Re-filed Exhibit List of Kairos Power LLC for the Hearing on Uncontested Issues
ML23285A124
Person / Time
Site: Hermes
Issue date: 10/12/2023
From: Lighty R, Polonsky A
Kairos Power, Morgan, Morgan, Lewis & Bockius, LLP
To:
NRC/OCM
SECY RAS
References
Construction Permit Mndtry Hrg, RAS 56821, 50-7513-CP
Download: ML23285A124 (0)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the matter of:

Docket No. 50-7513-CP KAIROS POWER, LLC October 12, 2023 (Hermes Test Reactor)

(Mandatory Hearing)

RE-FILED EXHIBIT LIST OF KAIROS POWER, LLC FOR THE HEARING ON UNCONTESTED ISSUES In accordance with the Commissions Scheduling Order dated October 5, 2023, Kairos Power, LLC, hereby re-submits its list of exhibits for the hearing on uncontested issues.

Panel Number/ ADAMS Exhibit Sponsoring Exhibit Title Accession Number Witness(es) Number Applicants Pre-Filed Testimony of KRS-001 Peter Hastings Peter Hastings; Kairos Power LLC; N/A Evidentiary Hearing Overview Panel Mike Laufer Edward Blanford Kairos Power; Hermes Mandatory KRS-002 N/A Per Peterson Hearing - Overview Panel (Slides)

Peter Hastings Safety Panel Mike Laufer Edward Blanford Kairos Power; Hermes Mandatory KRS-003 N/A Per Peterson Hearing - Safety Panel (Slides)

Peter Hastings Environmental Panel Mike Laufer Edward Blanford Kairos Power; Hermes Mandatory KRS-004 N/A Per Peterson Hearing - Environmental Panel (Slides)

Peter Hastings

All Witnesses Mike Laufer Edward Blandford Peter Hastings Per Peterson Martin Bryan Anthonie Cilliers Matthew Denman Oded Doron Darrell Gardner Micah Hackett Kairos Power; Statements of KRS-005 Jordan Hagaman Qualification for All Witnesses N/A Brandon Haugh Alan Kruizenga Drew Peebles Nader Satvat Brian Song Nicolas Zweibaum Steve Ahr Antonio Fernandez Lori Gross Kevin Taylor Kairos Power LLCs Responses to KRS-006 Peter Hastings Commissions Pre-hearing Questions N/A Respectfully submitted, Signed (electronically) by Ryan K. Lighty Executed in Accord with 10 C.F.R. § 2.304(d)

RYAN K. LIGHTY, ESQ. ALEX S. POLONSKY, ESQ.

Morgan, Lewis & Bockius llp MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W. 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004 Washington, D.C. 20004 (202) 739-5274 (202) 739-5830 Ryan.Lighty@morganlewis.com Alex.Polonsky@morganlewis.com Counsel for Kairos Power, LLC Dated in Washington, D.C.

This 12th day of October 2023 2

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the matter of:

Docket No. 50-7513-CP KAIROS POWER, LLC October 12, 2023 (Hermes Test Reactor)

(Mandatory Hearing)

CERTIFICATE OF SERVICE I hereby certify that, on this date, copies of the foregoing Re-filed Exhibit List of Kairos Power, LLC for the Hearing on Uncontested Issues and Re-filed Hearing Exhibits KRS-001 through KRS-006 were served upon the Electronic Information Exchange (the NRCs E-Filing System) on the above-captioned docket.

Signed (electronically) by Ryan K. Lighty RYAN K. LIGHTY, ESQ.

MORGAN, LEWIS & BOCKIUS LLP 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004 (202) 739-5274 Ryan.Lighty@morganlewis.com Counsel for Kairos Power, LLC