December 6, 2023 MEMORANDUM TO:
Michelle W. Hayes, Chief Licensing and Infrastructure Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation FROM:
William (Billy) Gleaves, Senior Project Manager
/RA/
Licensing and Infrastructure Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF NOVEMBER 9, 2023, PRESUBMITTAL MEETING WITH WESTINGHOUSE ELECTRIC COMPANY ON AP300 WHITE PAPER #1 DESIGN DESCRIPTION OVERVIEW On November 9, 2023, at 12:00 p.m. Eastern Time (ET), the U.S. Nuclear Regulatory Commission (NRC) held a hybrid public meeting with representatives of Westinghouse Electric Company (WEC). The purpose of the presubmittal meeting was to hear WECs presentation on the AP300 conceptual design that will be discussed in greater detail in a white paper WEC plans to submit on Design Description Overview, which may include feedback from this meeting. The presentation slides for this meeting can be found under Agencywide Documents and Access Management System (ML23310A144). The meeting was divided into two sessions; a public session and a proprietary session.
WEC staff presented at both the public and proprietary sessions and received staff feedback on the details of their plans and general design during the proprietary session. The AP300 design is largely based on the AP1000 certified design with changes that reflect the smaller power output, lessons learned from the AP1000 construction, and a simplification of features.
A member of the public asked a question of the staff regarding the preparedness and resources of the NRC to review the AP300 design. The staff responded that a lead project manager has been assigned and staff are available and ready to review the application.
CONTACT: William (Billy) Gleaves 301-415-5848
The meeting notice and agenda are available under ML23290A106. A list of attendees is enclosed. There were approximately 38 participants remotely and 10 in person, including NRC staff, WEC staff, and members of the public. The public session of the meeting ended at 12:20 p.m. ET. The proprietary session started at 12:22 p.m. and closed at 2:35 p.m. ET.
Docket No. 999-02111
Enclosures:
- 1. List of Attendees
- 2. Summary of Proprietary Session (proprietary) cc: Listserv
Pkg: ML23331A046 Memo: ML23331A100 : ML23331A099 NRR-106 OFFICE NRR/DNRL/NLIB: PM NRR/DNRL/NLIB: LA NRR/DNRL/NLIB: BC NRR/DNRL/NLIB: PM NAME BGleaves SGreen MHayes BGleaves DATE 11/27/23 11/28/23 12/6/23 12/6/23
LIST OF ATTENDEES November 9, 2023 NRC Presubmittal Meeting with Westinghouse Name Organization Billy Gleaves Michelle Hayes Stew Bailey Richard Stattel Brian Wittick Angie Buford Maurin Sheetz Ian Tseng Wendell Morton Kerri Kavanagh Samuel Lee Phil Sahd Syed Haider Shanlai Lu Josh Miller Antonio Barrett Raul Hernandez Frankie Vega David Desaulniers Kamal Manoly Chris Van Wert David Nold Dan Widrevitz Cory Parker Sheila Ray John Hughey Tom Scarbrough Kayleh Hartage Derek Scully Gordon Curran Justin Donohoe Nick Hansing Brian Lee Angelo Stubbs Rob Taylor Rob Atienza Nageswara Karipineni Hanry Wagage Thang Thawn Ryan Nolan NRC
2 Name Organization Zach Harper Rachel Christian Brian Friedman Rita Baranwal Kevin May Chris Goosen Luis Rejas Lopez, Tecnatom Megan Durse Warren Odess-Gillett Keegan Foster Westinghouse and Contractors Bill Freebairn S&P Global Platts Jana Bergman, Curtiss Wright Members of the Public