SMR, LLC, Meeting Presentation Materials for February 7, 2024
ML24026A030
Person / Time
Site: 99902049
Issue date: 02/07/2024
From: Essner P
Holtec, SMR
To:
Office of Nuclear Reactor Regulation
Shared Package
ML24026A028 List:
References
160-USNRC-074
Download: ML24026A030 (1)


Text

www.holtec.com www.smrllc.com GDC 17 Exemption Request February 7, 2024 Presented by: Patrick Essner SMR, LLC, A Holtec International Company Krishna P. Singh Technology Campus One Holtec Boulevard Camden, NJ 08104, USA

[Not Export Controlled]

holtec.com l smrllc.com l Page 2 Meeting Agenda

Introductions

Purpose & Outcome Overview of Electrical Design and Application to Safe Shutdown Discussion on GDC 17 Exemption Request Additional GDCs included in Exemption Request Open Forum

holtec.com l smrllc.com l Page 3 Purpose & Outcome

Purpose:

Provide an overview of the SMR-300 electrical design and its application to achieving and maintaining safe shutdown Discuss implications for GDCs requiring offsite power Outcome:

Gain alignment on proposed exemption request covering GDC 17, 33, 34, 35, 38, 41, and 44

holtec.com l smrllc.com l Page 4 Dual Unit Approach Common Station Service transformer (SST) and non-Class 1E switchgears Independent Class 1E circuit U2 U1 COM MVE GR 1 SWGR UAT MVE GR 2 SWGR SST MVE C1 SWGR MVE GR 2 SWGR MVE GR 1 SWGR UAT SBD MVE C2 SWGR SBD LVE C1 SWGR LVE C1 SWGR LVE C1 SWGR LVE C2 SWGR LVE C2 SWGR LVE C2 SWGR LVE GR 1 SWGR LVE GR 1 SWGR LVE GR 2 SWGR LVE GR 2 SWGR LVE GR 2 SWGR LVE GR 2 SWGR LVE GR 1 SWGR LVE GR 1 SWGR LVE GR 1 SWGR LVE GR 2 SWGR LVE GR 2 SWGR LVE GR 1 SWGR MSU MG MSU MG DIV A 1E 250VDC/120VAC DIV B 1E DISTRIBUTION DIV B 1E DISTRIBUTION DIV A 1E DISTRIBUTION NON-1E G1 120 VAC NON-1E G2 120 VAC NON-1E G1 120 VAC NON-1E G2 120 VAC

holtec.com l smrllc.com l Page 5 Class 1E Electrical Distribution System DCE DIV A1 BUS DCE DIV A2 BUS BAT UPS UPS BAT ICE DIV A1 BUS ICE DIV A1 BUS ICE DIV A2 BUS ICE DIV A2 BUS CHGR CHGR UNIT 1 DCE DIV B1 BUS DCE DIV B2 BUS BAT UPS UPS BAT ICE DIV B1 BUS ICE DIV B1 BUS ICE DIV B2 BUS ICE DIV B2 BUS CHGR CHGR DIVISION B DIVISION A UNIT 1

holtec.com l smrllc.com l Page 6 SMR-300 Electrical Safe Shutdown Approach The Class 1E batteries are sized with a coping time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and to address SBO coincident with a LOCA Sequence of Events Loss of all AC power to battery chargers.

Battery starts to discharge powering Class 1E DC loads and inverters Loads include continuous loads from the inverter as well as loads that are normally energized but will later be de-energized.

Safeguards Actuation signal, Containment Isolation signal. Loads include continuous loads from the inverter, energization of MOV's changing position, and de-energization of NC (normally closed) AOV's/SOV's to place them in their safety position.

Continuous loads for duration of 72-hour coping period.

holtec.com l smrllc.com l Page 7 SMR-300 Regulatory Compliance Overview SMR-300 design supports an exemption to GDC 17 SMR-300 still meets underlying purpose of GDC 17 Will be compliant with proposed PDC 17 SMR-300 design similarly supports exemption to portions of GDC 33, 34, 35, 38, 41, and 44 Only portions requiring offsite power sources Will be compliant with proposed PDCs

holtec.com l smrllc.com l Page 8 GDC 17 An onsite electric power system and an offsite electric power system shall be provided to permit functioning of structures, systems, and components important to safety. The safety function for each system (assuming the other system is not functioning) shall be to provide sufficient capacity and capability to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained in the event of postulated accidents.

The onsite electric power supplies, including the batteries, and the onsite electric distribution system, shall have sufficient independence, redundancy, and testability to perform their safety functions assuming a single failure.

Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits (not necessarily on separate rights of way) designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions. A switchyard common to both circuits is acceptable. Each of these circuits shall be designed to be available in sufficient time following a loss of all onsite alternating current power supplies and the other offsite electric power circuit, to assure that specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded. One of these circuits shall be designed to be available within a few seconds following a loss-of-coolant accident to assure that core cooling, containment integrity, and other vital safety functions are maintained.

Provisions shall be included to minimize the probability of losing electric power from any of the remaining supplies as a result of, or coincident with, the loss of power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electric power supplies.

holtec.com l smrllc.com l Page 9 Underlying Purpose of GDC 17 To ensure that sufficient electrical power is available to permit safety functions of the SMR-300 The SMR-300 is designed to utilize passive safety systems that only rely on redundant, onsite Class 1E power systems to achieve and maintain safe shutdown during anticipated operating conditions and postulated accidents.

holtec.com l smrllc.com l Page 10 SMR-300 PDC 17 A redundant onsite electric power system shall be provided to permit functioning of structures, systems, and components important to safety. The safety function for the system shall be to provide sufficient capacity and capability to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not exceeded as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained in the event of postulated accidents.

The onsite electric power supplies, including the batteries, and the onsite electric distribution system, shall have sufficient independence, redundancy, and testability to perform their safety functions assuming a single failure.

Provisions shall be included to minimize the probability of losing electric power from any of the remaining supplies as a result of, or coincident with, the loss of power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electric power supplies.

holtec.com l smrllc.com l Page 11 Remaining GDCs - GDC 34 A system to remove residual heat shall be provided. The system safety function shall be to transfer fission product decay heat and other residual heat from the reactor core at a rate such that specified acceptable fuel design limits and the design conditions of the reactor coolant pressure boundary are not exceeded.

Suitable redundancy in components and features, and suitable interconnections, leak detection, and isolation capabilities shall be provided to assure that for onsite electric power system operation (assuming offsite power is not available) and for offsite electric power system operation (assuming onsite power is not available) the system safety function can be accomplished, assuming a single failure.

holtec.com l smrllc.com l Page 12 Remaining GDCs - SMR-300 PDC 34 A system to remove residual heat shall be provided. The system safety function shall be to transfer fission product decay heat and other residual heat from the reactor core at a rate such that specified acceptable fuel design limits and the design conditions of the reactor coolant pressure boundary are not exceeded.

Suitable redundancy in components and features, and suitable interconnections, leak detection, and isolation capabilities shall be provided to assure that for onsite electric power system operation (assuming offsite power is not available) the system safety function can be accomplished, assuming a single failure.

holtec.com l smrllc.com l Page 13 Exemptions - 10 CFR 50.12 The proposed exemption request is Authorized by law Not inconsistent with Atomic Energy Act of 1954 No undue risk to the public health and safety No impact to postulated accident progressions or consequences Consistent with the common defense and security No impact to plant security or safeguards Accompanied by special circumstances Underlying purpose of the rule is met

holtec.com l smrllc.com l Page 14 Open Forum