Table of Contents for Inspection Manual Change Notice 24-0142024-05-10010 May 2024 Table of Contents for Inspection Manual Change Notice 24-014 ML24033A2992024-04-23023 April 2024 IMC 2562 Light-Water Reactor Inspection Program for Restart of Reactor Facilities Following Permanent Cessation of Power Operations Inspection Manual Change Notice 24-013, Table of Contents for Inspection Manual Change Notice 24-0132024-04-23023 April 2024 Table of Contents for Inspection Manual Change Notice 24-013 Inspection Manual Change Notice 24-012, Table of Contents for Inspection Manual Change Notice 24-0122024-04-22022 April 2024 Table of Contents for Inspection Manual Change Notice 24-012 Inspection Manual Change Notice 24-010, Table of Contents for Inspection Manual Change Notice 24-0102024-03-14014 March 2024 Table of Contents for Inspection Manual Change Notice 24-010 Inspection Manual Change Notice 24-009, Table of Contents for Inspection Manual Change Notice 24-0092024-03-0808 March 2024 Table of Contents for Inspection Manual Change Notice 24-009 Inspection Manual Change Notice 24-008, Table of Contents for Inspection Manual Change Notice 24-0082024-03-0404 March 2024 Table of Contents for Inspection Manual Change Notice 24-008 Inspection Manual Change Notice 24-007, Table of Contents for Inspection Manual Change Notice 24-0072024-02-12012 February 2024 Table of Contents for Inspection Manual Change Notice 24-007 Inspection Manual Change Notice 24-005, Table of Contents for Inspection Manual Change Notice 24-0052024-02-0707 February 2024 Table of Contents for Inspection Manual Change Notice 24-005 Inspection Manual Change Notice 24-006, Table of Contents for Inspection Manual Change Notice 24-0062024-02-0707 February 2024 Table of Contents for Inspection Manual Change Notice 24-006 ML23318A2002024-01-0909 January 2024 IMC 0307 Appendix D, Resident Inspector Retention and Recruitment Program Monitoring and Assessment Inspection Manual Change Notice 24-002, Table of Contents for Inspection Manual Change Notice 24-0022024-01-0909 January 2024 Table of Contents for Inspection Manual Change Notice 24-002 ML23307A0092024-01-0202 January 2024 IMC 2515 Appendix E, Inspection Program Modifications During Public Health Emergencies or Other Conditions Restricting Inspector Onsite Presence Inspection Manual Change Notice 24-001, Table of Contents for Inspection Manual Change Notice 24-0012024-01-0202 January 2024 Table of Contents for Inspection Manual Change Notice 24-001 Inspection Manual Change Notice 23-039, Table of Contents for Inspection Manual Change Notice 23-0392023-12-21021 December 2023 Table of Contents for Inspection Manual Change Notice 23-039 Inspection Manual Change Notice 23-037, Table of Contents for Inspection Manual Change Notice 23-0372023-12-15015 December 2023 Table of Contents for Inspection Manual Change Notice 23-037 ML23318A4262023-12-15015 December 2023 IP 71111.21N.04 Age-Related Degradation ML23234A1762023-12-14014 December 2023 IMC 0309 Reactive Inspection Decision Basis for Power Reactors Inspection Manual Change Notice 23-035, Table of Contents for Inspection Manual Change Notice 23-0352023-12-0606 December 2023 Table of Contents for Inspection Manual Change Notice 23-035 Inspection Manual Change Notice 23-034, Table of Contents for Inspection Manual Change Notice 23-0342023-11-15015 November 2023 Table of Contents for Inspection Manual Change Notice 23-034 Inspection Manual Change Notice 23-033, Table of Contents for Inspection Manual Change Notice 23-0332023-11-0606 November 2023 Table of Contents for Inspection Manual Change Notice 23-033 ML23214A3822023-10-31031 October 2023 IMC 0308, Attachment 2, Technical Basis for Inspection Program ML23222A1682023-10-31031 October 2023 IMC 0611 Appendix D Guidance for Problem Identification and Resolution Inspection Reports Inspection Manual Change Notice 23-032, Table of Contents for Inspection Manual Change Notice 23-0322023-10-31031 October 2023 Table of Contents for Inspection Manual Change Notice 23-032 ML23226A2232023-10-16016 October 2023 IP 71111.08 Inservice Inspection Activities Inspection Manual Change Notice 23-030, Table of Contents for Inspection Manual Change Notice 23-0302023-10-16016 October 2023 Table of Contents for Inspection Manual Change Notice 23-030 Inspection Manual Change Notice 23-028, Table of Contents for Inspection Manual Change Notice 