Nuclear Regulatory Commission Vendor Inspection Report of Korea Hydro & Nuclear Power Co., 99902120/2024201
ML24067A200
Person / Time
Site: 99902120
Issue date: 03/08/2024
From: Kerri Kavanagh
NRC/NRR/DRO/IQVB
To: Ryu R
Korea Hydro & Nuclear Power Co, Ltd
References
EPID I-2024-201-0001 IR 2024201
Download: ML24067A200 (10)


Text

Ryan Ryu, Deputy Director Korea Hydro & Nuclear Power Co.

8100 Boone Blvd., Suite 210 Vienna, VA 22182

SUBJECT:

NUCLEAR REGULATORY COMMISSION VENDOR INSPECTION REPORT OF KOREA HYDRO & NUCLEAR POWER CO. 99902120/2024-201

Dear Mr. Ryu:

On February 1, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an inspection at the of Korea Hydro & Nuclear Power Co.s (hereafter referred to as KHNP) facility in Vienna, VA. The purpose of this limited-scope routine inspection was to assess KHNPs compliance with selected portions of Title 10 of the Code of Federal Regulations (10 CFR) 73.21, Physical Protection of Plants and Materials and Commission Order EA-13-033, Order Imposing Safeguards Information Protection Requirements for Access to Safeguards Information. Specifically, this inspection evaluated KHNPs implementation of activities associated with the protection of Safeguards Information (SGI) associated with the APR1400 design certification. The enclosed report presents the results of the inspection. This NRC inspection report does not constitute NRC endorsement of KHNPSs overall SGI protection program.

During this inspection, the NRC inspection team observed the physical protections and programmatic processes utilized by KHNP to protect safeguards information. Based on the results of this inspection, the NRC inspection team found the implementation of your SGI protection program met the requirements imposed on you by the NRC. No findings of significance were identified.

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Rule of Practice, a copy of this letter, its enclosure(s), and your response will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS), accessible at http://www.nrc.gov/reading-rm/adams.html.

March 8, 2024

R. Ryu 2

Sincerely, Kerri Kavanagh, Chief Quality Assurance Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation Docket No.: 99902120 EPID No.:

I-2024-201-0001

Enclosure:

Inspection Report No.

99902120/2024-201 and Attachment Signed by Kavanagh, Kerri on 03/08/24

ML24067A200 NRR-106 OFFICE NRR/DRO/IQVB NRR/DRO/IQVB NRR/DRO/IRAB NAME DZhang KKavanagh BHughes DATE 3/7/2024 3/8/2024 3/7/2024 Enclosure U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION DIVISION OF REACTOR OVERSIGHT VENDOR INSPECTION REPORT Docket No.:

99902120 Report No.:

99902120/2024-201 Vendor:

Korea Hydro & Nuclear Power Co.

Ryan Ryu, Deputy Director ryanryu.pe@gmail.com Nuclear Industry Activity:

Nuclear Industry Activity: KHNPs facility in Vienna, Virginia is a management and marketing facility for KHNP licensing and marketing activities associated with the APR1400 power plant design in the US. They oversee KHNPs interface with the USNRC and with potential customers for the APR1400 in the US. They also maintain the necessary records for licensing and marketing activities, and previously served to oversee subcontractor efforts in support of licensing and design in the US during those phases of the APR1400 designs lifecycle.

Inspection Dates:

February 1, 2024 Vendor Location:

8100 Boone Blvd., Suite 210 Vienna, VA 22182 Inspection Team Leader:

Deanna Zhang NRR/DRO/IQVB Approved by:

Kerri Kavanagh, Chief Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation

2 EXECUTIVE

SUMMARY

Korea Hydro & Nuclear Co.

99902120/2024-201 The U.S. Nuclear Regulatory Commission (NRC) staff conducted a vendor inspection at the Korea Hydro & Nuclear Co. (hereafter referred to as KHNP) facility in Vienna, VA to verify that it had implemented an adequate Safeguards Information (SGI) protection program that complies with selected portions of Title 10 of the Code of Federal Regulations (10 CFR) 73, Physical Protection of Plants and Materials. This inspection specifically evaluated KHNPs implementation of SGI protection activities associated with maintaining the physical security of the information by access control and the intellectual security by screening the users of the SGI prior to granting access to it. The NRC inspection team conducted this inspection onsite on February 1, 2024.

