09 - NRC - 50.55a Rulemaking Update
ML24172A303
Person / Time
Issue date: 06/27/2024
From: Michael Benson
NRC/NRR/DNRL/NVIB
To:
Shared Package
ML24172A301 List:
References
Download: ML24172A303 (1)


Text

ASME Rulemaking Update

Michael Benson NRR/DNRL/NVIB

2024 Industry/NRC Materials Technical Exchange Meeting Rockville, MD June 25 - 27, 2024 10 CFR 50.55a Codes and Standards

  • Incorporation by reference

- American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section III (design and construction rules )

- ASME Boiler and Pressure Vessel Code,Section XI (inservice inspection rules)

- ASME code cases and code case regulatory guides (various requirements)

- ASME Operation and Maintenance Code (inservice testing rules)

- ASME NQA-1 (quality assurance requirements)

- Institute of Electrical and Electronics Engineers standards (various requirements)

  • Two rulemaking packages currently in process
  • One rulemaking package in the planning stages (see 6/26 presentation)
  • Planned rulemaking activities website
  • Title 10, Code of Federal Regulations

2 Code Case Regulatory Guides

- Issued March 6, 2023

- Public comment period closed June 16, 2023

  • Scope

- Draft Regulatory Guide (RG) 1.84, Revision 40 (Section III code cases, ML22195A282)

- Draft RG 1.147, Revision 21 (Section XI code cases, ML22195A284)

- Draft RG 1.192, Revision 5 (Operation and Maintenance code cases, ML22196A063)

- Code of Record interval (SECY-21- 0029 and SRM-SECY-21- 0029)

  • Status

- 12 public comment submissions, including Nuclear Energy Institute, ASME, NRC licensees, and private citizens

- Staff addressed all comments; the rulemaking package is under agency review

- Final rule expected August 2024

3 2021/2022 Editions Rulemaking

- Issued August 8, 2023

- Public comment period closed October 23, 2023

  • Scope

- 2021 Edition, ASME Section III

- 2021 Edition, ASME Section XI

- 2022 Edition, ASME Operation and Maintenance

- Select ASME code cases in 50.55a(a)(1)(iii)

  • Status

- 3 public comment submissions, including Nuclear Energy Institute, ASME, and Inser vice Testing Owners Group

- Staff addressed all comments; the rulemaking package is under agency review

- Final rule expected January 2025

4 Significant Public Comments

  • Code Case Regulatory Guides and Code of Record Interval Rule

- Include Code Case N-752-1 in RG 1.147

- Reevaluate Section XI Edition required for use of Code Case N-921

- Rules on use of later Code Editions (see 10 CFR 50.55a(f)(4)(iv) and (g)(4)(iv))

  • 2021/2022 Editions Rule

- Remove condition requiring preservice examination of steam generator tubes

- Remove condition requiring pressure testing of repaired/replaced mechanical joints

- Reevaluate existing Section XI conditions related to Master Curve RT T0

- Remove condition on Code Case N-770 regarding inspection of optimized weld overlay locations

5 November 8, 2023 6