ML24040A217

From kanterella
Jump to navigation Jump to search
(CN 89-008) IP 93803 Safety Systems Outage Modifications Inspection
ML24040A217
Person / Time
Issue date: 04/27/1989
From:
NRC/NRR/DRO/IRIB
To:
References
CN 89-008
Download: ML24040A217 (1)


Text

I UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 NRC INSPECTION MANUAL RSIB INSPECTION PROCEDURE 93803 SAFETY SYSTEMS OUTAGE MODIFICATIONS INSPECTION PROGRAM APPLICABILITY:

2515, 2525 93803-01 INSPECTION OBJECTIVES 01.01 To verify that the licensee has appropriate programmatic controls for accomplishing changes, modifications, and repairs.

01.02 To verify that the licensee is conducting activities related to design changes, modifications, and repairs ir. accordance with established proce-aures, commitments, and regulatory requirements.

01.03 To verify that completed modifications have been properly designed, installed, inspected, and tested to ensure the adequate performance of the modified systems and components.

01.04 To determine that the design margins of the modified safety-related systems and components have not been reduced.

01.05 To verify that the modified systems and components are ready for safe startup and operation of the plant.

93803-02 INSPECTION REQUIREMENTS He Safety Systems Outage t-1odifications Inspection (SSOMI) consists of a design inspection and an installation and testing inspection.

02.01 Advance Prt::~aration.

Each of the inspection teams should review the following applicab e documents, before the start of the inspections.

The teams should become familiar with the licensee's administrative programs for designing, installing, and testing modifications in addition to the compo-nents and systems for which modifications are planned.

a.

Final Safety Analysis Report (FSAR).

b.

Technical Specifications (TS).

c.

Descriptions of the proposed modifications.

d.

Administrative documents used to implement modifications.

Issue Date:

04/27/89

e.

Corporate and site engineering procedures.

f.

licensee event reports for the past 2 years.

g.

Past inspection reports.

h.

System descriptions.

02.02 Design Inspection.

This part of the inspection should be performed by a design engineering team staffed with electrical and r:iechanical engineers who are familiar with design and analysis practice and techniques.

The inspection should be conducted before the outage starts or soon after the start of a major outage, and should be done at the offices of the organiza-tion with principal engineering responsibility for the modifications.

The inspection will verify the following for a sample of modifications selected during the advance preparation for the SSOMI.

a.

Regulatory requirements and design bases as specified in the FSAR and TS and as documented in NRC safety evaluations, have been correctly reflected in the modifications.

b.

The licensee has adequately performed 10 CFR 50.59 safety evaluations for the modifications, as required.

c.

Design information is current and correct and the assumptions used in the design calculations are based on sound engineering principles and practices.

d.

Design information has been properly incorporated into project docu-ments such as specifications, dra\\olings, procedures, and instructions used for the modifications.

e.

Design information is controlled and has been applied to the original design changes, including field changes.

f.

Field changes are properly recorded and evaluated.

g.

The licensee's engineering staff has sufficient technical guidance and experience to adequately perform the assigned engineering functions.

h.

The design verification process, such as alternate or independent calculation review or qualification testing, is performed correctly.

02.03 Installation Inspection.

Sections 02.03 and 02.04 are performed by multi-discipline teams with expertise in electrical and mechanical system installation and testing requirements.

The installation inspection should be conducted at the plant sHe at a time during the outage when sufficient modification installation activities have been accomplished to warrant the inspection.

The inspection should verify the following for a sample of modifications selected during the advance preparation phase of the SSOMI.

a.

The licensee has adequately performed 10 CFR 50.59 safety evaluations for the modifications, as required.

Issue Date:

04/27/89 93803

b.

The installed modifications agree with design requirements such as those pertaining to as-built dimensions, code requirements.

ANSI standards, regulatory guides, A/E specifications, welding and NOE requirements, arid seismic requirements.

c.

For the work packages selected, the proper maintenance procedures or work procedures were invoked and followed, QA/QC hold points were properly accomplished and verified, and all required forms were properly completed, signed, and reviewed.

d.

Required QA/QC audits and survei 11 ances have been perf armed on the selected modifications, and the audit and surveillance findings have been properly dispositioned.

e.

Work requests and maintenance orders are in agreement with the work originally authorized, and work requests, if revised, did not expand the scope of the work originally planned by the modification.

f.

Deficiency reports, field change requests, engineering change notices, and similar documents recorded deviations from original design requirements, and adequate engineering review was done before correc-tive actions were accepted.

g.

QA documentation for replacement items is in agreement with the material installed, and the material is properly environmer,tally qualified (EQ) and agrees with design specifications.

h.

Maintenance or modifications on EQ components do not irvalidate the q u a l i f i ca t i on.

i.

All controlled documents (e.g., drawings, work procedures, site administration procedures, test procedures, TS, FSAR) affected by the modified component, system or structure have been revised or are being revised.

02.04 Testing Inspection.

Thi:: testir;g inspection should be conducted near the end of the outage at a time when a significant amount of post-modifica-tion testing is being performed.

The inspection team should verify the following for the systems modified:

a.

Modified systems and components were tested in accordance with ap-proved procedures, and the results were properly reviewed and approved before startup testing occurred and the systems and components were placed into service.

b.

Performance of the modified systems and components conforms to requirements and acceptance standards identified in ii censee proce-dures, and the operationa 1 margins of safety have not been compro-mised.

c.