23-0282023-09-19019 September 2023 Table of Contents for Inspection Manual Change Notice 23-028 Inspection Manual Change Notice 23-026, Table of Contents for Inspection Manual Change Notice 23-0262023-08-28028 August 2023 Table of Contents for Inspection Manual Change Notice 23-026 ML23191A5172023-08-18018 August 2023 IP 71111.07 Heat Exchanger/Sink Performance Inspection Manual Change Notice 23-024, Table of Contents for Inspection Manual Change Notice 23-0242023-08-17017 August 2023 Table of Contents for Inspection Manual Change Notice 23-024 Inspection Manual Change Notice 23-023, Table of Contents for Inspection Manual Change Notice 23-0232023-08-11011 August 2023 Table of Contents for Inspection Manual Change Notice 23-023 Inspection Manual Change Notice 23-021, Table of Contents for Inspection Manual Change Notice 23-0212023-07-27027 July 2023 Table of Contents for Inspection Manual Change Notice 23-021 Inspection Manual Change Notice 23-020, Table of Contents for Inspection Manual Change Notice 23-0202023-07-14014 July 2023 Table of Contents for Inspection Manual Change Notice 23-020 ML23192A8372023-07-12012 July 2023 IP 71111.21N.04 Age-Related Degradation ML23151A5462023-06-26026 June 2023 IMC 2515 Appendix C, Special and Infrequently Performed Inspections Inspection Manual Change Notice 23-018, Table of Contents for Inspection Manual Change Notice 23-0182023-06-26026 June 2023 Table of Contents for Inspection Manual Change Notice 23-018 ML23055B0532023-06-26026 June 2023 IMC 2515 Appendix E, Inspection Program Modifications During Public Health Emergencies or Other Conditions Restricting Inspector Onsite Presence 2024-07-29
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
NRC INSPECTION MANUAL IOLB INSPECTION PROCEDURE 83728
MAINTAINING OCCUPATIONAL EXPOSURES ALARA
83728-01 INSPECTION OBJECTIVE
To determine whether the licensee has established and is maintaining adequate programmatic controls and procedures that reasonably ensure compliance with the requirements of 10 CFR Part 20 to maintain exposures as-low-as-is-reasonably-achievable (ALARA).
83728-02 INSPECTION REQUIREMENTS
If desired, this procedure may be performed concurrent with supplemental procedure IP 79703, Control and Monitoring of Radiological Source Term.
Inspection procedure 71121.02, ALARA Planning Controls, addresses routine implementation of the ALARA program. Therefore, it should be used concurrent with this program review.
02.01 Management Controls. Review the licensees procedures that implement the ALARA program. Verify that there is sufficient management oversight and support station-wide to assure that program requirements are well understood and that radiologically significant activities receive the appropriate management review.
02.02 Audits and Appraisals. Review the results of audits and evaluations performed by or for the licensee since the last inspection of the licensee's ALARA program implementation and its effectiveness, and the adequacy of the licensee's commitments and corrective actions.
02.03 Worker Awareness and Involvement. Determine whether workers are aware of, and involved in, the ALARA program.
02.04 ALARA Goals and Objectives. Determine whether the licensee is establishing and tracking ALARA goals and objectives.
02.05 ALARA Results. Review measures of the effectiveness of the ALARA program and determine whether the program is effective.
Issue Date: 04/17/00 83728 02.06 Outage Preparation and Planning. Review and determine the adequacy of licensee ALARA planning and preparation for refueling and maintenance outages.
83728-03 INSPECTION GUIDANCE
General Guidance
Additional guidance can also be obtained by reviewing the EPRI TR-107991,Radiation-Field Control Manual - 1997 Revision and NCRP report no. 120, Dose Control at Nuclear Power Plants, (issued December 30, 1994).
Specific Guidance
03.01 Management Controls
- a. Verify that the licensee has developed detailed, implementing instructions for all personnel involved in the ALARA program.
- b. Verify that individuals understand their authorities and responsibilities under the ALARA program. Interview several workers, first-line supervisors and managers in various plant crafts groups.
- c. Determine if licensee management has established an ALARA committee, or some other process or means to facilitate the station-wide implementation and support of the ALARA program.
