MONTHYEARInspection Manual Change Notice 24-034, Table of Contents for Inspection Manual Change Notice 24-0342024-10-31031 October 2024 Table of Contents for Inspection Manual Change Notice 24-034 Inspection Manual Change Notice 24-033, Table of Contents for Inspection Manual Change Notice 24-0332024-10-29029 October 2024 Table of Contents for Inspection Manual Change Notice 24-033 Inspection Manual Change Notice 24-031, Table of Contents for Inspection Manual Change Notice 24-0312024-10-25025 October 2024 Table of Contents for Inspection Manual Change Notice 24-031 Inspection Manual Change Notice 24-032, Table of Contents for Inspection Manual Change Notice 24-0322024-10-25025 October 2024 Table of Contents for Inspection Manual Change Notice 24-032 Inspection Manual Change Notice 24-030, Table of Contents for Inspection Manual Change Notice 24-0302024-10-23023 October 2024 Table of Contents for Inspection Manual Change Notice 24-030 ML24150A2392024-07-29029 July 2024 IMC 2562 Light-Water Reactor Inspection Program for Restart of Reactor Facilities Following Permanent Cessation of Power Operations Inspection Manual Change Notice 24-023, Table of Contents for Inspection Manual Change Notice 24-0232024-07-29029 July 2024 Table of Contents for Inspection Manual Change Notice 24-023 Inspection Manual Change Notice 24-022, Table of Contents for Inspection Manual Change Notice 24-0222024-07-26026 July 2024 Table of Contents for Inspection Manual Change Notice 24-022 Inspection Manual Change Notice 24-021, Table of Contents for Inspection Manual Change Notice 24-0212024-07-24024 July 2024 Table of Contents for Inspection Manual Change Notice 24-021 Inspection Manual Change Notice 24-018, Table of Contents for Inspection Manual Change Notice 24-0182024-07-0101 July 2024 Table of Contents for Inspection Manual Change Notice 24-018 Inspection Manual Change Notice 24-016, Table of Contents for Inspection Manual Change Notice 24-0162024-05-30030 May 2024 Table of Contents for Inspection Manual Change Notice 24-016 Inspection Manual Change Notice 24-015, Table of Contents for Inspection Manual Change Notice 24-0152024-05-16016 May 2024 Table of Contents for Inspection Manual Change Notice 24-015 ML24044A2152024-05-10010 May 2024 IMC 0306 Planning, Scheduling, Tracking, and Reporting of the Reactor Oversight Process (ROP) Inspection Manual Change Notice 24-014, Table of Contents for Inspection Manual Change Notice 24-0142024-05-10010 May 2024 Table of Contents for Inspection Manual Change Notice 24-014 ML24033A2992024-04-23023 April 2024 IMC 2562 Light-Water Reactor Inspection Program for Restart of Reactor Facilities Following Permanent Cessation of Power Operations Inspection Manual Change Notice 24-013, Table of Contents for Inspection Manual Change Notice 24-0132024-04-23023 April 2024 Table of Contents for Inspection Manual Change Notice 24-013 Inspection Manual Change Notice 24-012, Table of Contents for Inspection Manual Change Notice 24-0122024-04-22022 April 2024 Table of Contents for Inspection Manual Change Notice 24-012 Inspection Manual Change Notice 24-010, Table of Contents for Inspection Manual Change Notice 24-0102024-03-14014 March 2024 Table of Contents for Inspection Manual Change Notice 24-010 Inspection Manual Change Notice 24-009, Table of Contents for Inspection Manual Change Notice 24-0092024-03-0808 March 2024 Table of Contents for Inspection Manual Change Notice 24-009 Inspection Manual Change Notice 24-008, Table of Contents for Inspection Manual Change Notice 24-0082024-03-0404 March 2024 Table of Contents for Inspection Manual Change Notice 24-008 Inspection Manual Change Notice 24-007, Table of Contents for Inspection Manual Change Notice 24-0072024-02-12012 February 2024 Table of Contents for Inspection Manual Change Notice 24-007 Inspection Manual Change Notice 24-005, Table of Contents for Inspection Manual Change Notice 24-0052024-02-0707 February 2024 Table of Contents for Inspection Manual Change Notice 24-005 Inspection Manual Change Notice 24-006, Table of Contents for Inspection Manual Change Notice 24-0062024-02-0707 February 2024 Table of Contents for Inspection Manual Change Notice 24-006 ML23318A2002024-01-0909 January 2024 IMC 0307 Appendix D, Resident Inspector Retention and Recruitment Program Monitoring and Assessment Inspection Manual Change Notice 24-002, Table of Contents for Inspection Manual Change Notice 24-0022024-01-0909 January 2024 Table of Contents for Inspection Manual Change Notice 24-002 