Testing of individual modHied components or subsystems takes into account the effects of the modifications on the operational perfor-mance of the entire system and on affected interfacing systems.

d.

93803 Piping and instrumentation diagrams, critical drawings, including control room drawings, and operating procedures were revised to incorporate system changes before system operation. Issue Date:

04/27/89

e.

Operator training for significant operational changes occurred before system ste1rtup, and operator training programs were revised in a reasonable time to reflect tht design changes or modifications that were implemented.

f.

As-built drawings were changed to reflect the current configurations, and this was accomplished not only for the modified systems, but also for other systems, components or structures which were affected by the modification activities.

g.

Deficiencies were clearly identified, and appropriate corrective actions were implemented.

h.

After corrective actions, or changes to the modifications, have been completed, tests were rerun as necessary to ensure that performance of the system is adequate.

i.

Results cf the evaluations are reviewed by appropriate licensee per-sonnel and/or contractor personnel, including the persons responsible for approving the original test procedures.

93803-03 INSPECTION GUIDANCE 03.01 General Guidance

a.
b.

Team Composition.

The design team normally is ccmpri sed of a team leader and four to six engineers who are experts in the design areas of electrical, instrumentation arid control, mechanical systems, arid mechanical components.

The installation and testing team normally consists of a team leader for each of the mechanical and electrical disciplines, with, typically, two or three additional inspectors per discipline area.

The installation inspectors should be knowledgeable in construction or modification and maintenance activities, and the testing inspectors should be knowledgeable in component and system testing.

Team compositions should be changed as necessary to meet changing inspection requirements or priorities for specific plants or specific outages.

For example, one or more procurement specialists may be added to either the design team or the installation and testing team for a broader or more detailed inspection in that area.

In addition, for major outages, separate teams may be warranted for installation activities and for testing activities.

Inspection Scheduling.

The design inspection and the installation and testing inspection are each normally four weeks long.

The first week is typically devoted to in-office preparation, then two weeks are normally spent inspecting, with an interim week devoted to in-office review.

If extensive or unusual findings are identified during the onsite inspection, team leaders should consider lengthening the onsite inspection period as necessary to complete the required inspections.

Some other factors to consider when extending the inspection !Jeriod include the complexity of the modifications to be reviewed, the length of the plant outage, travel time needed to get to the site, and the scope of the review.

Following completion of the inspection activi-ties, report inputs should be provided by each inspector on a schedule determined by the team leader and NRC management.

Issue Date:

04/27/89 93803 I

03.02 Specific Guidance

a.

Inspection Requirement 02. 01. Advance preparation shou 1 d be performed by the design team and the installation and test team.

The teams should review the licensee's applicable administrative. corporate and site engineering procedures in detail during this period so that they are thoroughly familiar with the utility's program for performing modifications.

In addition.

individual inspectors should become familiar with the systems being modified so that they can understand the impact of the modifications.

Before each team's advance review period, the team leader and selected team members should make a "bagman" trip to the utility to find and bring back the material needed during the advance preparation.

The teams should also be familiar with other applicable documents such as the FSAR. Technical Specifications. LERS, and NRC inspection reports.

b.

InsEection Requirement 02.02.

The design team inspectors will typically spend most of their time at the engineering offices where the organization responsible for the design of the modifications is located.

Sharing of design findings and concerns with the installa-tion and test team is particularly important for the successful completion of the SSOMI.

If practical, the installation and test team leader and discipline leaders should attend the design team preexit and exit meetings to become more familiar with the design tedm findings and concerns.

c.

Inspection Requirement 02.02a.

The inspector should verify that sys-tem informatfon is consistent between the Technical Specifications.

the FSAR, d~sign documents, and other licensee technical manuals.

d.
f.
g.

93803 Inspection Re~uirement 02.02d.

Design documents and information should be num ered and categorized for future use and reference.

Most licensees with good design engineering department practices will have all of the design documents numbered so that future modifications can be referenced to preexisting and accurate design information on the system rather than having to research existing design documents such as the TS and FSAR to resurrect good information whenever a system is modified.

Ins~ection Requirement 02.02e.

All design calculations should have tee nical independent reviews performed to ensure ttiat design calcu-lations are free from errors and that the assumptions made and the engineering approach taken are both conservative and reasonable.

Inspection Requirement 02.03a.

Proper safety evaluations should con-sist of more than a checklist and should state why the modification does not need a safety evaluation, if so noted.

Additionally, the inspector should review for potential unreviewed safety questions.

Inseection Re~uirement 02.03c.

All work performed for the modifi-cations shoul be with approved procedures which have been through the appropriate site approval process.

If work has been completed with the use of a locally generated procedure, the assumptions made in the safety a*nalysis may be incorrect and the licensee should perform a technical evaluation of the work performed to determine system operability. Issue Date: 04/27/89

h.

Inspection Requirement 02.04.

A combined installation anc! test team may not have the opportunity to witness modification testing during a SS0MI of a short du rat ion outage.

Therefore, the team may have t0 rely on reviews of test procedures, evaluation of completed test results and limited observation of testing.

i.

~~

Test results should be compared with t e va ues va ues are specified in the FSAR) and the licen-see's In-Service Testing reference values in order to determine the effect of the new test r~su l ts on tht! ASME Section XI requirements.

j.

Inspection Requirement 02.04c.

The site review and approval process for functional test procedures that have been written for specific modifications should be evaluated for adequacy and completeness.

END Issue Date: 04/27/89 93803