REACTOR ALLEGATIONS SUBSTANTIATED BY CY RECEIVED*: January 2020 - April 2024 Site 2020 2021 2022 2023 2024 ARKANSAS 1 & 2 1
2 BEAVER VALLEY 1 & 2 1
1 BRAIDWOOD 1 & 2 1
BROWNS FERRY 1, 2 & 3 1
CATAWBA 1 & 2 2
1 COLUMBIA PLANT 3
COMANCHE PEAK 1 & 2 2
COOPER 1
DAVIS-BESSE 1
DIABLO CANYON 1 & 2 1
1 DRESDEN 2 & 3 1
FARLEY 1 & 2 1
FERMI 2
FITZPATRICK 1
1 1
GRAND GULF 1
2 1
HARRIS 2
HATCH 1 & 2 2
LIMERICK 1 & 2 1
1 MCGUIRE 1 & 2 1
MILLSTONE 2 & 3 1
NINE MILE POINT 1 & 2 1
NORTH ANNA 1 & 2 1
OCONEE 1, 2, & 3 5
PALO VERDE 1, 2, & 3 1
PERRY 1
QUAD CITIES 1 & 2 1
RIVER BEND 1
1 1
7 SALEM/HOPE CREEK 3
2 2
SEQUOYAH 1 & 2 1
SOUTH TEXAS 1 & 2 5
1 ST LUCIE 1 & 2 1
1 2
SUMMER 1
SURRY 1 & 2 2
1 SUSQUEHANNA 1 & 2 1
TURKEY POINT 3 & 4 1
1 VOGTLE 1 & 2 1
2 VOGTLE 3 & 4 +
8 12 8
1 WATERFORD 1
1 WATTS BAR 1 & 2 1
4 1
3 WOLF CREEK 1
+ Vogtle 3 began Operations on August 3, 2022, and Vogtle 4 began Operations on July 28, 2023.
- This table refers to allegations from sources external to the NRC for which NRC has substantiated at least one concern.
NON-OP REACTOR ALLEGATIONS SUBSTANTIATED BY CY RECEIVED*: January 2020 - April 2024 Site 2020 2021 2022 2023 2024 CRYSTAL RIVER 1
3 INDIAN POINT 1, 2 & 3 1
OYSTER CREEK 1
2 PALISADES 1
PILGRIM 1
- This table refers to allegations from sources external to the NRC for which NRC has substantiated at least one concern.
FUEL FACILITY ALLEGATIONS SUBSTANTIATED BY CY RECEIVED*: January 2020 - April 2024 Site 2020 2021 2022 2023 2024 BWXT 1
NUCLEAR FUEL SERVICES 1
3 2
- This table refers to allegations from sources external to the NRC for which NRC has substantiated at least one concern.