Clinch River CP Saf Docs - Additional Information Need_Early Excavation Exemption Request
ML24075A322
Person / Time
Site: 99902056
Issue date: 03/15/2024
From:
NRC
To:
NRC/NRR/DNRL
References
Download: ML24075A322 (3)


Text

From:

Allen Fetter Sent:

Friday, March 15, 2024 3:11 PM To:

Schiele, Raymond Joseph Cc:

ClinchRiver-CPSafDocsPEm Resource; Greg Cranston; Jenise Thompson; Zuhan Xi; Luissette Candelario-Quintana

Subject:

Additional Information Need_Early Excavation Exemption Request Attachments:

Additional Information Need_Early Excavation Exemption_Geology &

Geotechnical.pdf

Ray, Attached is the written additional information need that was identified during our March 5, 2024 virtual audit on the Early Excavation Exemption Request.

Please let me know if a clarification call with staff is needed.

Thanks, Allen H. Fetter, Senior Project Manager U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of New and Renewed Licenses New Reactor Licensing and Infrastructure Branch Washington, D.C.

301-415-8556 (Office) 301-385-5342 (Mobile)

Hearing Identifier:

ClinchRiver_CPSafDocs_Public Email Number:

12 Mail Envelope Properties (MW4PR09MB93966C83F722BB38222D9DBD85282)

Subject:

Additional Information Need_Early Excavation Exemption Request Sent Date:

3/15/2024 3:11:07 PM Received Date:

3/15/2024 3:11:10 PM From:

Allen Fetter Created By:

Allen.Fetter@nrc.gov Recipients:

"ClinchRiver-CPSafDocsPEm Resource" <ClinchRiver-CPSafDocsPEm.Resource@nrc.gov>

Tracking Status: None "Greg Cranston" <Gregory.Cranston@nrc.gov>

Tracking Status: None "Jenise Thompson" <Jenise.Thompson@nrc.gov>

Tracking Status: None "Zuhan Xi" <Zuhan.Xi@nrc.gov>

Tracking Status: None "Luissette Candelario-Quintana" <luissette.candelario-quintana@nrc.gov>

Tracking Status: None "Schiele, Raymond Joseph" <rjschiele@tva.gov>

Tracking Status: None Post Office:

MW4PR09MB9396.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 555 3/15/2024 3:11:10 PM Additional Information Need_Early Excavation Exemption_Geology & Geotechnical.pdf 81487 Options Priority:

Normal Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Nuclear Regulatory Commission (NRC) Audit on the Tennessee Valley Authority (TVA) Early Excavation Exemption Request for the Clinch River Nuclear Site Additional Information Need During the NRC-TVA March 5, 2024, virtual audit pertaining to geologic and geotechnical information on TVAs early excavation information request for the Clinch River Site (ADAMS Accession No. ML24058A144), the NRC staff noted that more information related to the excavation activities and processes would be needed to support the safety review.

NRC staff needs to better understand of how TVA intends to address ESP-006 permit conditions and COL action items that could be associated with the excavation process. The staff also requests a written strategy or explanation for the excavation process that should include excavation decision points. Specifically, decision points for conditions such as large voids, unexpected geologic features and water infiltration, etc., that could affect the proposed excavation process, require additional mitigation measures or alter the excavation approach in such a way that might require NRC approval, observation or inspection.