ML23307A0092024-01-0202 January 2024 IMC 2515 Appendix E, Inspection Program Modifications During Public Health Emergencies or Other Conditions Restricting Inspector Onsite Presence Inspection Manual Change Notice 24-001, Table of Contents for Inspection Manual Change Notice 24-0012024-01-0202 January 2024 Table of Contents for Inspection Manual Change Notice 24-001 Inspection Manual Change Notice 23-039, Table of Contents for Inspection Manual Change Notice 23-0392023-12-21021 December 2023 Table of Contents for Inspection Manual Change Notice 23-039 Inspection Manual Change Notice 23-037, Table of Contents for Inspection Manual Change Notice 23-0372023-12-15015 December 2023 Table of Contents for Inspection Manual Change Notice 23-037 ML23318A4262023-12-15015 December 2023 IP 71111.21N.04 Age-Related Degradation ML23234A1762023-12-14014 December 2023 IMC 0309 Reactive Inspection Decision Basis for Power Reactors Inspection Manual Change Notice 23-035, Table of Contents for Inspection Manual Change Notice 23-0352023-12-0606 December 2023 Table of Contents for Inspection Manual Change Notice 23-035 Inspection Manual Change Notice 23-034, Table of Contents for Inspection Manual Change Notice 23-0342023-11-15015 November 2023 Table of Contents for Inspection Manual Change Notice 23-034 Inspection Manual Change Notice 23-033, Table of Contents for Inspection Manual Change Notice 23-0332023-11-0606 November 2023 Table of Contents for Inspection Manual Change Notice 23-033 ML23214A3822023-10-31031 October 2023 IMC 0308, Attachment 2, Technical Basis for Inspection Program ML23222A1682023-10-31031 October 2023 IMC 0611 Appendix D Guidance for Problem Identification and Resolution Inspection Reports Inspection Manual Change Notice 23-032, Table of Contents for Inspection Manual Change Notice 23-0322023-10-31031 October 2023 Table of Contents for Inspection Manual Change Notice 23-032 ML23226A2232023-10-16016 October 2023 IP 71111.08 Inservice Inspection Activities Inspection Manual Change Notice 23-030, Table of Contents for Inspection Manual Change Notice 23-0302023-10-16016 October 2023 Table of Contents for Inspection Manual Change Notice 23-030 Inspection Manual Change Notice 23-028, Table of Contents for Inspection Manual Change Notice 23-0282023-09-19019 September 2023 Table of Contents for Inspection Manual Change Notice 23-028 Inspection Manual Change Notice 23-026, Table of Contents for Inspection Manual Change Notice 23-0262023-08-28028 August 2023 Table of Contents for Inspection Manual Change Notice 23-026 ML23191A5172023-08-18018 August 2023 IP 71111.07 Heat Exchanger/Sink Performance Inspection Manual Change Notice 23-024, Table of Contents for Inspection Manual Change Notice 23-0242023-08-17017 August 2023 Table of Contents for Inspection Manual Change Notice 23-024 Inspection Manual Change Notice 23-023, Table of Contents for Inspection Manual Change Notice 23-0232023-08-11011 August 2023 Table of Contents for Inspection Manual Change Notice 23-023 Inspection Manual Change Notice 23-021, Table of Contents for Inspection Manual Change Notice 23-0212023-07-27027 July 2023 Table of Contents for Inspection Manual Change Notice 23-021 Inspection Manual Change Notice 23-020, Table of Contents for Inspection Manual Change Notice 23-0202023-07-14014 July 2023 Table of Contents for Inspection Manual Change Notice 23-020 ML23192A8372023-07-12012 July 2023 IP 71111.21N.04 Age-Related Degradation ML23151A5462023-06-26026 June 2023 IMC 2515 Appendix C, Special and Infrequently Performed Inspections Inspection Manual Change Notice 23-018, Table of Contents for Inspection Manual Change Notice 23-0182023-06-26026 June 2023 Table of Contents for Inspection Manual Change Notice 23-018 ML23055B0532023-06-26026 June 2023 IMC 2515 Appendix E, Inspection Program Modifications During Public Health Emergencies or Other Conditions Restricting Inspector Onsite Presence 2024-07-29
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555
- NRC INSPECTION MANUAL LPEB
INSPECTION PROCEDURE 71715
SUSTAINED CONTROL ROOM AND PLANT OBSERVATION
PROGRAM APPLICABILITY: 2515
71715-01 INSPECTION OBJECTIVES 01.01 To provide an opportunity for the resident inspector, an offsite inspector or regional management to evaluate a licensee* s control room and plant performance over a sustained period. The resident inspector should gain new insight from the sustained control room observation and the offsite inspector's independent view (if an offsite inspector is used).