The following regulations serve as the bases for the NRC inspection:

10 CFR 73.21, Protection of Safeguards Information: Performance Requirements 10 CFR 73.22, Protection of Safeguards Information: Specific Requirements Commission Order EA-13-033, Order Imposing Safeguards Information Protection Requirements for Access to Safeguards Information During this inspection, the NRC inspection team implemented inspection procedure (IP) 81811, Protection of Safeguards Information By Design Certification Applicants and Vendors, dated April 8, 2020.

In accordance with the IP, the NRC inspection team conducted the following activities:

Observed the physical security measures KHNP has in place to control access to the SGI; Reviewed records for retention, distribution, and destruction of SGI; Reviewed KHNP procedures for governing the handling of SGI and granting access to individual and subcontractor firm; Conducted interviews with KHNP staff to assess knowledge of processes and procedures; Reviewed personnel records for screening of users to assess the decisions to grant access to individuals; and Reviewed corrective actions implemented to address minor issues identified in NRCs inspection report 052000046/2019-201 dated August 23, 2019.

The NRC inspection team concluded that KHNPs SGI protection policies and implementing procedures comply with the applicable requirements of 10 CFR Part 73 and the Commissions Order and that KHNPs personnel are implementing these policies and procedures effectively.

No findings of significance were identified.

3 REPORT DETAILS 1.

Information Protection System

a. Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the information protection system to ensure it conforms to the applicable measures specified in Title 10 the Code of Federal Regulations (10 CFR) 73.22, Protection of Safeguards Information: Specific requirements, and the subsequently published Commission Order, EA-13-033, Order Imposing Safeguards Information Protection Requirements for Access to Safeguards Information.

The NRC inspection team discussed the program with KHNPs management and staff. The attachment to this inspection report lists the KHNP documents reviewed, and the KHNP staff interviewed by the NRC inspection team.

b. Observations and Findings No findings of significance were identified.

c. Conclusion

The NRC inspection team concluded that KHNP established its Information Protection System in accordance with the regulatory requirements of 10 CFR 73.22. Based on the limited sample of observations, the NRC inspection team also determined that KHNP is effectively implementing its policies and procedures associated with the Information Protection System. No findings of significance were identified.

2. Access to SGI
a. Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the access to SGI program to verify compliance with the requirements of 10 CFR 73.22(b). The NRC inspection team verified that KHNPs program conforms to the following:

Personnel must have a need-to-know Personnel must have favorably completed a criminal history records review Personnel are deemed trustworthy, based on a Commission approved review method Personnel meet the exception requirements of 10 CFR 73.59 The NRC inspection team discussed the program with KHNPs management and staff. The attachment to this inspection report lists the KHNP documents reviewed, and the KHNP staff interviewed by the NRC inspection team.

b. Observations and Findings No findings of significance were identified.

4

c. Conclusion

The NRC inspection team concluded that KHNP established its access to SGI system in accordance with the with the regulatory requirements of 10 CFR 73.22(b). Based on the limited sample of information reviewed, the NRC inspection team also determined that KHNP is effectively implementing its policies and procedures associated with access to SGI.

No findings of significance were identified.

3.

Protection of SGI

a. Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the protection of SGI to verify compliance with the requirements of 10 CFR 73.22(c)(1) and 10 CFR 73.22(c)(2). The NRC inspection team observed the storage area, cabinet, locks, and work area where SGI is utilized to confirm that these items met the requirements of these regulations.

The NRC inspection team discussed the program with KHNPs management and staff. The attachment to this inspection report lists the KHNP documents reviewed, and the KHNP staff interviewed by the NRC inspection team.

b. Observation and Findings No findings of significance were identified.

c. Conclusion

The NRC inspection team concluded that KHNP established its protection of SGI system in accordance with the regulatory requirements of 10 CFR 73.22(c)(1) and 10 CFR 73.22(c)(2).

Based on its observations, the NRC inspection team determined that KHNP is effectively implementing its policies and procedures associated with its protection of SGI. No findings of significance were identified.

4.

Processing, Reproducing, and Transmitting SGI

a. Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the processing, reproducing and transmitting of SGI to verify compliance with the requirements of 10 CFR 73.22(g)(1), 10 CFR 73.22(g)(2), 10 CFR 73.22(e), and 10 CFR 73.22(f)(1). Specifically, the NRC inspection team reviewed KHNPs procedures and processes for handling, packaging and receipt, process for sending and receiving, and for reproduction against the requirements in these regulations and the Order. The NRC inspection team also reviewed the corrective actions implemented to address the minor issues identified in the NRCs inspection report No. 052000046/2019-201 dated August 23, 2019, associated with (1) confirming that that contractors had appropriately destroyed SGI documents prior to removing the contractors from KHNP SGI procedures, and (2) documenting audits of two sub-contractor facilities and confirm, and confirmed that the corrective actions have been adequately implemented.

