October 17, 2023
SUBJECT:
SUMMARY
OF THE SEPTEMBER 15, 2023, PUBLIC MEETING WITH THE NUCLEAR ENERGY INSTITUTE TO DISCUSS THE STATUS OF ONGOING SEISMIC WORK UNDER THE PROCESS FOR THE ONGOING ASSESSMENT OF NATURAL HAZARDS INFORMATION On September 15, 2023, the US Nuclear Regulatory Commission (NRC) conducted a public meeting with the Nuclear Energy Institute (NEI) and industry representatives to discuss the status of the ongoing seismic work to consider the NGA-East ground motion characterization model and updated site response methods within the Process for the Ongoing Assessment of Natural Hazards Information (POANHI) framework. The public meeting was held as a hybrid meeting with virtual and in-person participants. The meeting notice and agenda, dated September 01, 2023, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML23257A047, and the slides presented at the public meeting are available at ML23255A099. A list of attendees is provided in the enclosure.
The NRC staff and NEI began the meeting with opening remarks. Following this, the NRC staff explained the POANHI process for seismic evaluations and presented a flowchart that further clarifies the POANHI decision making process. Further discussion included additional risk evaluation of POANHI seismic information and the process to resolve internal and external issues based upon POANHI decisions and the approach to communicate the NRCs decisions to licensees.
The staff also discussed the role of the POANHI seismic email account (POANHI.Seismic@nrc.gov) and noted that a total of seven comments via email have been received thus far. The staff emphasized that public and external stakeholders should send POANHI inquiries to the NRC via the POANHI seismic email account, and that a summary of comments will be addressed in the upcoming POANHI periodic report expected to be released by December 2023. Lastly, the NRC staff discussed the POANHI seismic review schedule to show which site reviews are upcoming and which have been completed.
NEI shared their appreciation regarding the NRCs consistency and predictability of the POANHI closure letters. NEI clarified with the NRC staff that the dates on the schedule are in reference to a calendar year versus a fiscal year. Additionally, NEI had a question regarding who is on the Senior Management Review Panel (SMRP). The staff clarified that the SMRP consists of senior members from the NRCs Division of Risk Assessment, Division of Engineering and External Hazards, and Division of Operating Reactor Licensing.
There were several comments from industry that recommended having the NRC staff make POANHI seismic risk evaluations publicly available, to share the risk insight with other licensees to better understand and prepare for what the NRC is looking for in its evaluations. The NRC staff also provided clarifications in response to questions and comments from the industry on the NRC staff evaluation process for analyzing risk associated with POANHI seismic.
Prior to the close of the meeting both the NRC and NEI provided closing remarks.
No regulatory decisions or commitments were made at this meeting. No comments were provided by the members of the public, and no public meeting feedback forms were received after the conclusion of this meeting.
Please direct any inquiries to me by email at Zachary.Turner@nrc.gov.
Sincerely,
/RA/
Zachary M. Turner, Project Manager Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Enclosure:
List of Attendees
Enclosure LIST OF ATTENDEES SEPTEMBER 15, 2023, PUBLIC MEETING WITH THE NUCLEAR ENERGY INSTITUTE TO DISCUSS THE STATUS OF ONGOING SEISMIC WORK UNDER THE PROCESS FOR THE ONGOING ASSESSMENT OF NATURAL HAZARD INFORMATION (POANHI)
Name Organization Zach Turner U.S. Nuclear Regulatory Commission (NRC)
Ed Miller NRC Shilp Vasavada NRC Barbara Hayes NRC Clifford Munson NRC Nicholas Taylor NRC Andrea Kock NRC Steven Alferink NRC Drew Childs NRC Michael Markley NRC Jinsuo Nie NRC Sunwoo Park NRC Ryan Payne NRC Kevin Quinlan NRC Sarah Tabatabi NRC Jenise Thompson NRC Nebiyu Tiruneh NRC Rosalynn Wang NRC Weijun Wang NRC Thomas Weaver NRC De Wu NRC Brett Titus Nuclear Engineering Institute Vince Anderson Constellation Energy Fred Hazboun Constellation Energy Roy Linthicum Constellation Energy Francis Peterson Constellation Energy Daniel Vasquez Dominion Energy Robert Rishel Duke Energy Winston Stewart Duke Energy Rob Drsek Energy Harbor Tony Mangan Energy Harbor Douglas Rapp Energy Harbor John Richards Electric Power Research Institute Gabriel Toro Lettis Consultants International Melanie Brown Southern Nuclear Company Russell Thompson Tennessee Valley Authority Victoria Anderson No Affiliation Given Thomas Basso No Affiliation Given Name Organization Jana Bergman No Affiliation Given Karen Carboni No Affiliation Given Rob Choromokos No Affiliation Given Jeremy Graham No Affiliation Given Melinda Graham No Affiliation Given Katherine Gromek No Affiliation Given Gregory Hardy No Affiliation Given Se-Kwon Jung No Affiliation Given Larry Lee No Affiliation Given Andrew Mauer No Affiliation Given Robin McGuire No Affiliation Given Vish Patel No Affiliation Given Frances Pimentel No Affiliation Given Deann Raleigh No Affiliation Given Benny Ratnagaran No Affiliation Given Ram Srinivasan No Affiliation Given Jeffrey Stone No Affiliation Given Philip Tarpinian No Affiliation Given
Package: ML23283A050 Meeting Notice: ML23257A047 NRC Presentation Slides: ML23255A099 Meeting Summary: ML23278A137 NRC-001 OFFICE NRR/DORL/LPL2-1/PM NRR/DORL/LPL2-1/LA NRR/DRA/PLA/BC NAME ZTurner KGoldstein SVasavada DATE 10/10/2023 10/10/2023 10/10/2023 OFFICE NRR/DEX/EXHB/BC NRR/DORL/LPL2-1/BC NAME BHayes (NTiruneh for)
MMarkley (SWilliams for)
DATE 10/10/2023 10/17/2023