Submittal and Review of Licensing Topical Reports in Support of Carbon Free Power Project Combined License Application
ML23157A031
Person / Time
Site: 99902052
Issue date: 06/13/2023
From: Beverly Smith, Tabatabai-Yazdi O
NRC/NRR/DNRL, NRC/NRR/DNRL/NRLB
To: Volkoff J
NuScale
References
Download: ML23157A031 (1)


Text

June 13, 2023 Mr. John Volkoff Manager, Combined License Applications NuScale Power, LLC 1100 Circle Boulevard, Suite 200 Corvallis, OR 97330

SUBJECT:

SUBMITTAL AND REVIEW OF LICENSING TOPICAL REPORTS IN SUPPORT OF CARBON FREE POWER PROJECT COMBINED LICENSE APPLICATION

Dear Mr. Volkoff:

During recent preapplication engagements with NuScale Power, LLC (NuScale) and Carbon Free Power Project (CFPP) on topics related to emergency planning and mitigation of beyond-design-basis events, NuScale has informed the U.S Nuclear Regulatory Commission (NRC) staff that NuScale plans to submit three topical reports (TRs) that would be referenced in or support the NRC staffs review of CFPP combined license application (COLA). These TRs are titled, Emergency Action Level Scheme, On-Shift and Emergency Response Organization Staffing, and Mitigation of Beyond-Design-Basis Events. As communicated to the staff, NuScale plans to submit the TRs between August 2023 and before the end of calendar year 2023.

The NRC staff would like to note that these TRs include substantive and complex information that is necessary for the CFPP COLA review, and that these TRs may require more than a year to complete. As a result, the staff will require that each of these TRs be accepted for review before the CFPP COLA will formally be accepted for review. This guidance and criteria would also be applied to any other TRs submitted during the COLA pre-submittal timeframe that are not identified above.

Consistent with NRC practice, the review schedule and estimated staff hours for these TRs will be established at the time of acceptance and will be incorporated into the overall schedule and hours for the COLA review. If, during the technical review of any of the TRs, it is determined that their review schedules need to be extended, an evaluation on the impact to the CFPP COLA schedule will also be conducted. Thus, the timely completion of the technical reviews for each of the TRs will be essential in maintaining the review schedule for the CFPP COLA.

If you have any questions regarding this matter, please contact Mr. Omid Tabatabai, Senior Project Manager, at (301) 415-6616 or Omid.Tabatabai@nrc.gov.

Sincerely, Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No.: 99902052 cc: CFPP ListServ Brian W.

Smith Digitally signed by Brian W. Smith Date: 2023.06.13 07:42:17 -04'00'

ML23157A031

  • via email NRR-106 OFFICE DNRL/NRLB: PM DNRL/NRLB: LA DNRL/NRLB: BC DNRL: D NAME OTabatabai SGreen*

MDudek*

BSmith*