5

b. Observation and Findings No findings of significance were identified.

c. Conclusion

The NRC inspection team concluded that KHNP established its protection of SGI system in accordance with the regulatory requirements of 10 CFR 73.22(g)(1), 10 CFR 73.22(g)(2), 10 CFR 73.22(e), and 10 CFR 73.22(f)(1). Based on its observations, the NRC inspection team determined that KHNP is effectively implementing its policies and procedures associated with the processing, reproducing and transmitting of SGI. No findings of significance were identified.

5.

Marking of SGI a.

Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the marking of SGI to verify compliance with the requirements of 10 CFR 73.22(d)(1), and 10 CFR 73.22(d)(2). Specifically, the NRC inspection team sampled SGI KHNP documents and verified that these documents and transmittal cover letters are properly marked in accordance with regulatory requirements.

The NRC inspection team discussed the program with KHNPs management and staff. The attachment to this inspection report lists the KHNP documents reviewed, and the KHNP staff interviewed by the NRC inspection team.

b.

Observation and Findings No findings of significance were identified.

c.

Conclusion The NRC inspection team concluded that KHNP established its protection of SGI system in accordance with the regulatory requirements of 10 CFR 73.22(d)(1), and 10 CFR 73.22(d)(2). Based on its observations, the NRC inspection team determined that KHNP is effectively implementing its policies and procedures associated with marking of SGI. No findings of significance were identified.

6.

Removal of SGI and Destruction a.

Inspection Scope The NRC inspection team reviewed KHNPs policies and implementing procedures that govern the removal and destruction of SGI for KHNP to verify compliance with the requirements of 10 CFR 73.22(h) and 10 CFR 73.22(i). Specifically, the NRC inspection team confirmed that KHNP policies and implementing procedures include reviews of SGI documents to determine whether the documents continue to meet SGI classification criteria and provide for the removal and destruction of SGI documents.

6 The NRC inspection team discussed the program with KHNPs management and staff. The attachment to this inspection report lists the KHNP documents reviewed, and the KHNP staff interviewed by the NRC inspection team.

b.

Observation and Findings No findings of significance were identified.

c.

Conclusion The NRC inspection team concluded that KHNP established its protection of SGI system in accordance with the regulatory requirements of 10 CFR 73.22(h) and 10 CFR 73.22(i).

Based on its observations, the NRC inspection team determined that KHNP is effectively implementing its policies and procedures associated with the removal and destruction of SGI. No findings of significance were identified.

7.

Entrance and Exit On February 1, 2024, the NRC inspection team presented the inspection scope during an entrance meeting with Ryan Ryu, Deputy Director, and other members of KHNPs staff. On February 1, the NRC inspection team presented the inspection results with Ryan Ryu and other members of KHNPs staff. The attachment to this report lists the attendees of the entrance and exit meetings, as well as those individuals whom the NRC inspection team interviewed.

7 ATTACHMENT 1.

ENTRANCE/EXIT MEETING ATTENDEES Name Position Affiliation Entrance Exit Interviewed Ryan Ryu Deputy Director KHNP X

X X

Oh-su Ahn Manager KHNP X

X X

Robert Sweeney KHNP Contractor AECOM X

X X

Deanna Zhang Inspector NRC X

X 2.

INSPECTION PROCEDURES USED Inspection Procedure (IP) 81811, Protection of Safeguards Information by Design Certification Applicants and Vendors, dated April 8, 2020.

3.

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Item Number Status Type Description None 4.

DOCUMENTS REVIEWED Korea Hydro & Nuclear Power Co, LTD (KHNP), DC-DG-03-19, Protection of Safeguards Information (SGI), Revision 3, dated July 2019 KHNP DC-DG-03-20, Safeguards Information (SGI) Access Authorization, Revision 3, dated July 2019 2024 KHNP Inventory Audit, January 16, 2024 Safeguards log entries CAP #01306136 CAP #01306153 SGI Access Authorization Qualification Record for Sung-yoon (Ryan) Ryu SGI Access Authorization Qualification Record for Oh-su Ahn SGI Access Authorization Qualification Record for Jy-yong Oh SGI Access Authorization Qualification Record for Kap-soon Kim