From:
Murray, Scott P. (GE Vernova)
To:
Duane Hardesty; Geoffrey Wertz Cc:
Mcconnell, Thomas J (GE Vernova); Martinez, Carlos (GE Vernova); Smyly, Jeffrey (GE Vernova)
Subject:
[External_Sender] FW: RE: Action Request on "GEH NTR LR Issuance Package" Date:
Thursday, June 15, 2023 2:11:57 PM Attachments:
image001.png GEH NTR Appendix A Technical Specifications.docx Comments to GEH for Renewed Facility Operating License R OGC.docx I declare under penalty of perjury that this information is true and correct.
Executed on June 15, 2023 Scott Murray
From: Mcconnell, Thomas J (GE Vernova) <thomas.mcconnell@ge.com>
Sent: Thursday, June 15, 2023 1:06 PM To: Murray, Scott P. (GE Vernova) <Scott.Murray@ge.com>
Cc: Martinez, Carlos (GE Vernova) <CARLOS1.MARTINEZ@GE.com>; Smyly, Jeffrey (GE Vernova)
<Jeffrey.Smyly@ge.com>
Subject:
RE: RE: Action Request on "GEH NTR LR Issuance Package"
- Scott,
Not sure what was going on with the section numbering next time I opened the file it displayed as I wanted it to. I think my version of WORD briefly showed some already accepted changes. Please disregard my below comment on section numbering not being correct.
I agree with all the NRC suggested changes to the license document and all of J. Wachutkas suggestions in the Tech Specs.I added one additional administrative edit to Tech Spec section 3.5.1 see attached. Please attach your affirmation statement and forward to the NRC.
- Thanks, Tom
From: Murray, Scott P. (GE Vernova) <Scott.Murray@ge.com>
Sent: Thursday, June 15, 2023 9:10 AM To: Mcconnell, Thomas J (GE Vernova) <thomas.mcconnell@ge.com>
Cc: Martinez, Carlos (GE Vernova) <CARLOS1.MARTINEZ@GE.com>; Smyly, Jeffrey (GE Vernova)
<Jeffrey.Smyly@ge.com>
Subject:
RE: RE: Action Request on "GEH NTR LR Issuance Package"
Tom:
If you send me your reply e-mail first, I will add the oath and affirmation statement and send to NRC.
From: Duane Hardesty <Duane.Hardesty@nrc.gov>
Sent: Thursday, June 15, 2023 12:02 PM
To: Mcconnell, Thomas J (GE Vernova) <thomas.mcconnell@ge.com>; Murray, Scott P. (GE Vernova)
<Scott.Murray@ge.com>
Cc: Geoffrey Wertz <Geoffrey.Wertz@nrc.gov>; Martinez, Carlos (GE Vernova)
<CARLOS1.MARTINEZ@GE.com>; Smyly, Jeffrey (GE Vernova) <Jeffrey.Smyly@ge.com>
Subject:
EXT: RE: RE: Action Request on "GEH NTR LR Issuance Package"
WARNING: This email originated from outside of GE. Please validate the sender's email address before clicking on links or attachments as they may not be safe.
Please correct the numbering how you want it and submit back as a marked and clean copy in Word. The clean copy is to make sure the format, pagination, etc., will be as you expect it when we reissue the TS to you. Also, please acknowledge the OGC changes as being acceptable or making changes, if appropriate. We will take it from there.
Dont forget the affirmation statement when you return it via email.
- Thanks, Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL
From: Mcconnell, Thomas J (GE Vernova) <thomas.mcconnell@ge.com>
Sent: Thursday, June 15, 2023 11:58 AM To: Duane Hardesty <Duane.Hardesty@nrc.gov>; Murray, Scott P. (GE Vernova)
<Scott.Murray@ge.com>
Cc: Geoffrey Wertz <Geoffrey.Wertz@nrc.gov>; Martinez, Carlos (GE Vernova)
<CARLOS1.MARTINEZ@GE.com>; Smyly, Jeffrey (GE Vernova) <Jeffrey.Smyly@ge.com>
Subject:
[External_Sender] RE: Action Request on "GEH NTR LR Issuance Package"
Morning Duane,
There is still a problem with the section numbering in the Tech Specs, Chapter 4, sections 4.3 through 4.8. Do you want me to fix or can you take a shot?
Best regards,
Thomas McConnell Manager, Nuclear Test Reactor Nuclear Energy
+1 925 918 6081
From: Duane Hardesty <Duane.Hardesty@nrc.gov>
Sent: Thursday, June 15, 2023 6:49 AM To: Murray, Scott P. (GE Vernova) <Scott.Murray@ge.com>
Cc: Mcconnell, Thomas J (GE Vernova) <thomas.mcconnell@ge.com>; Geoffrey Wertz
<Geoffrey.Wertz@nrc.gov>; Martinez, Carlos (GE Vernova) <CARLOS1.MARTINEZ@GE.com>
Subject:
EXT: FW: Action Request on "GEH NTR LR Issuance Package" Importance: High
WARNING: This email originated from outside of GE. Please validate the sender's email address before clicking on links or attachments as they may not be safe.
Hi Scott:
I was reminded by Geoff that we took out Part 40 for source material because GEH had stated that they no longer had source material. As such, see the changed file for license conditions. Again, I need you to agree to these changes so that the renewal can proceed. I would appreciate if you could give these two files your immediate attention.
Kind Regards, Duane
Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL
From: Duane Hardesty Sent: Wednesday, June 14, 2023 5:58 PM To: Murray, Scott P. (GE Power) <scott.murray@ge.com>
Cc: McConnell, Thomas J (GE Power) <thomas.mcconnell@ge.com>; Martinez, Carlos (GE Power Portfolio) <Carlos1.Martinez@ge.com>; Josh Borromeo <Joshua.Borromeo@nrc.gov>; Holly Cruz (She/Her/Hers) <Holly.Cruz@nrc.gov>; Geoffrey Wertz <Geoffrey.Wertz@nrc.gov>
Subject:
FW: Action Request on "GEH NTR LR Issuance Package"
Scott:
Please find attached the OGC comments on the GEH NTR license and TS. My intention is to accept them all. The TS comments are primarily grammatical changes (punctuation, etc.)
The license are punctuation, to clarify Part 40 inclusion, or duplicative information that we wish to eliminate.
Please look these comments over. If you agree, please email me under an affirmation statement (as we did before) that these are changes you wish to be incorporated. I will then work with OGC for acceptance of the documents.
As always, please call me if you have any questions/concerns regarding any of these comments!
Kind Regards,
Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL