MONTHYEARML23180A3042023-06-28028 June 2023 Submittal of Westinghouse Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Request ML23241A0122023-09-0505 September 2023, 6 September 2023 U.S. NRC Completeness and Withholding Forms for Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Request ML23241A0172023-09-0505 September 2023 NRC 897 Withholding Form for Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other ML23241A0182023-09-0505 September 2023 NRC 898 Completeness Form for Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other ML23241A0152023-09-0606 September 2023 Transmittal Email Completeness Determination and Withholding Determination for the Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other ML24054A0462024-02-27027 February 2024 April 16, 2024, Regulatory Audit Plan for the Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Revision 0, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other ML24157A1872024-06-21021 June 2024 Transmittal Email Requests for Additional Information Westinghouse Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: RAI ML24199A2232024-07-17017 July 2024 Cover Letter Audit Report Westinghouse Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other ML24285A2052024-10-17017 October 2024 NRC 897 Withholding Form for Westinghouse Response to NRC RAI Number 1 on WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: RAI ML24285A2062024-10-17017 October 2024 Transmittal Email NRC 897 Withholding Form for Westinghouse Response to NRC RAI Number 1 on WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: RAI ML24345A0212025-02-12012 February 2025 Transmittal Email for the U.S. NRC Draft Safety Evaluation for Westinghouse Electric Company Topical Report WCAP 18773-P/NP, Revision 0, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Draft Approval ML25274A1132025-09-30030 September 2025 Submittal of WCAP-18773-P-A, Revision 0, and WCAP-18773-NP-A, Revision 0, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Request ML25274A1142025-09-30030 September 2025 Enclosure 3: WCAP-18773-NP-A, Revision 0, Higher Enrichment or Westinghouse and Combustion Engineering Fuel Designs (Non-Proprietary) Project stage: Request ML25325A1622025-11-21021 November 2025 NRC Form 896 for the U.S. Nuclear Regulatory Commission Verification for Westinghouse Electric Company Topical Report WCAP-18773-P-A, Revision 0, and WCAP-18773-NP-A, Revision 0, Higher Enrichment for Westinghouse and Combustion Engineering Project stage: Other ML25325A2192025-11-24024 November 2025 Request for Withholding Proprietary Information from Public Disclosure - Westinghouse Electric Company Topical Report WCAP-18773-P-A WCAP-18773-NP-A, Revision 0, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs Project stage: Other 2024-06-21
[Table View] |
Text
From:
Ekaterina Lenning To:
Zozula, Camille T.
Cc:
Harper, Zachary S; Christian, Rachel; Scott Krepel; Gerond George; Lois James
Subject:
COMPLETENESS DETERMINATION AND WITHHOLDING DETERMINATION FOR THE WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18773-P/NP, HIGHER ENRICHMENT FOR WESTINGHOUSE AND COMBUSTION ENGINEERING FUEL DESIGNS (EPID L 2023-TOP-0039)
Date:
Wednesday, September 6, 2023 7:28:00 AM Attachments:
NRC 898 WCAP-18773 Topical Report Completeness Determination Form.pdf NRC 897 WCAP-18773 Topical Report Withholding Determination Form.pdf Ms. Camille Zozula Manager, Infrastructure & Facilities Licensing Westinghouse Electric Company 1000 Westinghouse Drive, Building 1, Suite 165 Cranberry Township PA 16066
SUBJECT:
COMPLETENESS DETERMINATION AND WITHHOLDING DETERMINATION FOR THE WESTINGHOUSE ELECTRIC COMPANY TOPICAL REPORT WCAP-18773-P/NP, HIGHER ENRICHMENT FOR WESTINGHOUSE AND COMBUSTION ENGINEERING FUEL DESIGNS (EPIDL2023-TOP-0039)
Ms. Zozula,
Attached please find the completed forms for the U.S. Nuclear Regulatory Commission staffs completeness determination and proprietary information withholding determination for the Westinghouse Electric Company Topical Report WCAP-18773-P/NP, Higher Enrichment for Westinghouse and Combustion Engineering Fuel Designs.
If you have any questions, please feel free to contact me at 301-415-3151 or by email at Ekaterina.Lenning@nrc.gov.
Sincerely, Ekaterina Lenning Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission
Docket No.99902038
ML23241A012 (Package)
ML23241A015 (Email)
ML23241A017 (Withholding Determination NRC 897 Form)
ML23241A018 (Completeness Determination NRC 898 Form)
OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DSS/SFNB/BC NRR/DORL/LLPB/BC (A)
NAME ELenning DHarrison SKrepel GGeorge (LJames for)
DATE 8/29/2023 9/5/2023 9/5/2023 9/5/2023 OFFICE NRR/DORL/LLPB/PM NAME ELenning DATE 9/6/2023