01.02 This procedure has been established to permit long-term, continuous observation of control room activities. More than one inspector is generally required for this type of sustained observation. However, due to varying circumstances, it may be more appropriate for regional management to assign more inspectors is inapplicable. the task to a single inspector, in which case the direction regarding two or
71715-02 INSPECTION REQUIREMENTS 02.01 Inspectors. This inspection shall be conducted by the senior resident inspector, resident inspector, region-based inspector, or an offsite inspector designated by management for this purpose. Management may choose to represent the second inspector.
with control room protocol regarding access and administrative controls prior Inspectors who are not part of the site resident staff should become familiar to the initiation of the inspection.
02.02 Ins~ection Items. For a period of time determined to be appropriate by regiona management, observe operational activities conducted by the detracts from their ability to monitor and operate the plant. The inspector licensee. The inspector should obtain the licensed operators* views on what should evaluate the following conditions or practices as appropriate.
- a. Operators are attentive and responsive to plant parameters and condi-l tions. Operators are aware of the reasons for annunciators that are in the alarm condition
- Issue Date: 04/14/92 - 1 - 71715
- b. Plant evolutions and testing are planned and properly authorized. When a more complex special evolution or non-routine evolution takes place, a pre-evolution briefing of the shift crew and other personnel affected by the evolution may be appropriate.
- c. Procedures are used and followed as required by plant policy.
- d. Equipment status changes are appropriately documented and communicated to appropriate shift personnel, when they occur.
- e. The operating conditions of plant equipment are effectively monitored, and appropriate corrective action is initiated when required.
- f. Backup instrumentation, measurements, and readings are used as appropriate when normal instrumentation is found to be defective or out of tolerance. Equipment out of service controls are adequate.
- g. Logkeeping is timely, accurate, and adequately reflects plant activities and status.
- h. Operators follow good operating practices and maintain shift professionalism in conducting plant operations. Operators are aware of ongoing plant activities and surveillance testing. Administrative controls are adequate to ensure in-plant work activities are being performed with the knowledge of control room personnel.
- i. The control room environment is adequate for conduct of duties; i.e. lighting, noise levels, traffic volume, number of alarms, ventilation, heating and cooling are acceptable.
- j. Communication between workers and first line supervisors, as well as specific communications procedures. interdepartmental communications, are appropriate and follow any plant *
- k. Shift turnovers are professional and provide the oncoming shift an adequate update from the last time they were on shift.
- 1. Blocking/tagging and valve lineups are conducted in accordance with plant procedures and are adequate to provide isolation or proper system lineup for existing plant conditions.
- m. The administrative burden on the control room supervisor does not prevent adequate supervision of shift activities.
- n. Manipulation of plant controls that may effect reactivity changes is performed by licensed operators, or by individuals enrolled in an approved operator licensing training program who are under the direction and in the presence of a license operator.
- o. Overall material condition of the plant does not hinder the effectiveness of the operators in conducting normal plant evolutions as well as non-routine evolutions.
- p. Technical satisfied. Specification limiting conditions for operation are Entry into LCO action statements are controlled and tracked. Additional surveillance activities required by action statements are performed and tracked.
- 71715 - 2 - Issue Date: 04/14/92
- q. Abnormal conditions and equipment problems are evaluated promptly to determine the impact on plant safety, equipment operability, and reportability. Plant management is informed of abnormal conditions as required by plant policies.
71715-03 INSPECTION GUIDANCE General Guidance This procedure is intended to be used when regional management determines that as a result of plant events or poor licensee performance it is necessary to conduct a continuous surveillance of licensee performance. This procedure was developed based on the assumption that the inspection would continue for approximately 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />; however, other factors may indicate that a shorter or longer surveillance period is required. Regional management can use this procedure to allow one resident to participate in the inspection of another Management participation in the implementation of this procedure is left to facility thereby enhancing the inspection techniques of both residents.
the discretion of regional management.
Specific Guidance 03.01 Inspection Requirements 02.01. If the inspection period is of short duration, both inspectors should be present during the period. If the period is greater than four hours, the inspectors should divide the observation period so that at least one inspector is observing plant activities during the entire period.
03.02 Inspection Requirement 02.02. The criteria listed in this section provides only broad guidance for evaluating operational activities. The inspectors should pay particular attention to the performance of licensed and non-licensed (auxiliary) operators. Approximately 25 percent of the obser vati9n time should be spent observing ~perator performance outside the control room. Backshift observations should be included as feasible, de pending on the duration of the inspection. The regions should modify these criteria as necessary.
03.02.a No inspection guidance.
03.02.b Inspection Requirement 02.02b. When evaluating complex or non routine evolutions, the inspector may consider the following supporting activities:
Effectiveness of written communications, such as daily orders or special orders, in directing plant operations.
Adequacy of management involvement during the evolution.
Appropriateness of any risk assessment to understand the risk associated with the activity.
03.02.c-q No inspection guidance
- Issue Date: 04/14/92 - 3 - 71715 71715-04 RESOURCE ESTIMATE On the average, about 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of direct inspection are needed to accomplish the inspection requirements of this inspection procedure.