Review the ALARA committee charter, interview selected members and review selected meeting minutes to verify that the Committee is meeting its intended function.
03.02 Audits and Appraisals
- a. Review reports of required audits, evaluations, ALARA committee (process) reviews, etc., performed since the last inspection, that examine the licensee's performance in meeting ALARA commitments and that recommend changes in the program. Look particularly for those audits that probe for programmatic weaknesses and assess the quality of the program. Focus upon licensee follow up actions for identified deficiencies. Are corrective actions timely and technically acceptable?
Requirements for reviews and audits normally are contained in the technical specifications. Audit teams should include someone knowledgeable in ALARA programs (Regulatory Guide 1.146 and ANSI/ASME N45.2.23-1978, Section 2.2).
- b. Review reports of other audits, appraisals, assessments, and evaluations, that may provide information on program quality.
83728 Issue Date: 04/17/00 03.03 Worker Awareness and Involvement. Attachment 2 of the baseline inspection procedure IP 71121 for the Occupational Radiation Safety cornerstone addresses routine implementation of the ALARA program, including observations of work activities and discussions with workers. Therefore, the baseline procedure, with additional samples to determine extent of condition, should be used for this portion of the ALARA program review.
03.04 ALARA Goals and Objectives
- a. Attachment 2 of the baseline inspection procedure for the Occupational Radiation Safety cornerstone addresses routine implementation of the ALARA program, including establishing and managing dose goals.
- b. Goals and objectives may be qualitative and quantitative.
Means should be provided to track progress toward the goals and to take action on the findings. Goals may be set for the facility as a whole and for different divisions or groups within the facility. Facility goals might include, for example, a total annual collective dose (person-rem) value, and a percentage reduction in preventive maintenance time in high radiation areas.
03.05 ALARA Results
- a. As a minimum, consider the total annual collective dose (person-rem) for the facility. Determine whether that collective dose is increasing or decreasing, and whether it is higher or lower than the collective dose for other facilities of the same type and generating capacity.
Consider reasons for increases or higher than average doses and discuss licensee's plans in relation to relatively high collective doses, or upward dose trends.
- b. Successes in meeting ALARA goals and objectives (Sections 02.04 and 03.04) provide other measures of ALARA program effectiveness.
03.06 Planning and Preparation for Outages. Review representative records and discuss outage planning with licensee representatives, and observe activities to verify necessary planning and preparations. Examples of areas that may be examined include:
- a. Plans for integrating supplemental contract HP technicians for outage job coverage duties, including method of ensuring adequate supervisor control over the contractors activities.
- b. Special training, including use of mockup training.
- c. Increased supplies, including clothing, temporary shielding materials, etc.
Issue Date: 04/17/00 83728
- d. ALARA considerations, including work package review by health physics personnel, dose reduction methods, and radwaste reduction.
- e. Adequacy of licensee controls and monitoring of contractor work standards, equipment, and practices.
- f. Early involvement of health physics group and knowledge of work to be performed. This involvement should include an examination of the adequacy of plant review of special (non-routine, seldom used) procedures and infrequent evolutions that have the potential for creating radiological hazards.
Lessons learned from previous industry experiences/evolutions are utilized.
- g. Provisions for engineering controls, such as auxiliary ventilation systems to minimize the need to use respiratory protection equipment (Regulatory Guide 8.8, Section C.2.d).
- h. Examination of indicators of management support, or lack of support, for radiation protection planning such as:
- 1. Approvals of activities needed for radiation protection during the outage.
- 2. Inclusion of radiation protection staff in outage planning meetings.
- i. For plants planning significant tasks (e.g., 10-year in-service inspection) for the first time, determination of the extent to which the outage experience of other similar plants is being used in the planning process.
- j. Adequacy of licensees ability to accurately project job doses. Accurate estimation of job doses requires good lines of communication with other departments (e.g, maintenance and engineering) who planned and will be performing the work, availability of up-to-date dose rate surveys, detailed documentation of lessons learned from similar evolutions performed at this or other facilities, preplanning of jobs done well in advance of actual work to permit thorough job dose analysis, and detailed scheduling of jobs to ensure that dose rates during job performance are not impacted by other jobs being performed nearby.
83728-04 RESOURCE ESTIMATE
It is estimated that about 25-30 hours of onsite inspection hours will be needed to complete this procedure. No additional time is needed for multi-unit sites.
END
83728 Issue Date: 04/17/00