Summary of 10-19-23 Pre-Application Meeting Inverter Completion Times
ML23297A028
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 10/30/2023
From: Geoffrey Miller
Plant Licensing Branch II
To: Markley M
Southern Nuclear Operating Co
Miller G
References
EPID L-2023-LRM-0094
Download: ML23297A028 (1)


Text

October 30, 2023 MEMORANDUM TO: Michael T. Markley, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM:

G. Edward Miller, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF OCTOBER 19, 2023, MEETING

SUMMARY

REGARDING POTENTIAL LICENSE AMENDMENT REQUEST CHANGE TO TS 3/4.8.3 FOR V.C. SUMMER NUCLEAR STATION On October 19, 2029, the U.S. Nuclear Regulatory Commission (NRC) staff held an Observation Meeting public teleconference1 with representatives from the Dominion Energy (Dominion). The purpose of the meeting was for Dominion to discuss its plans to submit a license amendment request regarding an extension of the completion time for Action c of Technical Specification (TS) 3/4.8.3 for the V.C. Summer Nuclear Station, Unit 1, and to receive NRC staff feedback on what information would be needed to support the NRC staff review of the submittal. The request would change the completion time to re-energize one AC vital bus to its associated inverter from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 7 days.

During the meeting, Dominion staff indicated that they planned to include risk insights in the submittal, but they did not intend to make the request fully risk-informed, (i.e., not adhering to the guidance in Regulatory Guide 1.200, Revision 3, Acceptability of Probabilistic Risk Assessment Results for Risk Informed Activities). The licensee discussed some insights gained from their risk models (including fire and seismic models) and discussed defense-in-depth strategies that they believed were supportive of a 7-day completion time. The licensee indicated it reviewed precedent from a recent Hope Creek license amendment to extend a completion time. The NRC staff suggested that the licensee may find it helpful to also review precedent amendment from Palo Verde. The NRC staff reinforced that a discussion of the timelines for expected maintenance evolutions would be helpful.

The NRC staff also acknowledged that the change of the inverter equipment was done under a licensee-controlled program. The NRC staff noted, that although the change of the equipment wasnt the subject of the review, the type and nature of the currently installed equipment would factor into the appropriateness of the completion time.

1 The meeting notice is available under Agencywide Documents Access and Management System (ADAMS)

Accession No. ML23279A069.

/RA/

No regulatory decisions were made during the meeting. Following the discussion, an opportunity was afforded to any other participants who wished to ask questions or make comments. No questions or comments were received from the public.

Enclosure:

List of Attendees

Enclosure LIST OF PARTICIPANTS OCTOBER 19, 2022, PUBLIC MEETING TO DISCUSS POTENTIAL EMERGENCY PREPAREDNESS SUBMITTAL Name Organization Ed Miller NRC/NRR/DORL Khadijah West NRC/NRR/DSS Jay Robinson NRC/NRR/DRA Mike Markley NRC/NRR/DORL Zach Turner NRC/NRR/DORL Wendell Morton NRC/NRR/DEX Yan Gao Dominion Kyle Gibson Dominion Justin Bouknight Dominion Devon Gallagher Dominion Creighton Adsit Dominion

ML23297A028 OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DRA/APLB/BC NAME GEMiller KGoldstein JWhitman DATE 10/27/2023 10/26/2023 10/27/2023 OFFICE NRR/DSS/STSB/BC NRR/DEX/EEEB/BC NRR/DORL/LPL2-1/BC NAME SMehta WMorton MMarkley DATE 10/27/2023 10/27/2023 10/30/2023